Explained · power, water, myths

How big is a data centre, really?

Megawatts, terawatt-hours and litres are hard to picture. Start with five ideas that make every number on this site readable, then see the scale in homes, chips and swimming pools, with every number sourced, and the common rumours checked.

Five ideas behind every number

Each takes a minute and ends with Ireland's real figures. Pick any, or follow them in order.

Idea 1 of 5

A data centre is one part of a shared power system.

Follow electricity from where it's made to the servers. Each stage can set its own limit, so each answers a different question. Pick a stage.

Is there enough generation when it's needed, including when the wind drops?

Gas plants, wind and solar farms, and imports through the interconnectors put electricity into the system. Together they have to meet demand at every moment. How Ireland makes its electricity →

With Ireland's numbers

Measured · CSO In 2025, data centres used 7.7 TWh of the 33.0 TWh of electricity metered in Ireland: 23.2%. That is the site end of the chain. National supply totals can't say which power station or cable fed a particular site.

Figure: Ireland's electricity as one system, from source to use →

Used, contracted, possible

The overview's three headline numbers measure different things: electricity already used, grid capacity held, and demand that might come.

Figure 1

MW is a rate; TWh is an amount

The headline 23.2% is a share of electricity used across 2025, not a share of grid capacity.

Power and electricity use are different unitsIn 2025, Irish data centres used 7.7 terawatt-hours, 23.2 percent of metered electricity. Spread evenly over 8,760 hours, that annual amount equals about 875 megawatts of average power. A megawatt is a rate; a terawatt-hour is an amount over time.RATE AT A MOMENTMWhow fast a site draws electricityAMOUNT OVER A YEARTWhpower added up across all the hoursIreland’s metered electricity, 2025 · ≈ 33.0 TWh23.2%other metered users7,662 GWh data centres ÷ 8,760 hours ≈ 875 MW average
Power and electricity use are different unitsIn 2025, Irish data centres used 7.7 terawatt-hours, 23.2 percent of metered electricity. Spread evenly over 8,760 hours, that annual amount equals about 875 megawatts of average power. A megawatt is a rate; a terawatt-hour is an amount over time.RATE AT A MOMENTMWhow fast electricity is drawnAMOUNT OVER TIMETWhpower added up over a yearIreland’s metered electricity, 202523.2%other metered users7,662 GWh ÷ 8,760 hours≈ 875 MW average

The CSO recorded 7,662 GWh (7.7 TWh rounded) of metered data-centre electricity in 2025, or 23.2% of Ireland’s metered total. Dividing the unrounded annual use by 8,760 hours gives an equivalent average draw of about 875 MW. A real site’s power varies by hour; the average is a way to picture an annual total.

EstimateAverage MW and total metered TWh are derived from the CSO data.

Sources: CSO MEC02, 7 Jul 2026

Figure 2

Used, contracted and possible are different

Only the first figure is electricity already used. The others describe a connection allowance and potential future demand.

Three different kinds of power numberUSED: 7.7 TWh, Metered during 2025, an observed annual amount. CONTRACTED: 2,400 MVA, Maximum grid connection, includes some other large loads. POSSIBLE: 5.8 GW, Future demand signalled, market sounding, not approvals. They are different units and stages, so do not add them or read the three figures as a time series.USED7.7 TWhMetered during 2025an observed annual amountMEASUREMENTCONTRACTED2,400 MVAMaximum grid connectionincludes some other large loadsRIGHT TO CONNECTPOSSIBLE5.8 GWFuture demand signalledmarket sounding, not approvalsEARLY INTEREST
Three different kinds of power numberUSED: 7.7 TWh, Metered during 2025, an observed annual amount. CONTRACTED: 2,400 MVA, Maximum grid connection, includes some other large loads. POSSIBLE: 5.8 GW, Future demand signalled, market sounding, not approvals. They are different units and stages, so do not add them or read the three figures as a time series.USED · MEASUREMENT7.7 TWhMetered during 2025an observed annual amountCONTRACTED · RIGHT TO CONNECT2,400 MVAMaximum grid connectionincludes some other large loadsPOSSIBLE · EARLY INTEREST5.8 GWFuture demand signalledmarket sounding, not approvals

The CSO measured 7.7 TWh of data-centre electricity in 2025. EirGrid reports 2,400 MVA of connected or contracted capacity for data centres and some other new-technology loads; think of this as the size of a doorway, not how much passed through it during the year. The 5.8 GW figure comes from system operators’ market sounding cited by the CRU; it is possible new demand, not capacity approved or built. MVA and MW are different power measures, so these three numbers are intentionally not drawn on one scale.

Sources: CSO MEC02, 7 Jul 2026 · EirGrid AIRAA 2026–2035, Dec 2025 · CRU2025236, 12 Dec 2025

How much power is that?

Data centres used 7.7 TWh in 2025. Drag the slider to see what a site's megawatts mean in homes, chips and pools. Each comparison rests on its own assumptions, shown under it.Illustration · comparisons

A data centre drawing 135 MW, around the clock

281.6 thousand
Irish homes' worth of electricity
at 4,200 kWh a home a year
3.6%
Of all metered electricity in Ireland
CSO 2025
97.1 thousand
AI chips it could run, at most
H100-class, 8-GPU servers at full 10.2 kW, PUE 1.09 (Google's fleet; most sites are higher, so fewer chips)
10.8–13.5 billion
Simple AI text prompts a day, if it did nothing else
at 0.24–0.3 Wh a prompt (company and Epoch AI estimates); reasoning, image or video requests use 10–100× more
841.6 million
Hours of video streamed a day, data-centre share
IEA, ~5% of streaming energy
73
Olympic pools of water a year, at the average licensed site
154 L per MWh (EPA reports, 2025); typical site 13 L/MWh = 6 pools; highest 2,453 L/MWh = 1,161

These are illustrations, not a description of any real site. Real data centres run a mix of storage, cloud services, video and AI, with spare capacity. GPU count assumes every watt goes to AI servers. Sources: CRU Factsheet: Domestic Electricity and Gas Bills in Ireland (CRU20125), 2020 · NVIDIA DGX H100 User Guide, 2023-20 · Google Cloud blog, 'Measuring the environmental impact of AI inference' (+ technical paper), 2025-08 · Epoch AI (Josh You), 'How much energy does ChatGPT use?', 2025-02 · IEA commentary (George Kamiya), 'The carbon footprint of streaming video: fact-checking the headlines', 2020-12 · water from EPA annual reports.

Inside a data centre

Megawatts, MVA, MW thermal and PUE are measured at different points in the same building. Here is where.

Figure 3

Anatomy of a data centre, and where each number is measured

Power flows grid → substation → batteries → servers → heat. Each headline number is taken at a different point, which is why megawatts, MVA, MW thermal and PUE can't be compared directly.

Anatomy of a data centreGrid: Transmission lines bring power in at high voltage. Measured as MWh, metered. CSO counts here: 7,662 GWh in 2025 Substation: Steps voltage down; the grid contract sets its maximum import. Measured as MVA, contracted. 2,000–2,400 MVA nationally UPS and batteries: Carry the load for the seconds until generators start. Measured as seconds–minutes. No battery size stated in the 34 campus files we read Data halls: Servers, storage and network: the useful load. Measured as IT load, MW. Stated for 5 of 34 campuses in files we read Cooling and losses: Fans, chillers, power conversion. Measured as PUE = total ÷ IT. 1.54 industry average; 1.09 Google fleet Backup generators: Diesel, HVO or gas; run in grid emergencies and tests. Measured as MW thermal; EPA licence at ≥50. 1,225 units at licensed sites; ran 0.6–6.4 full-load hours a year Water: Mains water, mainly for cooling. Measured as litres; L per MWh. 1–2,453 L/MWh at licensed sites, 2025WHERE EACH NUMBER IS MEASUREDMWH, METEREDCSO counts here:7,662 GWh in 2025MVA, CONTRACTED2,000–2,400 MVAnationallySECONDS–MINUTESNo battery sizestated in the 34campus files we readIT LOAD, MWStated for 5 of 34campuses in files wereadGridTransmissionlines bringpower in at highvoltageSubstationSteps voltage down;the grid contractsets its maximumimportUPS and batteriesCarry the load forthe seconds untilgenerators startData hallsServers, storage andnetwork: the usefulloadHeat outalmost all the powerends up as heat;some planning filesdescribe heat reuseBackup generatorsDiesel, HVO or gas; run ingrid emergencies and testsCooling and lossesFans, chillers, powerconversionWaterMains water,mainly for coolingMW THERMAL; EPA LICENCE AT ≥501,225 units at licensed sites; ran 0.6–6.4full-load hours a yearPUE = TOTAL ÷ IT1.54 industry average;1.09 Google fleetLITRES; L PER MWH1–2,453 L/MWh atlicensed sites,2025
Anatomy of a data centreGrid: Transmission lines bring power in at high voltage. Measured as MWh, metered. CSO counts here: 7,662 GWh in 2025 Substation: Steps voltage down; the grid contract sets its maximum import. Measured as MVA, contracted. 2,000–2,400 MVA nationally UPS and batteries: Carry the load for the seconds until generators start. Measured as seconds–minutes. No battery size stated in the 34 campus files we read Data halls: Servers, storage and network: the useful load. Measured as IT load, MW. Stated for 5 of 34 campuses in files we read Cooling and losses: Fans, chillers, power conversion. Measured as PUE = total ÷ IT. 1.54 industry average; 1.09 Google fleet Backup generators: Diesel, HVO or gas; run in grid emergencies and tests. Measured as MW thermal; EPA licence at ≥50. 1,225 units at licensed sites; ran 0.6–6.4 full-load hours a year Water: Mains water, mainly for cooling. Measured as litres; L per MWh. 1–2,453 L/MWh at licensed sites, 2025GridTransmission lines bring power in at high voltageMWH, METEREDCSO counts here: 7,662 GWh in 2025SubstationSteps voltage down; the grid contract sets its maximum …MVA, CONTRACTED2,000–2,400 MVA nationallyUPS and batteriesCarry the load for the seconds until generators startSECONDS–MINUTESNo battery size stated in the 34 campus files we readData hallsServers, storage and network: the useful loadIT LOAD, MWStated for 5 of 34 campuses in files we readCooling and lossesFans, chillers, power conversionPUE = TOTAL ÷ IT1.54 industry average; 1.09 Google fleetFEEDING INBackup generatorsDiesel, HVO or gas; run in grid emergencies and testsMW THERMAL; EPA LICENCE AT ≥501,225 units at licensed sites; ran 0.6–6.4 full-loadhours a yearWaterMains water, mainly for coolingLITRES; L PER MWH1–2,453 L/MWh at licensed sites, 2025

Electricity arrives from the transmission grid, passes through an on-site substation whose contracted maximum import (in MVA) is the "capacity" in grid debates, then through batteries that bridge outages, to the servers in the data halls. The CSO's 7,662 GWh for 2025 is energy metered at the grid connection. PUE compares total power with power reaching the servers: the industry average is 1.54, meaning 54% extra for cooling and losses. Backup generators are rated by fuel input (MW thermal), roughly two to three times their electrical output, and need an EPA licence above 50 MW thermal; water is metered at the mains connection.

Sources: CSO MEC02, 7 Jul 2026 · EirGrid AIRAA 2026–2035 and Constrained Area Overview, Dec 2025 / May 2026 · Uptime Institute Global Data Center Survey 2025, Jul 2025 · Google Data Centers - Efficiency, 2026 · Our epa_generation pipeline (EPA LEAP AERs), 3 Oct 2026 · EPA LEAP licences and annual environmental reports, 3 Oct 2026

Electricity is not energy

The "a quarter of Ireland's energy" line mixes up the two. Electricity is only about a fifth of all the energy Ireland uses; oil for transport and heating is much bigger.

23.2%
Of metered electricity, 2025
CSO
4.9%
Of all final energy used in Ireland, 2024
SEAI energy balance
84%
Of the electricity used by every Irish home combined
9.1 TWh for homes · CSO
Figure 4

Electricity is not energy

Data centres used 21.2% of Ireland's final electricity use in 2024 (SEAI basis) but only about 4.9% of all the energy the country used, because electricity is just 22.9% of final energy.

Electricity is not energyIn 2024 Ireland used 143.7 TWh of final energy; electricity was 22.9% (32.9 TWh). Data centres used 7.0 TWh: 21.2% of that electricity and 4.9% of all final energy.All final energy, 2024: 144 TWhElectricity: 32.9 TWh (22.9%)All final energy 143.7 TWhElectricity 32.9 TWhData centres 7.0 TWhoil for transport and heat, gas, other fuelshomes, business, industry21.2%Data centres: 7.0 TWh = 21.2% of electricity, but 4.9% of all energy
Electricity is not energyIn 2024 Ireland used 143.7 TWh of final energy; electricity was 22.9% (32.9 TWh). Data centres used 7.0 TWh: 21.2% of that electricity and 4.9% of all final energy.All final energy, 2024: 144 TWhElectricity: 32.9 TWh (22.9%)All final energy 143.7 TWhElectricity 32.9 TWhData centres 7.0 TWhoil, gas, other fuelshomes, business, industry21.2%Data centres: 7.0 TWh21.2% of electricity, 4.9% of all energy

The top bar is all final energy used in Ireland in 2024 (144 TWh), most of it oil for transport and heating. The solid slice next to the red is electricity (22.9%), which the second bar stretches to full width. Data centres (red) used 7.0 TWh in 2024 according to the CSO; against the SEAI's electricity total that is 21.2%, while the CSO's own share of metered electricity is 21.9%. "A fifth of Ireland's energy" claims mix up the two bars; the electricity share is the right measure for the grid, the energy share for climate and energy security.

EstimateData-centre share of final energy = CSO data-centre use ÷ SEAI total final consumption, same year; the two bodies count slightly differently.

Sources: SEAI, Energy in Ireland 2025 report, Table 5.1, Dec 2025 · SEAI, Energy in Ireland 2025, Table 5.1, Dec 2025 · CSO MEC02, 7 Jul 2026

SEAI, Energy in Ireland 2025 report, Table 5.1, 2025-12 · CSO, Metered Electricity Consumption 2025 - Key Findings, 2026-07

How much water?

Less than you've heard nationally, more than you'd think at two sites, and very seasonal.

1.05 bn L
Public water used by 16 licensed sites, 2025
≈ 419 Olympic pools · EPA reports
0.17%
Of Uisce Éireann's public supply
91%
Used by just two sites
Meta Clonee and Equinix Blanchardstown
46 bn L
The widely quoted 'footprint'
water used to generate their electricity, not drawn on site
Two different measures. The "over 999 million litres" in the press (The Journal, 2025) is, like our 1.05 bn above, a sum of what licensed sites report to the EPA; the totals differ by which sites are counted. The 46 billion litres from the Maynooth paper multiplies data-centre electricity by water used at power stations (6 L/kWh). Never add them. Ireland's climate lets most sites cool with outside air most of the year, which is why many use very little.

Litres per MWh of electricity, 2025

Meta · P1192471
Equinix Hyperscale 1 (DB5) · P11682,453
K2 Strategic Infrastructure · P1143315
Microsoft · P119040
Amazon Data Services · P117218
Microsoft · P11915
Amazon Data Services · P117714
Google · P118915
Microsoft · P118713
Amazon Data Services · P11713

Equinix Blanchardstown (evaporative cooling) uses ~2,450 L per MWh; most Amazon sites 1–26 L.

The 2026 summer, million litres a day

Jan-Apr 20262.3
May-Jul 20265.6
Jul 20266.5

Use rose with the hot summer from May, before the hosepipe bans (Dublin mid-July, national 24 July). About 0.6–0.9% of Dublin's supply at the peak.

EPA annual environmental reports (public-supply water) · Uisce Éireann via Dáil answers and The Journal · Maynooth MUSSI Working Paper 31 · as of 2026-10-03

How a data centre "brings its own power"

Since December 2025 a new data centre has two separate obligations: one physical, one on paper.

01 · physical

Firm power it can switch on

Gas turbines, engines or batteries on or near the site, at least as big (after de-rating) as its grid connection, bidding into the market. Wind counts for only ~5.6% here, so it's almost always gas. CRU example: a 30 MVA site needs ~31 MW of gas turbines.
02 · contractual

80% matched by new Irish renewables

Power purchase agreements with new, unsubsidised wind or solar anywhere in Ireland, within six years. Same 30 MVA example: ~55 MW of new onshore wind under contract.
03 · where the gas comes from

Mostly Scotland

About 80–95% of Ireland's gas comes through two subsea pipelines from Moffat, Scotland; the Corrib field off Mayo is declining (−15.6% capacity this winter). There's no LNG terminal. So "own power" mostly means gas imported via one entry point.
04 · the catch

Dublin can't take it

EirGrid says on-site gas generators would push Dublin's short-circuit currents past switchgear limits, part of why Dublin is "fully constrained". Sites with pre-2021 contracts are exempt and hold 1.0–1.4 GW unused.

CRU2025236 (Dec 2025) · EirGrid Constrained Area Overview (May 2026) · Gas Networks Ireland Winter Outlook 2025/26 and Network Development Plan · see the Power and Policy tabs for the evidence.

Rumours, checked

What people say about Irish data centres, and the verdict. Each opens its full check, with the numbers and sources.

All twelve checks on one page →