Data centre · Fingal · 53.4069, -6.3604

← All data centres

K2 Strategic Ballycoolin

operating K2 Strategic Our classification · status

18 MW
Average grid draw, 2025
up to ≈2% of the CSO data-centre total (upper bound)
277 MWth
On-site generation licensed
backup-diesel
2.8 ha
Building footprint mapped
2 buildings · OSM
€2.9m
Estimated rates a year
NAV €15.6m
2022
First completion certificate

Why we say it's operating

  • EPA P1143: on-site generators licensed and in use (Licensable Activity Commenced)
  • Valuation list: property 10029012 rated as DATA CENTRE
  • Valuation list: property 10028964 rated as DATA CENTRE
  • Valuation list: property 2194415 rated as DATA CENTRE
  • Planning FW19A/0089: completion certificate 2022-08-29

What's next on this site

  • permitted: Planning FW20A/0181: unstarted (live permission, no commencement notice) (expires 2031-01-28)

Who runs it

  • EPA licensee 'K2 Strategic Infrastructure Ireland Limited'
  • planning applicant
  • planning applicant 'K2 Strategic Infrastructure Ireland Ltd'
  • planning applicant 'K2 Strategic Infrastructure Ireland Ltd.'
  • some records attributed by co-location only (no operator in their own source)
Leaflet © OpenStreetMap contributors

Generators and power

EPA licenceStatusRoleMWthPlantPermitted hours
P1143Licensed · Licensable Activity Commencedbackup-diesel277.1232 x 8.66 MWth backup generators100 h/yr per generator

What the annual environmental reports say

YearLicenceGrid MW avgOn-site fuel GJFull-load hours
2025P114317.56330.6

* part year. Full-load hours = fuel burned ÷ the whole fleet at full load, a derived figure.

What the planning and licence documents say

K2 Dublin (Dub4/5) installation under EPA licence P1143-01 (32 generators licensed, 16 installed by 2025); grid-supplied, generators backup only; water from the 2025 AER.

SpecValueQuote and source
Connection pointexisting off-site substation (FW16A/0159), c.250 m east, shared with adjacent data centre"connection to an offsite substation (plannning reference: FW16A/0159) (approx. 250 m east of the site)" EPA P1143-01: IR-LA007230, p.4
On-site generationbackup diesel generators (run on HVO)"with 32 diesel powered back-up generators to provide power" EPA P1143-01: IR-LA007230, p.1
Generating units32 units"in total 32 no. 8.66 megawatt thermal (MWth) backup generators will be installed" EPA P1143-01: IR-LA007230, p.2
Full build-out; only 16 installed per the 2025 AER.
On-site thermal input277.1 MWth"exceed the 50 MWth threshold of Class 2.1 of the First Schedule of the EPA Act, (277.12 MWth)" EPA P1143-01: IR-LA007230, p.2
32 x 8.66 MWth.
FuelHVO (reported as diesel for ETS)"The backup generators onsite run on hydrotreated vegetable oil (HVO)" EPA P1143-01: AER 2025 - P1143-01 K2 Dublin v1.0.pdf, p.12
Running hours100 h/yr per generator"The RD limits the operation of each generator to 100 hours per year with no more than 277.12 MWth operating simultaneously" EPA P1143-01: IR-LA007230, p.13
Coolingindirect evaporative cooling (IEC) air handling units"Each data hall will utilise Indirect Evaporative Cooling (IEC) Air Handling Units (AHU)" EPA P1143-01: IR-LA007230, p.2
Water133 m3/day (derived)"Public Supply 48,432 109%" EPA P1143-01: AER 2025 - P1143-01 K2 Dublin v1.0.pdf, p.15
Derived: 48,432 m3 in 2025 / 365; only Dub4 and Dub5 operating.
Data halls4 halls (derived)"The licence is for the operation of 32 diesel back up generators (x8 per data hall)" EPA P1143-01: AER 2025 - P1143-01 K2 Dublin v1.0.pdf, p.9
Derived: 32 generators / 8 per data hall.
Phasing4 buildings planned (Dub2-5); Dub4 and Dub5 built and operating"ultimately consist of four data storage buildings (Dub2, Dub3, Dub4 and Dub5) but currently only two" EPA P1143-01: AER 2025 - P1143-01 K2 Dublin v1.0.pdf, p.9

Every value is quoted from the document and page cited; the quote was checked against that page's text. "Derived" means the reader worked it out from stated figures (shown in the quote). Planning and licence figures are design or permitted values, not measured use; values derived from an EPA annual environmental report (AER), mostly water, are reported use for that year. The note under each quote gives the scope and whether a demand figure is a maximum or an average.

Planning history

ReceivedRefWhatDecisionBuilt?
2019-06-05FW19A/0089
Demolition of two existing light industrial / commercial buildings and site clearance works (on a phased basis); Construction of two data storage facilities (both over two and three levels), to be
GRANT PERMISSIONcompleted (completion certificate)

Sources for this page

osm:way/1003253881 · osm:way/713340741 · epa:P1143 · valuation:10029012 · valuation:10028964 · valuation:2194415 · planning:FINGAL/FW19A/0089 · planning:FINGAL/FW21A/0009 · planning:FINGAL/FW20A/0181

Joined from OpenStreetMap, the planning register, An Coimisiún Pleanála, EPA licences and annual reports, the Tailte Éireann valuation list and Building Control. Data built 2026-10-10.