Scenarios · 2026–2032 · a model, not a forecast

Irish data centres in 2032: four possible futures

By 2032 Irish data centres could use between 6.7 and 27.6 TWh of electricity a year, 20–50% of metered electricity, against 7.7 TWh (23.2%) in 2025 (CSO). Even with no new grid connections, use reaches 12.9 TWh as contracts signed before 2021 fill. StackPath scenario model, 10 October 2026: scenarios, not forecasts.

Updated 10 October 2026 · data build 2026-10-10 · how we know · corrections

The four futures Scenario

Data centres' share of Ireland's metered electricity in 2032 · the tick on each bar is 2025, measured (23.2%)

Frozen. Nothing new connects to the grid. Operators fill contracts signed before 2021, mostly with denser AI racks on existing Dublin campuses.

How it gets there

  1. 2026Contracts signed before 2021 fill up: +595 MW of average load by 2032
  2. —No new grid connections for data centres
Everything Frozen assumes

Legacy (pre-2021) contracts only: ~600 MW of the 1.0-1.4 GW unused headroom fills by 2032, mostly AI densification in existing Dublin campuses. No new connections under CRU/2025/236; offshore merchant projects slip past 2032.

  • Legacy contract holders (Amazon, Microsoft, Meta and pre-2021 colocation) fill ~600 MW of 1.0-1.4 GW unused headroom, mostly by densifying with AI racks (12.87 TWh by 2032).
  • The grid copes with a DC peak ~1,543 MW in 2032 (3 MW above EirGrid's AIRAA median path) without new firm-capacity obligations, because legacy contracts are exempt from bring-your-own-power.
  • The electricity sector still overshoots its 2026-30 budget (27.0 Mt vs 20 Mt) because renewables build stays at its recent pace.
  • Little new AI capacity is built in Ireland: new hyperscale AI campuses go elsewhere (recent announcements: Spain, Finland, Denmark, Portugal).
0102030405060%← MEASURED · 2025: 23.2%SCENARIOS →Every Irish home combined, 2025: 27.5%2015: 5% (CSO, measured)2016: 5.8% (CSO, measured)2017: 6.8% (CSO, measured)2018: 8.2% (CSO, measured)2019: 9.4% (CSO, measured)2020: 11.2% (CSO, measured)2021: 14.1% (CSO, measured)2022: 17.7% (CSO, measured)2023: 20.7% (CSO, measured)2024: 21.9% (CSO, measured)2025: 23.2% (CSO, measured)Decline: 19.8% in 2032Managed growth: 40% in 2032AI hub: 50.4% in 2032Frozen: 32.2% in 2032Frozen, 2026: 24.8%Frozen, 2027: 26.3%Frozen, 2028: 27.8%Frozen, 2029: 29%Frozen, 2030: 30.1%Frozen, 2031: 31.2%Frozen, 2032: 32.2%50.4%AI hub · 27.6 TWh40%Managed growth · 18.1 TWh32.2%Frozen · 12.9 TWh19.8%Decline · 6.7 TWh20152020202520302032

Measured: CSO MEC02, to 2025 · scenarios: StackPath model, Oct 2026 · shaded band = the range of the four futures · click a line to pick it

What Frozen would mean by 2032

Electricity used, 203212.9 TWh

1.7× what they used in 2025, and 1.4× what every Irish home used that year.

CSO MEC02, 2025; scenario model

Share of Ireland's metered electricity32.2%

About 3 in every 10 units metered in Ireland, against 23.2% in 2025.

CSO MEC02; other demand grows 1% a year (assumption)

Spare gas capacity used, coldest dayGas Networks Ireland plans for a cold, still 1-in-50 winter day, when gas plants run hardest. The CRU's best estimate leaves 10% spare capacity on that day to 2032/33 (CRU202657). This counts only data-centre load above what EirGrid already expects (its median forecast), assuming the gas forecast includes that.0%

No load above what EirGrid already expects, so no extra call on spare capacity. Data centres would burn 17.1% of the gas used that day.

GNI Winter Outlook 2025/26; CRU202657; scenario model

Electricity-sector CO₂, 2026–30The Government's sectoral emissions ceilings (2022) cap the electricity sector at 20 million tonnes of CO₂ over 2026–30, about 4 Mt a year. It emitted 6.3 Mt in 2025 (EPA, provisional). Data centres' share is worked out from their share of demand.27 Mt

35% over the sector's ceiling. Every future overshoots, the lowest by 15%: data centres decide by how much. Their own share: 7.1 Mt.

Sectoral Emissions Ceilings 2022; EPA 2025; scenario model

Unsubsidised wind and solar used upThe CRU's 80% rule (CRU/2025/236): a new data centre must match 80% of its yearly use with new Irish renewables that get no State support. This is the share of the wind and solar already permitted without support (about 6 TWh a year, PlanSight, 3 Oct 2026) that data centres would need to contract.0%

None needed: nothing new connects, and contracts signed before 2021 are exempt from the 80% rule.

CRU/2025/236; PlanSight permitted pool; scenario model

Construction workers at the peak7,615

53% of the 2020 peak (14,300 direct construction jobs).

DETE/KPMG, Jun 2026 (55 jobs per MW built); scenario model

€128mcouncil rates a year by 2032, against an estimated €73m in 2025
4,888direct operating jobs in 2032, against about 3,300 in 2024 (KPMG)
€22bninvested to grow, 2026–32, before refreshing today's servers; cost per MW unchecked
+68%by 2032 even if nothing new connects (Frozen): contracts signed before 2021 still have room to fill.
4 of 4futures break the electricity sector's 2026–30 carbon ceiling of 20 Mt (22.9 to 29.2 Mt).
6.7–27.6 TWhthe range in 2032. New connections under the CRU's rules make up 63% of the gap between Decline and AI hub.

Where the growth comes from Scenario

In Managed growth, 50% of the increase (5.2 of 10.5 TWh) comes from contracts signed before 2021, which need no new connection. In Frozen, all of it does.

Used in 2025Lost by 2032Contracts signed before 2021Energy parks (new, CRU rules)AI campuses (new)

TWh in 2032. The model adds average load (MW) in each segment each year; we split each future's change from 2025 in proportion. Energy parks and AI campuses are new connections, so each must bring its own power and new renewables under CRU/2025/236.

Year by year: Frozen Scenario

Firm power: the peak, and who covers it

The peak reaches 1,543 MW by 2032, 3 MW above EirGrid's expected path. Contracts signed before 2021 don't have to bring their own power.

MW01,0002,000’26’27’28’29’30’31’322026, Data-centre peak: 1,0132027, Data-centre peak: 1,1072028, Data-centre peak: 1,2022029, Data-centre peak: 1,2912030, Data-centre peak: 1,3752031, Data-centre peak: 1,4592032, Data-centre peak: 1,5432026, EirGrid's expected path (median): 1,0682027, EirGrid's expected path (median): 1,1472028, EirGrid's expected path (median): 1,2262029, EirGrid's expected path (median): 1,3042030, EirGrid's expected path (median): 1,3832031, EirGrid's expected path (median): 1,4622032, EirGrid's expected path (median): 1,540
Own plant new sites must bringData-centre peakEirGrid's expected path (median)

EirGrid AIRAA 2026–35 (959 MVA in 2024, 1,870 MVA median in 2035); CRU/2025/236

Gas on a 1-in-50 winter day

Data centres would burn 17.1% of the gas used on that day by 2032 (12% in 2026). No call on spare capacity: load stays within EirGrid's expected path.

% of spare capacity0%100%200%’26’27’28’29’30’31’32all the spare capacity: 2026 100%, 2027 100%, 2028 100%, 2029 100%, 2030 100%, 2031 100%, 2032 100%
Spare capacity usedall the spare capacity

GNI Winter Outlook 2025/26 (325.5 GWh/day); CRU202657 (10% spare, best estimate)

The 80% renewables rule

Not needed: nothing new connects, and contracts signed before 2021 are exempt.

No requirement in this future.

CRU/2025/236 s.3.5; PlanSight permitted pool; EirGrid ORESS 1 yields

Electricity-sector CO₂ against its ceiling

27 Mt over 2026–30 against a 20 Mt ceiling, 35% over. Data centres' grid share is 7.1 Mt, plus 0.54 Mt from their own gas plant.

Mt CO₂ a year05102026, Data centres' share (grid): 1.42026, Rest of the electricity sector: 4.5’262027, Data centres' share (grid): 1.52027, Rest of the electricity sector: 4.4’272028, Data centres' share (grid): 1.42028, Rest of the electricity sector: 3.8’282029, Data centres' share (grid): 1.42029, Rest of the electricity sector: 3.7’292030, Data centres' share (grid): 1.52030, Rest of the electricity sector: 3.6’302031, Data centres' share (grid): 1.52031, Rest of the electricity sector: 3.5’312032, Data centres' share (grid): 1.52032, Rest of the electricity sector: 3.4’32ceiling (2031–32 assumed): 2026 4, 2027 4, 2028 4, 2029 4, 2030 4, 2031 3, 2032 3
Data centres' share (grid)Rest of the electricity sectorceiling (2031–32 assumed)

Sectoral Emissions Ceilings 2022; EPA 2025 (6.3 Mt); 2031–35 ceilings not yet set

Investment each year

€22bn to grow over 2026–32, 50% of it IT hardware, nearly all imported. Refreshing today's servers adds €17.3bn.

€bn a year€0bn€2bn€4bn2026, IT hardware: €1.7bn2026, Buildings: €1.7bn’262027, IT hardware: €1.7bn2027, Buildings: €1.7bn’272028, IT hardware: €1.7bn2028, Buildings: €1.7bn’282029, IT hardware: €1.6bn2029, Buildings: €1.6bn’292030, IT hardware: €1.5bn2030, Buildings: €1.5bn’302031, IT hardware: €1.5bn2031, Buildings: €1.5bn’312032, IT hardware: €1.5bn2032, Buildings: €1.5bn’32
IT hardwareBuildingsGrid and own plantRenewables

DETE/KPMG building cost per MW; hardware, grid and generation costs per MW unchecked

Jobs

Construction peaks at 7,615 direct jobs. Direct operating jobs reach 4,888 by 2032.

direct jobs010k20k2026, Construction (direct): 8k’262027, Construction (direct): 8k’272028, Construction (direct): 8k’282029, Construction (direct): 7k’292030, Construction (direct): 7k’302031, Construction (direct): 7k’312032, Construction (direct): 7k’322020 construction peak: 2026 14k, 2027 14k, 2028 14k, 2029 14k, 2030 14k, 2031 14k, 2032 14k2026, Operating (direct): 3k2027, Operating (direct): 4k2028, Operating (direct): 4k2029, Operating (direct): 4k2030, Operating (direct): 4k2031, Operating (direct): 5k2032, Operating (direct): 5k
Construction (direct)Operating (direct)2020 construction peak

DETE/KPMG, Jun 2026: 55 construction and 1.8–2.1 operating jobs per MW; 2020 peak 14,300

What breaks first Scenario

The carbon ceiling breaks first, in every future, from 2026, whatever data centres do. After that: Decline nothing else breaks; Frozen nothing else breaks; Managed growth passes the 2020 construction peak in 2029; AI hub passes the 2020 construction peak in 2028, then the 80% renewables rule in 2029, then spare gas capacity in 2030.

LimitLineDeclineFrozenManaged growthAI hub
Electricity-sector CO₂, 2026–3020 Mt ceiling22.9 Mtcrossed 202627 Mtcrossed 202627.2 Mtcrossed 202629.2 Mtcrossed 2026
Spare gas capacity used, 1-in-50 day100%0%0%76%210%crossed 2030
Permitted unsubsidised wind and solar contractedall of today's pool0%0%29%98%
80% rule, worst-year shortfallnonemetmetmet0.39 TWh shortcrossed 2029
Construction workers at the peak2020 peak, 14,3003,3857,61521,577crossed 202938,500crossed 2028
Own power plant to build by 2032no set limit0 MW0 MW1,062 MW2,442 MW
Over the lineWithin 25% of itClear

2032 values, except CO₂ (2026–30 total). "Crossed" is the first year a limit is passed: for CO₂, when cumulative emissions pass the cumulative ceiling. The 2020 construction peak is not a legal limit; it is the most the industry has done before.

What would tell us which future we're on Editorial judgement

None of these futures is a forecast. These dated decisions and releases will show which one Ireland is heading for.

WhenWhatWhat it would tell us
pending (no hearing date published)High Court judicial review of CRU2025236 (LEU connection policy): FIE, Friends of the Earth Ireland, ClientEarth v CRUIf the CRU's rules are quashed, new sites have no route to a grid connection, which leaves Frozen or Decline. If they are upheld, the growth futures stay open.
Managed growthAI hub
pending (consultation closed 5 Aug 2026; no date set)CRU decision on interruptible gas connections above 50 MWth (CRU202657)Sets the terms on which new sites' own gas plant connects. Managed growth needs 1,062 MW of own plant by 2032, AI hub 2,442 MW.
Managed growthAI hub
21 September 2026
overdue
ACP decision on Oriel Wind Farm offshore wind (375 MW), case OA15.319799: 19 days past the statutory date, 28.5 months in planningOne of only two offshore wind farms that can sell to data centres. Managed growth needs it from 2031, AI hub from 2030.
Managed growthAI hub
3 December 2026EU AI Gigafactories call (EuroHPC JU) closes, 17:00 CETAn Irish site in a bid would be an early sign of the AI hub case; no Irish site would make it less likely.
AI hub
early December 2026Expected ACP decision on Arklow Bank Wind Park 2 (SSE)The second offshore wind farm that can sell to data centres, with Oriel. Managed growth needs it from 2032, AI hub from 2031.
Managed growthAI hub
25 March 20272030/31 T-4 capacity auction runs (bids close 10:00)Shows whether gas plant linked to data centres wins capacity contracts: an early sign that new connections are coming.
Managed growthAI hub
early July 2027CSO Data Centres Metered Electricity Consumption 2026 (annual release)The first hard number. About 8.0 TWh, Decline; 8.5 TWh, Frozen or Managed growth; 8.6 TWh, AI hub. The futures barely differ in 2026; they split from 2028.
DeclineFrozenManaged growthAI hub
Q2 2028 (assumed)Celtic Interconnector (700 MW, Cork to Brittany) expected in serviceAssumed in every future from 2028 (about 2 TWh a year of imports, unchecked). A delay means more gas burned and more CO₂ in all four.
DeclineFrozenManaged growthAI hub

Dates: StackPath watch list (ACP case pages, CRU, SEMO/EirGrid, EuroHPC, CSO), as of 2026-10-10 · "What it would tell us" is our reading

All four, side by side, with 2025

2025DeclineFrozenManaged growthAI hub
Data-centre electricity, 20327.7 TWh6.7 TWh12.9 TWh18.1 TWh27.6 TWh
Share of metered electricity23.2%19.8%32.2%40%50.4%
Average load875 MW765 MW1,470 MW2,070 MW3,145 MW
Installed IT capacity1.54 GW1.34 GW2.46 GW3.38 GW4.85 GW
Own firm power required (new sites)0 MW0 MW0 MW1,062 MW2,442 MW
Share of a 1-in-50 gas peak day—9.7%17.1%22.6%30.7%
Spare gas capacity used—0%0%76%210%
Electricity-sector CO₂, 2026–30 (ceiling 20 Mt)6.3 Mt in 202522.9 Mt27 Mt27.2 Mt29.2 Mt
Data centres' grid CO₂, 2026–30—5 Mt7.1 Mt7.4 Mt9.1 Mt
Renewables shortfall, worst year (full 80%)—0 TWh0 TWh0 TWh0.39 TWh
Permitted unsubsidised pool contracted—0%0%29%98%
Growth investment 2026–32 (excl. refresh)—€1.5bn€22bn€48.7bn€105.8bn
Imported equipment 2026–32 (incl. server refresh)—€17.5bn€32.1bn€48.8bn€91.4bn
Rates a year, 2032€72.6m (est.)€60m€128m€183m€271m
Direct operating jobs, 2032~3,300 (2024)2,8754,8886,8269,471
Peak construction jobs14,300 (2020)3,3857,61521,57738,500

2025 column: CSO MEC02 (electricity, share); DETE/KPMG (installed IT, 2025; jobs, 2024; 2020 construction peak); EPA provisional (CO₂); StackPath rates estimate from the Tailte Éireann valuation list. Average load = CSO GWh ÷ 8,760 hours. Scenario columns: StackPath model, Oct 2026.

What's checked and what's assumed

58 inputs: 27 checked, 6 derived, 18 assumed, 10 unchecked (3 are part one, part another). The unchecked ones are mostly costs per MW and can move the € results by 30% or more.

KindInputValueSource or reasoning
checkeddc_twh_20257.662 TWhCSO MEC02, Data Centres Metered Electricity Consumption 2025 (7,662 GWh); extra.generation.annual
checkedmetered_twh_202533 TWhCSO MEC02 2025, all metered electricity (DC share 23.2%); cso.annual
checkedsystem_demand_twh_202534.6 TWhEmber 2025 demand = generation 28.918 + net imports 5.685 TWh; extra.generation.annual
deriveddc_avg_mw_2025874.7 MW7,663 GWh / 8,760 h (extra.legacy_capacity.national2025)
checkedinstalled_it_mw_20251,543 MW ITDETE/KPMG, The Value of Data Centres to Ireland (2 Jun 2026): 'approximately 1,543MW of installed data centre IT capacity' (2025)
assumptionnon_dc_growth0.01 per yearNon-DC metered demand grew ~0.6%/yr 2020-25 (Ember/CSO: +5.43 TWh total, +4.63 DC); 1.0%/yr allows for heat-pump/EV electrification. EirGrid's own forecasts are higher (unchecked).
checkedlegacy_headroom_mw1,025–1,405 MWextra.legacy_capacity.nationalHeadroom: 2,000-2,400 MVA contracted x 0.95 minus 2025 draw 875 MW
checkedairaa_dc_mva_2024959 MVAEirGrid/SONI AIRAA 2026-2035: existing DC demand 959 MVA (2024)
checkedairaa_dc_mva_2035_median1,870 MVAEirGrid/SONI AIRAA 2026-2035: 2035 DC forecast median 1,870 MVA (low 1,402, high 2,183)
checkedairaa_shortfall_2026_mw1,010 MWEirGrid AIRAA 2026-35: Ireland short 1,010 MW in 2026 (base) before emergency measures; base turns to surplus from 2029
assumptionpower_factor0.95 MW/MVAas in pipelines/legacy_capacity.py
assumptionpeak_to_avg1.05 ratioData centres are flat loads (overnight floor analysis, extra.generation.dataCentreLens); 5% for weather/cooling peaks
checkedbyo_rule1 MW firm per MW MICCRU/2025/236 (12 Dec 2025) s.3.3: new data centres must provide dispatchable onsite or proximate generation and/or storage which matches their MIC (subject to derating)
assumptionmic_per_it_mw1.15 MW MIC per MW ITDesign peak PUE ~1.25 less some power capping, because BYO plant makes spare MIC costly; gives MIC ~1.5-1.8x average load (an alternative 1.24x with a 0.85 load factor gives similar results). Legacy contracts excluded (already connected)
assumptionbyo_gas_share0.8 share of BYO MWMost CRU-rule BYO in planning files is gas engines/turbines; batteries cover the rest (extra.epa_generation, acp_reports)
checkedrule_share0.8 shareCRU/2025/236 s.3.5: >=80% of annual demand matched with additional Irish renewables (CPPA or own build); RESS/ORESS output does not count
checkedrule_glide_years6 yearsCRU/2025/236 s.3.5: within a 6-year glide path from energisation (modelled as linear ramp)
checkedpool_twh5.98 TWh/yrextra.ppa_supply.gap.poolTWhEst: permitted, unexpired, not RESS-contracted wind 1,397 MW + solar 2,397 MW (PlanSight, 3 Oct 2026; coverage ~54%)
checkedsid_pipeline_mw796 MWextra.ppa_supply.pool.inPlanningSid: 23 wind/solar SID applications undecided at ACP
derivedoffshore_twh_per_mw0.00394 TWh/yr per MWEirGrid ORESS 1 results: Oriel + Arklow Bank 2 (1,175 MW) deemed 4,631 GWh/yr (implied CF 45%)
derivedwind_twh_per_mw0.00222 TWh/yr per MW2025 realised: Ember wind 11.311 TWh / EirGrid installed 5,095 MW (after 11.4% dispatch-down)
uncheckedsolar_twh_per_mw0.00085 TWh/yr per MWp~9.7% capacity factor after ~10% dispatch-down; Irish utility solar
assumptionbase_onshore_add_mw250 MW/yrState-supported (RESS) onshore additions; 2024 +204 MW (SEAI), 2025 +191 MW all-island (EirGrid); AIRAA assumes ~350/yr
assumptionbase_solar_add_mw700 MWp/yrAIRAA assumption trajectory 3,260 MW (2026) -> 6,280 MW (2030), ~750/yr
checkedoress_offshore_path_mw25 MW, 2026–2032extra.offshore.totals.expectedByYear minus DC-eligible MW: state-supported Codling/Dublin Array/NISA not before 2033 on the index's timeline
assumptionimports_twh5.5 TWh/yrNet imports 5.685 TWh in 2025 (Ember); held flat
uncheckedceltic_twh2 TWh/yr from 2028Celtic Interconnector (700 MW to France) targeted ~2028; ~2 TWh/yr net import assumed
checkedhydro_bio_twh1.077 TWh/yrEmber 2025 hydro 0.601 + bioenergy 0.476
checkedother_fossil_twh0.793 TWh/yrEmber 2025 other fossil (oil, peat, waste); held flat; coal 0 from 2026 (Moneypoint coal end, unchecked)
assumptiongas_floor_twh4 TWh/yrSystem must-run / reserve gas floor
derivedgas_t_per_mwh_fuel0.204 tCO2/MWh fuel56.6 tCO2/TJ (extra.emissions assumption A1, Equinix DB5 ETS vs AER) x 3.6 GJ/MWh
checkedelec_sector_mt_20256.297 MtCO2EPA provisional 2025, electricity sector (extra.emissions.electricitySectorByYear)
uncheckedcoal_t_per_mwh0.9 tCO2/MWh_ecoal plant ~0.9 t/MWh
uncheckedother_fossil_t_per_mwh0.75 tCO2/MWh_eoil/peat/waste mix
checkedonsite_eff0.42 electrical efficiencyCCAC Annual Review 2026 scenario: on-site gas at 42% electrical efficiency (extra.emissions.shares.flex500h)
assumptionpeak_day_gas_share0.85 share of DC load from gas on a still winter day1-in-50 peak day: low wind, imports uncertain
assumptionpeak_day_eff0.5 efficiencyCCGT/OCGT mix on peak day
checkedroi_peak_day_gwh325.5 GWh/dayGNI Winter Outlook 2025/26 1-in-50 peak day (extra.gas.shortfall.roiPeakDayGWh2025_26)
checkedgni_headroom_pct10 %CRU202657: minimum 10% capacity headroom to 2032/33 (Best Estimate), 3% risk-adjusted
assumptionlegacy_onsite_kt2026: 30 · 2027: 80 · 2028: 145 · 2029: 145 · 2030: 145 · 2031: 145 · 2032: 145 (ktCO2)ETS 2025 verified 9.5 kt (EUTL); licensed gas pipeline run 500 h/yr = 145 kt (extra.emissions.shares.flex500h). Upside risk: 946 kt if run as licensed.
checkedassumptionceiling_elec_mt2026: 4 · 2027: 4 · 2028: 4 · 2029: 4 · 2030: 4 · 2031: 3 · 2032: 3 (MtCO2/yr)Sectoral Emissions Ceilings 2022: electricity 20 Mt for 2026-30 (4.0/yr). 2031-35 sectoral ceilings not set: 3.0/yr assumed (= 4.0 x carbon budget 151/200).
checkedassumptionceiling_commercial_mt2026: 1 · 2027: 1 · 2028: 1 · 2029: 1 · 2030: 1 · 2031: 0.76 · 2032: 0.76 (MtCO2/yr)Commercial & public buildings 5 Mt for 2026-30 (1.0/yr); 2031-35 scaled by 151/200 (assumption). On-site DC gas counts here unless SEM-registered.
checkedcapex_building_m_per_mwlegacy: 12 · parks: 12 · ai: 13 (EUR m per MW IT)DETE/KPMG (2 Jun 2026) p.145: EUR 11-13m/MW hyperscale, EUR 10-12.5m/MW non-hyperscale; AI campuses at the top of the range (liquid cooling) is an assumption
uncheckedcapex_it_m_per_mwlegacy: 12 · parks: 10 · ai: 25 · refresh: 8 (EUR m per MW IT)General-cloud servers/network ~EUR 8m/MW IT; accelerator racks (GB200-class ~US$3m per ~120-130 kW rack + network) ~EUR 25m/MW; legacy fill half AI. Cross-check: compute-kit net imports EUR 4.5bn in 2025, gross EUR 19.7bn in 12 months to Jul 2026 (Comext).
assumptionrefresh_years5 yearsServer refresh cycle for the 2025 fleet
uncheckedgrid_m_per_mw_mic0.5 EUR m per MW MICConnection + share of deep reinforcement (range 0.3-1.0); legacy contracts already connected
uncheckedgas_gen_m_per_mw0.9 EUR m per MWeReciprocating engines / OCGT
uncheckedbattery_m_per_mw0.35 EUR m per MW (2h)Grid-scale BESS 2025-26
uncheckedonshore_m_per_mw1.7 EUR m per MWIrish onshore wind
uncheckedsolar_m_per_mw0.7 EUR m per MWpIrish utility solar
derivedoffshore_m_per_mw3.111 EUR m per MWSceirde Rocks: 'EUR 1.4 billion wind farm' of 450 MW (RTE, 2 Jan 2026) = EUR 3.1m/MW; spread over the 3 years before COD
assumptioncppa_energy_mix_wind0.6 share of CPPA TWh from onshore windrest solar; the permitted pool is 3.7 TWh wind / 2.3 TWh solar
assumptionimport_shareit: 1 · building: 0.35 · gen: 0.7 · renewables: 0.6 (share imported)IT kit ~all imported; building M&E (transformers, switchgear, chillers) ~35%; engines/batteries 70%; turbines/panels 60%
checkedrates_eur_m_202572.6 EUR m/yrTailte Eireann valuation list x 2026 ARV: 66 DC properties, est. EUR 72.6m/yr (extra.valuation.totals; estimate, not bills)
checkedrates_k_per_mw_it60 EUR k per MW IT per yrDETE/KPMG p.145: EUR 60,000/MW commercial rates (excl. energy parks). Index's own: 72.6m / 1,543 MW IT = EUR 47k/MW IT
checkedfte_op_per_mwlegacy: 1.8 · parks: 2.1 · ai: 1.8 (direct FTE per MW IT)DETE/KPMG p.145: 1.8 FTE/MW hyperscale, 4.3 non-hyperscale; parks = 88/12 mix (KPMG base mix) = 2.1. Check: 1,543 MW x 2.1 = 3,240 vs KPMG 3,300 direct operational jobs (2024)
checkedfte_con_per_mw55 direct construction FTE per MW IT built per yearDETE/KPMG p.145: 55 FTE/MW hyperscale, 57 non-hyperscale ('inferred from KPMG input-output model')
derivedassumptionload_per_itbase: 0.57 · legacy: 0.65 · parks: 0.65 · ai: 0.75 (avg MW per MW IT)2025 fleet 875 MW avg / 1,543 MW IT = 0.57 (derived). New: legacy fill 0.65, parks 0.65, AI 0.75 (utilisation x PUE; assumption)
How the model works
  • Load is modelled as annual-average MW added per segment (legacy fill, energy parks, AI campuses) and converted to IT MW with load-per-IT-MW factors; additions count for the whole year they are listed in.
  • Share = DC TWh / (non-DC CSO metered demand grown at the non-DC rate + DC TWh). System demand uses Ember's basis (incl. losses).
  • Firm capacity: DC peak = avg x 1.05, compared with a straight line between EirGrid AIRAA's 959 MVA (2024) and 1,870 MVA median (2035). New connections must bring dispatchable MW = MIC (CRU/2025/236); legacy contracts are exempt. 'systemFirmGapMW' = DC peak above the AIRAA path not covered by BYO plant.
  • Supply balance: 2025 Ember actuals + baseline onshore/solar additions + DC CPPA renewables + DC-eligible offshore + imports (+Celtic from 2028) + hydro/bio + other fossil; gas is the residual (floor 4 TWh). Electricity-sector CO2 = gas TWh x a factor calibrated so 2025 matches EPA's 6.30 Mt.
  • DC grid emissions are attributional (DC share of system demand x sector emissions). On-site: BYO gas MW x run hours / 42% x 56.6 tCO2/TJ, plus legacy licensed gas sites (assumed 500 h/yr from 2028).
  • 80% rule: each energised cohort's requirement ramps linearly over 6 years (glide) and is also shown at the full 80%. Available = permitted onshore pool contracted at a scenario rate + DC-eligible merchant offshore (Oriel, Arklow Bank 2) at EirGrid's deemed yield.
  • Peak day: DC load on a 1-in-50 day met 85% by gas at 50% efficiency, compared with GNI's 325.5 GWh/day. 'pctOfGniHeadroomUsed' counts only DC load above EirGrid's AIRAA median path, assuming GNI's forecast already embeds that path (assumption), against CRU202657's 10% best-estimate headroom.
  • Investment: new IT MW x KPMG building cost/MW; IT hardware per MW (unchecked); grid per MW of new MIC; BYO firm plant; CPPA onshore/solar; offshore capex spread over 3 years before COD. Refresh of the 2025 fleet shown separately.
  • Rates = index 2025 estimate + new IT MW x KPMG EUR 60k/MW. Jobs = KPMG FTE/MW (operational 1.8 hyperscale / 2.1 mix; construction 55 per MW built in the year). Imports = layer capex x assumed import shares.
Caveats
  • This is a scenario model, not a forecast. Numbers marked 'unchecked' (hardware, grid, generation and renewables capex per MW; Celtic; solar yield) are general knowledge and can move results by 30%+.
  • Average MW is not IT MW or MIC. The 2025 fleet draws 875 MW on average against ~1,543 MW of installed IT and ~2,000-2,400 MVA contracted.
  • The onshore pool is shared: the same permitted wind/solar can win RESS instead, and PlanSight covers only ~54% of RESS projects, so the real pool may be larger.
  • The supply balance is energy-only (TWh). It ignores hourly matching, dispatch-down, network constraints and interconnector availability in stress events.
  • Electricity ceilings for 2031-35 are not set; 3.0 Mt/yr is an assumption scaled from the national carbon budget. Whether SEM-registered BYO plant counts in electricity or commercial buildings depends on registration.
  • IT hardware is the largest and most uncertain line. Comext shows EUR 19.7bn of compute kit imported in the 12 months to Jul 2026 (EUR 4.75bn net of exports); much is re-exported, and customs value is not installed value.
  • KPMG's capex and jobs per MW come from a survey and its input-output model; construction FTE/MW is 'inferred'. Rates per MW is KPMG's figure; this index's own estimate implies ~EUR 47k/MW IT.
  • Cross-checks: Frozen's 2026-30 electricity-sector total (27 Mt) is above EPA's WAM projection (24.5 Mt) because baseline renewables build here follows recent pace, not plans. Modelled hardware-plus-equipment imports in Frozen (~EUR 4.6bn/yr) are close to Comext's 2025 net compute-kit imports (EUR 4.5bn).
  • KPMG's 55 construction FTE/MW reflects past builds; AI campuses put more of their capex into imported hardware, so jobs per EUR invested will be lower.
  • Comparisons with Spain (AWS EUR 33.7bn), Finland (Google EUR 13bn) and Portugal (Microsoft US$10bn) use announced totals over different periods.

Model built on this index's checked data (CSO MEC02, Ember, EirGrid AIRAA 2026-35, CRU/2025/236, CRU202657, GNI, EPA, Sectoral Emissions Ceilings 2022, DETE/KPMG 'The Value of Data Centres to Ireland' Jun 2026, Tailte Eireann, Eurostat Comext) plus labelled assumptions. Inputs: ireland.json built 2026-10-06

Questions people ask

How much electricity will Irish data centres use in 2030?
Between 7.2 and 19.8 TWh in 2030 across our four scenarios, against 7.7 TWh measured in 2025 (CSO). EirGrid's forecast, as cited by the CRU, is 14.6 TWh by 2034. Scenarios follow from stated assumptions; they are not predictions.
Will data centres use half of Ireland's electricity?
Only in the stretch 'AI hub' scenario, where they reach 50.4% of metered electricity by 2032. With no new connections ('Frozen') they reach 32.2%, because grid contracts signed before 2021 still have room to fill. They used 23.2% in 2025 (CSO).
Why does data-centre use keep rising if new connections are frozen?
Operators hold about 2,000–2,400 MVA of grid contracts (EirGrid) but drew about 875 MW on average in 2025 (CSO). Filling part of that headroom takes use to 12.9 TWh by 2032 without a single new connection, in our Frozen scenario.
Can Ireland stay within its electricity carbon ceiling?
Not in any of our scenarios, which assume renewables keep being built at their recent pace: the electricity sector emits 22.9 to 29.2 Mt of CO₂ over 2026–30 against a 20 Mt ceiling. Data centres change how far it overshoots, not whether it does.