Data centre · Fingal · 53.4069, -6.3604
K2 Strategic Ballycoolin
operating K2 Strategic Our classification · status
Why we say it's operating
- EPA P1143: on-site generators licensed and in use (Licensable Activity Commenced)
- Valuation list: property 10029012 rated as DATA CENTRE
- Valuation list: property 10028964 rated as DATA CENTRE
- Valuation list: property 2194415 rated as DATA CENTRE
- Planning FW19A/0089: completion certificate 2022-08-29
What's next on this site
- permitted: Planning FW20A/0181: unstarted (live permission, no commencement notice) (expires 2031-01-28)
Who runs it
- EPA licensee 'K2 Strategic Infrastructure Ireland Limited'
- planning applicant
- planning applicant 'K2 Strategic Infrastructure Ireland Ltd'
- planning applicant 'K2 Strategic Infrastructure Ireland Ltd.'
- some records attributed by co-location only (no operator in their own source)






Generators and power
| EPA licence | Status | Role | MWth | Plant | Permitted hours |
|---|---|---|---|---|---|
| P1143 | Licensed · Licensable Activity Commenced | backup-diesel | 277.12 | 32 x 8.66 MWth backup generators | 100 h/yr per generator |
What the annual environmental reports say
| Year | Licence | Grid MW avg | On-site fuel GJ | Full-load hours |
|---|---|---|---|---|
| 2025 | P1143 | 17.5 | 633 | 0.6 |
* part year. Full-load hours = fuel burned ÷ the whole fleet at full load, a derived figure.
What the planning and licence documents say
K2 Dublin (Dub4/5) installation under EPA licence P1143-01 (32 generators licensed, 16 installed by 2025); grid-supplied, generators backup only; water from the 2025 AER.
| Spec | Value | Quote and source |
|---|---|---|
| Connection point | existing off-site substation (FW16A/0159), c.250 m east, shared with adjacent data centre | "connection to an offsite substation (plannning reference: FW16A/0159) (approx. 250 m east of the site)" EPA P1143-01: IR-LA007230, p.4 |
| On-site generation | backup diesel generators (run on HVO) | "with 32 diesel powered back-up generators to provide power" EPA P1143-01: IR-LA007230, p.1 |
| Generating units | 32 units | "in total 32 no. 8.66 megawatt thermal (MWth) backup generators will be installed" EPA P1143-01: IR-LA007230, p.2 Full build-out; only 16 installed per the 2025 AER. |
| On-site thermal input | 277.1 MWth | "exceed the 50 MWth threshold of Class 2.1 of the First Schedule of the EPA Act, (277.12 MWth)" EPA P1143-01: IR-LA007230, p.2 32 x 8.66 MWth. |
| Fuel | HVO (reported as diesel for ETS) | "The backup generators onsite run on hydrotreated vegetable oil (HVO)" EPA P1143-01: AER 2025 - P1143-01 K2 Dublin v1.0.pdf, p.12 |
| Running hours | 100 h/yr per generator | "The RD limits the operation of each generator to 100 hours per year with no more than 277.12 MWth operating simultaneously" EPA P1143-01: IR-LA007230, p.13 |
| Cooling | indirect evaporative cooling (IEC) air handling units | "Each data hall will utilise Indirect Evaporative Cooling (IEC) Air Handling Units (AHU)" EPA P1143-01: IR-LA007230, p.2 |
| Water | 133 m3/day (derived) | "Public Supply 48,432 109%" EPA P1143-01: AER 2025 - P1143-01 K2 Dublin v1.0.pdf, p.15 Derived: 48,432 m3 in 2025 / 365; only Dub4 and Dub5 operating. |
| Data halls | 4 halls (derived) | "The licence is for the operation of 32 diesel back up generators (x8 per data hall)" EPA P1143-01: AER 2025 - P1143-01 K2 Dublin v1.0.pdf, p.9 Derived: 32 generators / 8 per data hall. |
| Phasing | 4 buildings planned (Dub2-5); Dub4 and Dub5 built and operating | "ultimately consist of four data storage buildings (Dub2, Dub3, Dub4 and Dub5) but currently only two" EPA P1143-01: AER 2025 - P1143-01 K2 Dublin v1.0.pdf, p.9 |
Every value is quoted from the document and page cited; the quote was checked against that page's text. "Derived" means the reader worked it out from stated figures (shown in the quote). Planning and licence figures are design or permitted values, not measured use; values derived from an EPA annual environmental report (AER), mostly water, are reported use for that year. The note under each quote gives the scope and whether a demand figure is a maximum or an average.
Planning history
| Received | Ref | What | Decision | Built? |
|---|---|---|---|---|
| 2019-06-05 | FW19A/0089 | Demolition of two existing light industrial / commercial buildings and site clearance works (on a phased basis); Construction of two data storage facilities (both over two and three levels), to be | GRANT PERMISSION | completed (completion certificate) |
Sources for this page
osm:way/1003253881 · osm:way/713340741 · epa:P1143 · valuation:10029012 · valuation:10028964 · valuation:2194415 · planning:FINGAL/FW19A/0089 · planning:FINGAL/FW21A/0009 · planning:FINGAL/FW20A/0181
Joined from OpenStreetMap, the planning register, An Coimisiún Pleanála, EPA licences and annual reports, the Tailte Éireann valuation list and Building Control. Data built 2026-10-10.