How much water do data centres in Ireland use?
Licensed data centres used 1.05 billion litres of public-supply water in 2025, about 0.17% of Uisce Éireann's supply, according to their EPA annual environmental reports (16 sites). Two sites, Meta Clonee and Equinix Blanchardstown, used 91% of it. The widely quoted 46 billion litres is a modelled power-station footprint, not water drawn on site.
Updated 3 October 2026 · data build 2026-10-10 · how we know · corrections
The scale, and where it goes
Data-centre water use, on one scale
Licensed data centres drew about 2.9 million litres a day of public water in 2025, about 0.17% of the 1,700 million Uisce Éireann treats daily; the much bigger "46 billion litres" figure is water used to generate their electricity, not water they draw.
Each square's area is proportional to litres per day, so the red square (data centres' metered public-supply water, 1.05 billion litres in 2025 from 16 EPA-licensed sites) can be compared directly with Dublin's and the country's supply. Uisce Éireann's own figure for the 57 data centres on its network, and reported summer peaks, are higher but on the same small scale. The dashed square is a modelled footprint: data centres' electricity multiplied by 6 litres per kWh used at power stations, which is a different quantity from water piped to the sites. National totals hide local pressure: most sites are in the Greater Dublin Area.
EstimateDaily figures are annual totals ÷ 365; household equivalents use the CSO 2022 median household use. The 57-site and summer figures were released to a TD and reported by The Journal; no primary document is public.
Sources: EPA annual environmental reports (Table 5, water used), 3 Oct 2026 · Uisce Éireann press release on 2024 annual report, 30 Jun 2025 · Irish Times (citing Uisce Éireann), 29 May 2026; UE press release 10 Jul 2026 (693 ML record), 29 May 2026 · The Journal, 24 Aug 2026, 24 Aug 2026 · Fearon, Bresnihan & Brodie, 'How we all pay for Big Tech', MUSSI Working Paper 31, Maynooth University, Sept 2026 · CSO, Domestic Metered Public Water Consumption 2022 - Key Findings, 20 Nov 2023
Two sites use most of the data-centre water
One Meta site and one Equinix site used 91.1% of licensed data centres' public water in 2025; most other sites use a few litres per MWh.
Panel A splits the 1,048 million litres of public-supply water that EPA-licensed data centres reported for 2025 by site. Panel B divides each site's water by the electricity it drew, on a log scale, so each step is ten times the last: the median for the other 14 sites is 12.9 litres per MWh, while Equinix's site used 2,453. The reports do not say what the water is used for; a spread this wide is consistent with different cooling designs (our reading, not stated in the reports). The dashed line is the 6,000 litres per MWh a research paper assigns to generating Irish electricity, which happens at power stations, not data centres.
Sources: EPA annual environmental reports, Table 5 'Water used', 3 Oct 2026 · Fearon, Bresnihan & Brodie, 'How we all pay for Big Tech', MUSSI Working Paper 31, Maynooth University, Sept 2026
What's measured, site by site
Litres per MWh of electricity, 2025
Equinix Blanchardstown (evaporative cooling) uses ~2,450 L per MWh; most Amazon sites 1–26 L.
The 2026 summer, million litres a day
Use rose with the hot summer from May, before the hosepipe bans (Dublin mid-July, national 24 July). About 0.6–0.9% of Dublin's supply at the peak.
EPA annual environmental reports (public-supply water) · Uisce Éireann via Dáil answers and The Journal · Maynooth MUSSI Working Paper 31 · as of 2026-10-03
What the Government has said
| 2026-06-11 | "most large data centres have improved efficiency and rely on closed loop systems with minimal ongoing consumption" |
| 2026-07-28 | "data centres are not a major driver of demand on the public water supply network, accounting for less than 0.3%" |
| 2026-07-28 | "not all data centres use water from the Uisce Éireann network, with a number of them having their own wells" |
| 2023-02-02 | "There is currently no register held by a public body that includes the energy and water requirements of data centres." |
| 2025-03-19 | "Uisce Éireann does not publish ongoing water consumption figures relating to particular businesses as the information may be commercially sensitive" |
| 2026-04-14 | "data centres in Ireland are reporting this information to a confidential EU database on data centres" |
| 2026-09-17 | "ordinary people were asked to abide by a hosepipe ban this summer whereas data centres actually doubled their water consumption" |
Questions people ask
- Did data centres cause the 2026 hosepipe ban?
- No single cause is published. Uisce Éireann told the Dáil data centres are under 0.3% of public supply (PQ 225, 28 July 2026), but metered use at the two biggest sites roughly doubled during the dry summer, in the stressed Dublin supply area.