Policy · CRU2025236

The CRU's data-centre connection rules, explained

The CRU's Large Energy Users Connection Policy (CRU2025236, 12 December 2025) applies only to data centres. Sites of 10 MVA or more must bring new dispatchable generation or storage at least equal to their grid import capacity, and match at least 80% of annual demand with new Irish renewables within six years. A judicial review was lodged in March 2026.

Updated 10 October 2026 · data build 2026-10-10 · how we know · corrections

The four rules

Figure 1

The path a new data centre must take since December 2025

A new data centre now comes as a package: its own dispatchable power sized to its grid import, 80% of its demand matched by new Irish renewables, a location the grid can take, and, from 27 Oct 2026, equipment that rides through faults.

Decision tree: connection rules for a new data centre in IrelandA new data centre asks for a grid connection. Is it a data centre?. ≥ 10 MVA: Bring your own power; < 10 MVA: Small sites. DUBLIN: In Dublin; OUTSIDE DUBLIN: Elsewhere. 80% new Irish renewables. Stay on through grid faults. If its gas plant sits behind its own meter. A connection offer.STARTA new data centre asks for a grid connectionTransmission (EirGrid) or distribution (ESB Networks).SCOPE · CRU RULE 4Is it a data centre?Called a Large Energy User policy, but it applies only to data centres. If it isn't, these rules don't apply.≥ 10 MVA< 10 MVACRU RULE 1 · ≥10 MVABring your own powerData centres of 10 MVA or more need dispatchablegeneration or storage, on site or nearby, withde-rated capacity at least equal to their grid importcapacity (MIC). It must take part in the wholesalemarket.CRU RULE 2 · <10 MVASmall sitesFrom 1 MVA to below 10 MVA, an autoproducer unitcovering 100% of the site's import capacity. Below 1MVA the policy does not apply.DUBLINOUTSIDE DUBLINDCCOPP V3 · 20 MAY 2026In DublinDublin declared fully constrained. In Dublin therequired on-site gas generation itself worsensshort-circuit levels, so the policy cannot work thereuntil 400 kV reinforcement.LOCATIONElsewherePerhaps 150-300 MW possible in the west, realisticallyfrom the mid-2030s.CRU RULE 3 · 80% RENEWABLES80% new Irish renewablesNew data centres must match at least 80% of annual demand with additional renewable electricity generated in theRepublic of Ireland (CPPA or own build), within a 6-year glide path from energisation. Generation contracted underREFIT/RESS/ORESS does not count; full repowering can.NEW SINCE 22 SEP 2026 · MPID 345Stay on through grid faultsFrom 27 Oct 2026 every transmission-connected site must ride through faults, withstand ±1 Hz/s and recover 90% ofits demand within 500 ms.PROPOSED · CRU202657If its gas plant sits behind its own meterGas for it would be interruptible. Exempt: Gas-fired generators participating in the SEM, including data-centredispatchable generation that is separately connected and metered under the LEU policy (CRU2025236).OUTCOMEA connection offerOffered at the applicant's own risk while the judicial review lodged on 10 Mar 2026 is pending.
Decision tree: connection rules for a new data centre in IrelandA new data centre asks for a grid connection. Is it a data centre?. ≥ 10 MVA: Bring your own power; < 10 MVA: Small sites. DUBLIN: In Dublin; OUTSIDE DUBLIN: Elsewhere. 80% new Irish renewables. Stay on through grid faults. If its gas plant sits behind its own meter. A connection offer.STARTA new data centre asks for a grid connectionTransmission (EirGrid) or distribution (ESB Networks).SCOPE · CRU RULE 4Is it a data centre?Called a Large Energy User policy, but it applies onlyto data centres. If it isn't, these rules don't apply.≥ 10 MVA< 10 MVACRU RULE 1 · ≥10 MVABring your own powerData centres of 10 MVA ormore need dispatchablegeneration or storage, onsite or nearby, withde-rated capacity atleast equal to their gridimport capacity (MIC). Itmust take part in thewholesale market.CRU RULE 2 · <10 MVASmall sitesFrom 1 MVA to below 10MVA, an autoproducer unitcovering 100% of thesite's import capacity.Below 1 MVA the policydoes not apply.DUBLINOUTSIDE DUBLINDCCOPP V3 · 20 MAY 2026In DublinDublin declared fullyconstrained. In Dublinthe required on-site gasgeneration itself worsensshort-circuit levels, sothe policy cannot workthere until 400 kVreinforcement.LOCATIONElsewherePerhaps 150-300 MWpossible in the west,realistically from themid-2030s.CRU RULE 3 · 80% RENEWABLES80% new Irish renewablesNew data centres must match at least 80% of annualdemand with additional renewable electricity generatedin the Republic of Ireland (CPPA or own build), withina 6-year glide path from energisation. Generationcontracted under REFIT/RESS/ORESS does not count; fullrepowering can.NEW SINCE 22 SEP 2026 · MPID 345Stay on through grid faultsFrom 27 Oct 2026 every transmission-connected site mustride through faults, withstand ±1 Hz/s and recover 90%of its demand within 500 ms.PROPOSED · CRU202657If its gas plant sits behind its own meterGas for it would be interruptible. Exempt: Gas-firedgenerators participating in the SEM, includingdata-centre dispatchable generation that is separatelyconnected and metered under the LEU policy(CRU2025236).OUTCOMEA connection offerOffered at the applicant's own risk while the judicialreview lodged on 10 Mar 2026 is pending.

The CRU's decision of 12 Dec 2025 (CRU/2025/236) replaced an open-ended pause with conditions. A site of 10 MVA or more must bring dispatchable generation or storage, de-rated to at least its import capacity and bidding into the market; a smaller one needs an autoproducer covering all its import capacity; and at least 80% of annual demand must be matched by new, unsubsidised renewables in Ireland. EirGrid's connection policy then treats Dublin as fully constrained, the Grid Code adds fault ride-through from 27 Oct 2026, and the CRU has proposed (no decision yet) that gas for plant behind a data centre's own meter be interruptible, while separately metered plant bidding into the market is exempt. The red-edged steps were added after the decision.

Sources: CRU/2025/236 decision, 2025-12-12 · EirGrid DCCOPP v3, 2026-05-20 · CRU2026145 (MPID 345), 2026-09-22 · CRU202657 (proposed), 2026-06-25 · Judicial review (policy timeline), 2026-03-10

01

Bring your own power

Data centres of 10 MVA or more need dispatchable generation or storage, on site or nearby, with de-rated capacity at least equal to their grid import capacity (MIC). It must take part in the wholesale market.
02

Small sites

From 1 MVA to below 10 MVA, an autoproducer unit covering 100% of the site's import capacity. Below 1 MVA the policy does not apply.
03

80% new Irish renewables

At least 80% of annual demand matched by additional renewable projects generating in Ireland.
04

Data centres only

Called a Large Energy User policy, but it applies only to data centres.

CRU decision paper CRU2025236, 12 December 2025.

What it means, and for whom

Applies only to data centres of 1 MVA or more. Sites of 1-10 MVA need an autoproducer unit covering their MIC; 10 MVA and above need new, separately metered dispatchable generation/storage on-site or 'proximate', de-rated to at least their MIC and bidding into the market, and cannot energise or ramp until it is delivered. All must meet at least 80% of annual demand with additional, unsubsidised Irish renewables within six years of energisation or lose MIC. Location still decides; supersedes CRU/21/124 for new applications.

What changed. Ended the open-ended near-moratorium with a defined, demanding route: a data centre now comes as a package of demand plus a gas plant (or storage) plus new wind/solar PPAs. No change for gas connections; an interruptible gas product is to be consulted on separately. SOs had to publish processes by 31 March 2026.

DevelopersViable only for well-capitalised players able to co-develop generation and contract new renewables; worked example: a 30 MVA site needs about 31 MW of gas turbine plus about 55 MW of onshore wind (p65). Wind barely reduces the firm requirement because of its low de-rating (0.056).
Energy suppliersNew market for data-centre-linked gas peakers and batteries (1-year capacity contracts only) and for CPPAs with new unsubsidised wind/solar; RESS/ORESS projects excluded.
PublicData centres pay for their own adequacy and add renewables, but new gas plants are built and run, and up to 100% fossil supply is allowed in the first six years. Judicial review lodged March 2026.

Since the decision

2026-01-13Large Energy User Action Plan (LEAP)
17 actions for a plan-led approach after 2030: Green Energy Parks that co-locate big users with renewables, storage and dispatchable generation; a National Planning Statement on parks; flexible/non-firm connections; private-wire legislation; LEU efficiency reporting under the EED; an annual data-centre roundtable. Confirms grid investment to 2030 makes no room for data centres beyond existing contracts and that Dublin opportunities are extremely limited.
2026-03-10Judicial review lodged against CRU2025236
Three environmental groups sought leave in the High Court to quash the LEU decision, arguing it breaches the Climate Act and the Energy Efficiency Directive by allowing new data centres to run on fossil power for six years and leaving 20% unmatched, with back-up generator emissions ignored.
2026-05-20DCCOPP v3, Data Centre Technical Assessment and Constrained Area Overview
Implements CRU2025236 for transmission connections: a mandatory pre-application meeting (only for projects outside constrained areas), a three-part application (data centre + nominated generation + nominated renewables, each through ECP-GSS), 7.5 to 18 months to an offer, and MIC cuts or termination if generation or the 80% renewables test fails. The overview declares greater Dublin 'fully constrained' and estimates only 50-100 MW at each of Galway, Limerick and Cork on 220 kV, realistically from the mid-2030s.
2026-06-25CRU202657: proposed direction on interruptible gas connections
CRU is minded to direct GNI to make all new gas connections above 50 MWth interruptible, for a tariff discount, because 17 pending applications (5,466 MWth, mostly data centres and generators) would turn the 1-in-50 winter peak-day headroom (10%) into a 9% deficit by 2033, or an 18% deficit under GNI's risk-adjusted case (from 3% headroom). Market (SEM) generators, including separately metered data-centre generation under the LEU policy, are exempt; behind-the-meter data-centre gas would be interruptible.

Is there enough renewable power to match?

4.16 TWh
New renewables needed a year for 80% of demand growth to 2034
≈ 1.6 GW onshore wind
5.98 TWh
Permitted wind and solar with no state contract
4.4 GW · planning
1,909 MW
Corporate PPAs announced by data-centre operators
17 deals in the Republic

The supply gap, TWh a year

Needed: 80% of demand growth to 20344.16
Permitted, uncontracted wind + solar5.98
…of which onshore wind3.67

Assumed capacity factors: wind 30%, solar 11% (curtailment not deducted). Plants with state support (RESS/REFIT) can't count. Pool MW is mostly estimated from turbine counts and site area. "Growth" is EirGrid's 2025 → 2034 forecast (9.4 → 14.6 TWh, as cited in CRU2025236), one basis throughout; the CSO's metered 2025 figure (7.662 TWh) is lower and not comparable.

Corporate PPAs by buyer (MW)

Microsoft967
Amazon (AWS)334
Meta276
Facebook (Meta)179
Unnamed 'leading technology company'81
Google58
Keppel DC REIT14

No announced PPAs found for Equinix, Digital Realty, CyrusOne, EdgeConneX, Vantage or Echelon. Older deals serve existing sites and don't count toward the new rule.

For a renewable developer: permitted onshore wind without a state contract is the scarce product. The 4.16 TWh need is more than all of it (about 1.4 GW, ≈3.7 TWh a year); solar would have to fill the rest.

Annual vs hourly matching

A portfolio sized to meet Ireland's rule exactly (80% of annual energy, 80/20 wind/solar) matches about 70% of a flat load hour by hour, and covers 80% of load in only 50% of hours, so under Spain's draft it would fall in the top hourly-surcharge band in 12 of 12 months. Reaching 80% hourly-matched needs about 1.2x the load's annual energy in contracted output (1.5x what Ireland's rule requires); passing Spain's per-hour test in every hour is not reachable with wind and solar alone (even 3x gives 89% of hours).

MixContracted output, % of annual loadLoad matched hour by hourHours ≥80% covered (Spain's test)
wind only80%65.3%45.4%
80% wind / 20% solar80%69.5%50.1%
80% wind / 20% solar100%76.1%59.9%
80% wind / 20% solar150%84.9%74.2%
80% wind / 20% solar200%89.5%81.4%
80% wind / 20% solar300%93.9%89.2%
RuleMatchingThresholdStatus
IE CRU/2025/236 (decision, 12 Dec 2025)annualat least 80% of annual demandin force (connection policy); judicial review pending
ES Draft Royal Decree on data-centre sustainability and digital sovereignty (MITECO, urgent procedure)hourly80% of total consumption from additional renewables (Art. 8) AND each hour at least 80% backed by renewables generated in that hour (Art. 9)draft; public consultation 27 Aug-4 Sep 2026; final adoption not found as of 3 Oct 2026 (unchecked beyond press search)
DE EnEfG s.11(5) (in force since Nov 2023)annual balance ('bilanziell')50% from 1 Jan 2024, 100% from 1 Jan 2027in force

Flat 24/7 load; portfolio shaped like the national wind and solar fleet (EirGrid actual output, 2025-10 to 2026-09). The fleet is smoother than any single portfolio, so real figures would be lower. Spain's rule is a draft.

Could any operator pass an 80%-every-hour test today? model

Modelled on public data, none of the 6 operators with EPA-reported loads would pass an 80%-every-hour test today. Best placed on paper (every announced ROI deal counted as if fully built): Microsoft (70% of hours, 132% annual cover; counting only deals marked fully operational, 0% of hours and 13% cover, as 900 of its 967 MW are partly built, under construction or framework deals), Meta (32% of hours, 62% annual cover), Google (13% of hours, 25% annual cover). Passing every hour needs firm low-carbon supply close to 80% of load (77-81% after rounding) even with contracts topped up to 2x the load's energy and a 4-hour battery (still 86-88% of hours pass). With storage alone, a battery of 0.8x load would need about 121-126 hours (about 5 days) of storage: the longest Irish wind-and-solar lull sets the size.

Operator (EPA-licensed sites)Load 2025Irish CPPAsAnnual coverHours ≥80%Extra MW for 80% hourly-matchedFirm low-carbon MW to pass every hour
Amazon (AWS)425 MW334 MW24%0%1,781333
Microsoft154 MW967 MW
67 operating
132%
13% operating
70%
0% operating
0121
Meta135 MW455 MW62%32%365106
Google26 MW58 MW25%13%12220
Equinix19 MW0 MW0%0%9815
K2 Strategic18 MW0 MW0%0%9314

Estimates from a model, not site data: no hourly site loads or PPA outputs are public. Load = 2025 grid electricity in EPA annual reports, assumed flat; CPPAs = announced Irish deals by buyer at assumed capacity factors (wind 30%, solar 11%), shaped like the national fleet; the main figures count every announced deal as if built, and the grey "operating" line counts only deals marked fully operational (the truth for partly built portfolios lies between). 0% means no announced Irish CPPA was found, not that the operator buys no renewable power. Extra MW = new 80/20 wind/solar contracts. Firm MW assumes contracts topped up to 2× the load's energy plus a 4-hour battery of half the load. On-site gas engines are firm but not renewable, so they do not count; no campus document states an on-site battery. Spain's additionality rule is not applied.

PlanSight planning · EirGrid RESS 1–5 · company and developer announcements · CRU2025236 · MITECO draft decree (Aug 2026) · EnEfG §11 · EirGrid Smart Grid Dashboard · as of 2026-10-10

Questions people ask

What does a 30 MVA data centre need under the rules?
The CRU's own worked example: about 31 MW of gas turbines on or near the site, plus about 55 MW of new onshore wind under contract (CRU2025236, p65).