Statistics · every number sourced and dated
Data centres in Ireland: the numbers
The headline numbers: data centres used 7.7 TWh in 2025, 23.2% of Ireland's metered electricity (CSO, published 7 July 2026); 55 campuses are operating and 7 under construction (StackPath directory, Oct 2026); and licensed sites used 1.05 billion litres of public water in 2025 (EPA reports). Every figure below has its source and date.
Updated 10 October 2026 · data build 2026-10-10 · how we know · corrections
Where Ireland's electricity growth went
Since 2015, metered electricity use grew by 8,388 GWh, and data centres account for 77% of that growth.
Each bar is all electricity measured by meters in Ireland in one year: red is data centres, grey is homes, businesses and industry combined. Data centres went from 1,240 GWh (5%) in 2015 to 7,662 GWh (23.2%) in 2025, while everyone else added 1,966 GWh. The share of growth is our arithmetic on the CSO series. The SEAI, measuring all electricity demand rather than metered use, puts data centres at 88.2% of demand growth from 2015 to 2024.
Sources: CSO, Data Centres Metered Electricity Consumption (MEC02), 7 Jul 2026 · SEAI, Energy in Ireland 2025, Dec 2025
Every headline number
Values are read from the data build at render time. Estimates are labelled as ours; competitor and press figures are on the pages linked.