Money · rates and tax

What tax do data centres pay in Ireland?

Data centres pay commercial rates like any business: about €72.6m a year on 66 properties, our estimate from the Tailte Éireann valuation list and 2026 council rates (Oct 2026). KPMG puts their employment-related tax at about €280m in 2024. No public figure exists for corporation tax on data-centre operations.

Updated 3 October 2026 · data build 2026-10-10 · how we know · corrections

What they pay councils

€73m
Estimated commercial rates a year
valuation × 2026 rate
€291m
Net annual value on the valuation list
Tailte Éireann
66
Properties coded 'data centre'

Estimated rates by council, €m a year

South Dublin · 2943
Fingal · 1811.6
Meath · 310.2
Dublin · 137.4
Clare · 10.2
Louth · 10.2
Limerick City And · 10

Where the operator is named, €m a year

Meta · 29.9
Amazon (AWS) · 56
EdgeConneX · 14.1
Microsoft · 23.5
K2 Strategic · 11.3
Equinix · 10.5
Digital Realty (Interxion) · 10.4
GTT (Hibernia Atlantic) · 10.1

52 properties don't name the occupier. Rates are estimates (net annual value × each council's 2026 rate), not bills; valuation dates differ by council, and Cork isn't on the comparable list yet.

Tailte Éireann valuation list (CC-BY-4.0) · 2026 rates on valuation · as of 2026-10-03

Rates per megawatt drawn (estimate)

€64k
Estimated rates per MW of average grid draw
12 campuses, 776 MW, 2025
136 kWh
Grid electricity drawn per € of rates
≈ €7.35 of rates per MWh
CouncilCampusesMW drawnRates€ per MWMWh per €× warehouse× office
South Dublin5322€27.1m€84k0.116.5×7.3×
Fingal4162€6.1m€37k0.248×3.5×
Meath2148€10.2m€69k0.1344.6×11.7×
Dublin City1144€6.6m€46k0.194.9×0.8×
Campus by campus
CampusCouncilMW drawnRates€ per MW€/m² NAV× warehouse
Amazon (AWS) BlanchardstownFingal49.8€691k€14k1952.9×
Amazon (AWS) DroghedaMeath12.7€265k€21k65031×
Amazon (AWS) CruiserathFingal76.6€1.9m€25k66210×
Equinix BlanchardstownFingal18.5€511k€28k68510.4×
Amazon (AWS) ClonshaughDublin City144.4€6.6m€46k1874.9×
Amazon (AWS) Grange Castle SouthSouth Dublin61€3m€48k65516.4×
Amazon (AWS) Belgard, TallaghtSouth Dublin45.6€2.4m€52k64916.2×
Meta CloneeMeath135€9.9m€74k94745.1×
Microsoft Grange CastleSouth Dublin154.5€12.4m€80k66016.5×
Amazon (AWS) Greenhills Road, TallaghtSouth Dublin34.6€3.8m€110k67016.7×
K2 Strategic BallycoolinFingal17.5€2.9m€167k67610.2×
Google Grange Castle SouthSouth Dublin26€5.6m€217k66116.5×

Estimates. MW is the 2025 average grid draw in EPA annual environmental reports (licensed sites only); rates are net annual value × the council's 2026 rate, not bills. "× warehouse" compares the campus's rated floor area with what the same area would pay at the council's median value per m² for large warehouse/industrial floors (× office: office floors), same list and valuation date. A data centre's value can include rateable electrical and cooling plant, which a shed lacks. Rates per MW for other industry can't be computed: the valuation list holds no power data.

Who says what

SideFigureSource
Industry / Government€14.6bn employment taxes in 'dependent sectors' (28%)KPMG for DETE (Jun 2026)
Industry / Government€2.8bn employment-related tax 2010-2024; €280m in 2024KPMG for DETE (Jun 2026)
Industry / Government€33bn corporation tax at risk if IP follows data centres abroadDigital Infrastructure Ireland via Irish Times (27 May 2026)
Critics / researchersNo data-centre-specific corporation-tax figure is published; ~€4bn of 2023 CT linked to ICT incl. DCsOireachtas Library, The future of data centres in Ireland (Mar 2025)
Critics / researchersCyrusOne Irish unit paid €24.6m dividend to Dutch parent (2024)Una Mullally, Irish Times (19 Jan 2026)

Our data: ~€73m/yr commercial rates (Tailte Éireann valuation × 2026 ARV; estimate).