Power · demand and forecasts
How much electricity does Ireland use?
Ireland's grid carried 35.6 TWh in the 12 months to 9 October 2026, an average of 4,064 MW, peaking at 5,912 MW on 5 January 2026 (EirGrid 15-minute data). Data centres were 22.1% of 2025 demand (CSO, Ember); EirGrid forecasts their use rising from 9.4 to 14.6 TWh by 2034.
Updated 10 October 2026 · data build 2026-10-10 · how we know · corrections
Why the grid now limits data centres
Why the grid can only lose 900 MW at once
In a voltage dip data centres can drop off the grid in milliseconds. EirGrid plans for a worst case in which 90% of their demand goes at once (recorded faults dropped 16–52%), so about 1,000 MW of data centres fills the 900 MW limit, and that happened in Jun 2026.
When a fault dips the voltage, data centres protect their servers by switching to on-site batteries and generators, so their demand can vanish from the grid in milliseconds and frequency jumps. EirGrid's weekly operating rules cap the demand and exports the system can lose in one event at 900 MW; planning for 90% of data-centre demand at risk, roughly 1,000 MW of data centres uses it all, and EirGrid told the CRU that peak was reached in late June 2026. To stay inside the limit EirGrid keeps more spinning plant on (inertia floor 28,000 MWs), caps the instantaneous share of wind, solar, batteries and HVDC imports (SNSP) at 75%, limits battery charging and cuts interconnector exports. The step sketches are schematic, not measured traces.
Estimate"A 100 MW campus adds about 90 MW" is our arithmetic with EirGrid's 90% assumption.
Sources: EirGrid/SONI Weekly Operational Constraints Update, week 42 2026, 2026-10-09 · CRU202704 (EirGrid figures: ~1,000 MW peak, 90% drop, limit reached), 2026-07-08 · CRU202705, EirGrid FRT update, 2026-06-26 · CRU/2025/236 s.5.1.7, 2025-12-12
Each fault takes more data-centre demand off the grid
The demand lost in a single fault has grown from 74 MW in Jan 2022 to 480 MW in Jun 2026, 53% of the 900 MW the grid can lose at once.
Each bar is one grid fault in which data centres disconnected, as listed by EirGrid in the CRU's July 2026 paper. The drop grew from 74 MW (16% of data-centre demand) in 7 Jan 2022 to 480 MW (52%) on 6 Jun 2026, because, on these figures, there is more data-centre demand and a larger share of it lets go. All five were single-phase faults; EirGrid estimates that up to 90% of data-centre demand could drop off in certain credible faults, and plans the limit around that figure. The dashed outlines show the data-centre demand each percentage implies.
EstimateImplied data-centre demand at the time = MW dropped ÷ share dropped (our arithmetic).
Sources: CRU202704 Table 1 (EirGrid fault ride-through events), 2026-07-08 · EirGrid/SONI Weekly Operational Constraints Update, week 42 2026, 2026-10-09
The grid, every 15 minutes
A typical day: demand by hour (MW)
Data-centre load is drawn as a flat band at its 2025 average (CSO 7.7 TWh ÷ 8,760 hours). It runs all night, which is why Ireland's overnight floor is so high.
Wind share and imports by month
Wind as a share of demand. Imports are net over the EWIC and Greenlink interconnectors to Britain.
EirGrid Smart Grid Dashboard, Republic of Ireland, 15-minute data 2025-10-10 to 2026-10-09 · operational, not settled, figures
The Republic now imports power around the clock
In 2020 the Republic exported power overnight. Over the last 12 months it imported in every hour of the average day, and on still winter evenings it imports more than the two cables to Wales can carry (1,219 MW on average against 1,004 MW); the rest comes over the North–South line or is measurement difference.
The lines show average net imports into the Republic for each hour of the day: dashed for 2020, red for 2025-10-10 to 2026-10-09. The 2020 day dipped to about -304 MW (exporting) at night; the recent day never falls below 524 MW and peaks at 877 MW. The Republic was a net importer in 40.1% of quarter-hours in 2020 and 89.4% in 2025. When the wind is low imports average 1,045 MW, and on still winter evenings both cables to Wales were importing at 95% of their rating or more in 95.0% of quarter-hours (a small sample: 219 quarter-hours, about 55 hours).
EstimateNet import = system demand minus Irish generation each quarter-hour, so it includes the North–South line and metering mismatch.
Sources: EirGrid Smart Grid Dashboard, 15-minute demand and generation (operational data), 2026-10-10 · Link ratings: EirGrid/SONI AIRAA 2026–2035 (EWIC), CRU Greenlink review, 2025
Data centres' part of demand
CSO MEC02, updated 2026-07-07.
What EirGrid has forecast for data centres
| Edition | Published | Measure | Forecast |
|---|---|---|---|
| GCS 2019-2028 | 2019 | data centres' share of Ireland's demand, median | 29% by 2028 |
| GCS 2021-2030 | 2021 | data centres' share of demand, median (high: 30%, per CRU/21/124 p17) | 23% by 2030 |
| EirGrid letter to CRU | 2021-05-27 | data centres' share of demand, median / high, latest forecast | 25% / 33% by 2030 |
| Government Statement | 2022-07-27 | if all contracted capacity connected | 25-33% by 2030 |
| GCS 2023-2032 | 2024-01 | data centres and new large energy users, median | 30% by 2032 |
| CRU202504 (citing EirGrid) | 2025-02-18 | data-centre and new tech load demand | 7.1 TWh (21%) in 2023 to 13.3 TWh (30%) in 2032 |
| AIRAA 2026-2035 | 2025 (freeze 30 Jun 2025) | data centres and new tech loads share of demand, median; MVA 2024 to 2035 | 32% by 2030; 959 MVA to 1,870 MVA by 2035 |
Each forecast as published; earlier editions over-shot or under-shot as the connection rules changed.