Policy · grid connections

Is there a data-centre moratorium in Ireland?

There has never been a legal moratorium on data centres in Ireland. The CRU rejected one in November 2021 (CRU/21/124), but its connection criteria and EirGrid's January 2022 statement that Dublin could take no new connections until about 2028 worked as a de facto pause. The CRU's December 2025 decision replaced it with a bring-your-own-power route.

Updated 3 October 2026 · data build 2026-10-10 · how we know · corrections

The moratorium, and what replaced it

Figure 1

From open door to moratorium to 'bring your own power'

The de facto moratorium stopped new grid contracts from Nov 2021, but data centres' share of electricity kept climbing, from 14.1% in 2021 to 23.2% in 2025, as sites contracted earlier were built out.

Data-centre policy phases in Ireland since 2017, against data centres' share of metered electricityPhases: Open door (2017-10 to 2019-06); Managed constraint (2019-06 to 2021-11); De facto moratorium (2021-11 to 2025-12); Bring your own power (and renewables) (2025-12 to present); Plan-led energy parks (announced) (2026-01 to 2030s). Data centres' share of metered electricity rose from 5% in 2015 to 23.2% in 2025. Turning points: 7 Jun 2018 Government statement backs data centres as strategic infrastructure; 12 Jun 2019 EirGrid's first data-centre connection policy names Dublin as constrained; 27 May 2021 EirGrid writes to the CRU asking it to act; 23 Nov 2021 CRU direction: location and on-site generation tests for every new application; Jan 2022 EirGrid: no new data-centre connections in Dublin until about 2028; Jul 2022 Gas Networks Ireland stops contracting new data-centre gas connections; 27 Jul 2022 Revised Government statement: not all demand can be met; 12 Dec 2025 CRU decision: bring your own power, match 80% with new renewables; 13 Jan 2026 Large Energy User Action Plan points to energy parks after 2030; 10 Mar 2026 Judicial review lodged against the CRU decision; 20 May 2026 EirGrid DCCOPP v3: Dublin fully constrained, little room elsewhere; Jun 2026 Data-centre demand fills the grid's 900 MW load-rejection limit; 22 Sep 2026 CRU approves fault ride-through rule MPID 345, with caps on existing sites; 27 Oct 2026 MPID 345 takes effect.DATA CENTRES' SHARE OF METERED ELECTRICITY (CSO), BY YEAR2015: data centres 5.0% of metered electricity (1.2 TWh)2016: data centres 5.8% of metered electricity (1.5 TWh)2017: data centres 6.8% of metered electricity (1.8 TWh)2018: data centres 8.2% of metered electricity (2.2 TWh)2019: data centres 9.4% of metered electricity (2.5 TWh)2020: data centres 11.2% of metered electricity (3.0 TWh)2021: data centres 14.1% of metered electricity (4.0 TWh)2022: data centres 17.7% of metered electricity (5.3 TWh)2023: data centres 20.7% of metered electricity (6.3 TWh)2024: data centres 21.9% of metered electricity (7.0 TWh)2025: data centres 23.2% of metered electricity (7.7 TWh)5%6%7%8%9%11%14%18%21%22%23%nowOpen doorManagedconstraintDe facto moratoriumEnergy parks (announced), 2030s201520182021202420272030Black band: Bring your own power, since Dec 2025The turning points7 Jun 2018Government statement backs data centres as strategic infrastructure12 Jun 2019EirGrid's first data-centre connection policy names Dublin as constrained27 May 2021EirGrid writes to the CRU asking it to act23 Nov 2021CRU direction: location and on-site generation tests for every new applicationJan 2022EirGrid: no new data-centre connections in Dublin until about 2028Jul 2022Gas Networks Ireland stops contracting new data-centre gas connections27 Jul 2022Revised Government statement: not all demand can be met12 Dec 2025CRU decision: bring your own power, match 80% with new renewables13 Jan 2026Large Energy User Action Plan points to energy parks after 203010 Mar 2026Judicial review lodged against the CRU decision20 May 2026EirGrid DCCOPP v3: Dublin fully constrained, little room elsewhereJun 2026Data-centre demand fills the grid's 900 MW load-rejection limit22 Sep 2026CRU approves fault ride-through rule MPID 345, with caps on existing sites27 Oct 2026MPID 345 takes effect
Data-centre policy phases in Ireland since 2017, against data centres' share of metered electricityPhases: Open door (2017-10 to 2019-06); Managed constraint (2019-06 to 2021-11); De facto moratorium (2021-11 to 2025-12); Bring your own power (and renewables) (2025-12 to present); Plan-led energy parks (announced) (2026-01 to 2030s). Data centres' share of metered electricity rose from 5% in 2015 to 23.2% in 2025. Turning points: 7 Jun 2018 Government statement backs data centres as strategic infrastructure; 12 Jun 2019 EirGrid's first data-centre connection policy names Dublin as constrained; 27 May 2021 EirGrid writes to the CRU asking it to act; 23 Nov 2021 CRU direction: location and on-site generation tests for every new application; Jan 2022 EirGrid: no new data-centre connections in Dublin until about 2028; Jul 2022 Gas Networks Ireland stops contracting new data-centre gas connections; 27 Jul 2022 Revised Government statement: not all demand can be met; 12 Dec 2025 CRU decision: bring your own power, match 80% with new renewables; 13 Jan 2026 Large Energy User Action Plan points to energy parks after 2030; 10 Mar 2026 Judicial review lodged against the CRU decision; 20 May 2026 EirGrid DCCOPP v3: Dublin fully constrained, little room elsewhere; Jun 2026 Data-centre demand fills the grid's 900 MW load-rejection limit; 22 Sep 2026 CRU approves fault ride-through rule MPID 345, with caps on existing sites; 27 Oct 2026 MPID 345 takes effect.DC SHARE OF METERED ELECTRICITY (CSO)2015: data centres 5.0% of metered electricity (1.2 TWh)2016: data centres 5.8% of metered electricity (1.5 TWh)2017: data centres 6.8% of metered electricity (1.8 TWh)2018: data centres 8.2% of metered electricity (2.2 TWh)2019: data centres 9.4% of metered electricity (2.5 TWh)2020: data centres 11.2% of metered electricity (3.0 TWh)2021: data centres 14.1% of metered electricity (4.0 TWh)2022: data centres 17.7% of metered electricity (5.3 TWh)2023: data centres 20.7% of metered electricity (6.3 TWh)2024: data centres 21.9% of metered electricity (7.0 TWh)2025: data centres 23.2% of metered electricity (7.7 TWh)5%7%9%14%21%23%nowManagedMoratoriumEnergy parks20152018202120242027Last band: Open door, since Oct 2017Black band: Bring your own power, since Dec 2025The turning points7 Jun 2018Government statement backs data centresas strategic infrastructure12 Jun 2019EirGrid's first data-centre connectionpolicy names Dublin as constrained27 May 2021EirGrid writes to the CRU asking it toact23 Nov 2021CRU direction: location and on-sitegeneration tests for every newapplicationJan 2022EirGrid: no new data-centre connectionsin Dublin until about 2028Jul 2022Gas Networks Ireland stops contractingnew data-centre gas connections27 Jul 2022Revised Government statement: not alldemand can be met12 Dec 2025CRU decision: bring your own power,match 80% with new renewables13 Jan 2026Large Energy User Action Plan points toenergy parks after 203010 Mar 2026Judicial review lodged against the CRUdecision20 May 2026EirGrid DCCOPP v3: Dublin fullyconstrained, little room elsewhereJun 2026Data-centre demand fills the grid's 900MW load-rejection limit22 Sep 2026CRU approves fault ride-through ruleMPID 345, with caps on existing sites27 Oct 2026MPID 345 takes effect

The top panel draws each policy phase to scale behind the CSO's yearly figure for data centres' share of metered electricity, which rose from 5% in 2015 to 23.2% in 2025. The moratorium was never a law: it was the CRU's November 2021 direction plus EirGrid's Dublin pause, under which only one new data centre was contracted by mid-2025. The CRU's December 2025 decision replaced it with a demanding route, and in 2026 a new constraint appeared: the grid's limit on how much demand it can lose in a fault, answered by the MPID 345 ride-through rule. Energy parks after 2030 are announced, not built.

Sources: Policy timeline from primary documents (CRU, EirGrid, DETE, DCEE), 2026-10-03 · CSO MEC02, 2026-07-07 · CRU202704, CRU2026145, 2026-09-22

The new limit: how much demand the grid can lose

Figure 2

Why the grid can only lose 900 MW at once

In a voltage dip data centres can drop off the grid in milliseconds. EirGrid plans for a worst case in which 90% of their demand goes at once (recorded faults dropped 16–52%), so about 1,000 MW of data centres fills the 900 MW limit, and that happened in Jun 2026.

What a voltage dip does to data-centre demand, and the 900 MW limitFour steps: a grid fault dips the voltage; data centres switch to back-up power and about 90% of their demand drops off; frequency rises; they reconnect. Below, a bar shows peak data-centre demand of about 1,000 MW, of which 900 MW could drop, filling the 900 MW load-rejection limit. Then four measures EirGrid uses to stay inside it.01 · 0 MSvoltageA fault on the gridA short circuit on ahigh-voltage line pulls thevoltage down for a fractionof a second. 4 of the 5faults EirGrid has reportedwere in Dublin.02 · MILLISECONDSdata-centre grid demandData centres let goTo protect their servers,sites switch to batteries(UPS) and back-up generators.In some faults, EirGridestimates, up to 90% could goat once.03 · NEXT SECONDSfrequency (50 Hz dashed)Frequency jumpsSupply now exceeds demand, sofrequency rises above 50 Hz.Plant must ride throughchanges up to ±1 Hz/s.04 · THENdemand returns in a rushThey come backSites reconnectautomatically: a second jolt.The CRU's December 2025decision records EirGrid'sconcern that this makesdisturbances worse.The budget: how much demand the grid can lose in one goData-centre demand peaked at about 1,000 MW in late June 2026 (EirGrid to the CRU, CRU202704).90% of 1,000 MW = 900 MW that a single fault could take off the grid.900 MW could drop (90%)limit 900 MWpeak data-centre demand ~1,000 MW (Jun 2026)Reached in Jun 2026. Interconnector exports count against the same 900 MW, so EirGrid cuts exports when data-centredemand is high. A 100 MW campus without ride-through would add about 90 MW to the budget.How EirGrid stays inside it (week 42, 2026)28,000 MWsInertia floorwas 23,000; morespinning plant kept on75%SNSP capinstant share of wind,solar and HVDC imports;80% trial paused200 MWBattery charging capkept as a shockabsorberExports cutInterconnector exportscount against the samelimit
What a voltage dip does to data-centre demand, and the 900 MW limitFour steps: a grid fault dips the voltage; data centres switch to back-up power and about 90% of their demand drops off; frequency rises; they reconnect. Below, a bar shows peak data-centre demand of about 1,000 MW, of which 900 MW could drop, filling the 900 MW load-rejection limit. Then four measures EirGrid uses to stay inside it.01 · 0 MSvoltageA fault on the gridA short circuit on ahigh-voltage line pulls thevoltage down for a fractionof a second. 4 of the 5faults EirGrid has reportedwere in Dublin.02 · MILLISECONDSdata-centre grid demandData centres let goTo protect their servers,sites switch to batteries(UPS) and back-upgenerators. In some faults,EirGrid estimates, up to90% could go at once.03 · NEXT SECONDSfrequency (50 Hz dashed)Frequency jumpsSupply now exceeds demand,so frequency rises above 50Hz. Plant must ride throughchanges up to ±1 Hz/s.04 · THENdemand returns in a rushThey come backSites reconnectautomatically: a secondjolt. The CRU's December2025 decision recordsEirGrid's concern that thismakes disturbances worse.The budget: what the grid can lose at onceData-centre demand peaked at about 1,000 MW in late June 2026 (EirGrid to the CRU, CRU202704).90% of 1,000 MW = 900 MW that a single fault could take off the grid.900 MW could drop (90%)limit 900 MWpeak data-centre demand ~1,000 MW (Jun 2026)Reached in Jun 2026. Interconnector exports count againstthe same 900 MW, so EirGrid cuts exports when data-centredemand is high. A 100 MW campus without ride-through wouldadd about 90 MW to the budget.How EirGrid stays inside it (week 42, 2026)28,000 MWsInertia floorwas 23,000; morespinning plant kept on75%SNSP capinstant share of wind,solar and HVDC imports;80% trial paused200 MWBattery charging capkept as a shock absorberExports cutInterconnector exportscount against the samelimit

When a fault dips the voltage, data centres protect their servers by switching to on-site batteries and generators, so their demand can vanish from the grid in milliseconds and frequency jumps. EirGrid's weekly operating rules cap the demand and exports the system can lose in one event at 900 MW; planning for 90% of data-centre demand at risk, roughly 1,000 MW of data centres uses it all, and EirGrid told the CRU that peak was reached in late June 2026. To stay inside the limit EirGrid keeps more spinning plant on (inertia floor 28,000 MWs), caps the instantaneous share of wind, solar, batteries and HVDC imports (SNSP) at 75%, limits battery charging and cuts interconnector exports. The step sketches are schematic, not measured traces.

Estimate"A 100 MW campus adds about 90 MW" is our arithmetic with EirGrid's 90% assumption.

Sources: EirGrid/SONI Weekly Operational Constraints Update, week 42 2026, 2026-10-09 · CRU202704 (EirGrid figures: ~1,000 MW peak, 90% drop, limit reached), 2026-07-08 · CRU202705, EirGrid FRT update, 2026-06-26 · CRU/2025/236 s.5.1.7, 2025-12-12

Figure 3

The fix: ride through faults, or accept a cap, until about October 2028

From 27 Oct 2026 every transmission-connected data centre must stay on through grid faults. Most can't yet, so each gets a capped allowance of non-compliant demand until about 27 Oct 2028, and the 900 MW limit itself stays.

The MPID 345 fault ride-through rule: timeline to October 2028 and how the cap is sized12 Dec 2025: CRU flags the problem. 9 Jan 2026: 900 MW limit appears. 1 Apr 2026: EirGrid proposes MPID 345. 8 May 2026: Inertia floor raised. Jun 2026: Limit reached. 8 Jul 2026: CRU asks for more views. 22 Sep 2026: CRU approves MPID 345. 27 Oct 2026: Rule in force. 27 Apr 2027: Compliance plans due. 27 Oct 2028: Group derogation ends. The aggregate cap: 900 MW limit divided by the demand loss factor gives about 1,000 MW of non-compliant data-centre demand, less allowances for distribution sites, a peak margin and 2026 connections, whose sizes are not published.NOT TO SCALE · EVENTS IN ORDER12 Dec 2025CRU flags the problemThe large-energy-user decision recordsEirGrid's concern that data centres droppingoff and reconnecting worsens faults.9 Jan 2026900 MW limit appearsFirst listed in EirGrid's weekly operatingconstraints (absent in the December 2025edition).1 Apr 2026EirGrid proposes MPID 345A Grid Code rule for alltransmission-connected demand: ride throughfaults, withstand ±1 Hz/s, recover 90% ofdemand within 500 ms.8 May 2026Inertia floor raisedTo 28,000 MWs, using two new synchronouscondensers.Jun 2026Limit reachedData-centre demand peaks at about 1,000 MW;exports already cut.8 Jul 2026CRU asks for more viewsThree options for setting each site's cap;closed 29 July 2026.22 Sep 2026CRU approves MPID 345With a derogation framework that caps eachexisting site's non-compliant demand.27 Oct 2026Rule in forceSites must report non-compliance and apply fora derogation before this date.~27 Apr 2027Compliance plans due (our arithmetic)Data centres file a plan within 6 months.~27 Oct 2028Group derogation ends (our arithmetic)The 24-month derogation for data centresconnected before end-2026 runs out.as of 9 Oct 2026How the cap on existing sites is sizedCRU2026145b, the derogation framework900 MWload-rejection limit (unchanged)÷ demand loss factor (not published)~1,000 MWmost non-compliant demand allowedminus three allowances, sizes not published?distribution−?peak margin−?2026 sites= shared out as one cap (DUT) per siteOne DUT per sitevalues not publishedEach transmission-connected data centre's DUT= its highest 2025 monthly-average demand + apro-rata share of any headroom. Peaks up toDUT +10% are allowed; it is measured on30-minute metering. Compliant demand is notcapped.
The MPID 345 fault ride-through rule: timeline to October 2028 and how the cap is sized12 Dec 2025: CRU flags the problem. 9 Jan 2026: 900 MW limit appears. 1 Apr 2026: EirGrid proposes MPID 345. 8 May 2026: Inertia floor raised. Jun 2026: Limit reached. 8 Jul 2026: CRU asks for more views. 22 Sep 2026: CRU approves MPID 345. 27 Oct 2026: Rule in force. 27 Apr 2027: Compliance plans due. 27 Oct 2028: Group derogation ends. The aggregate cap: 900 MW limit divided by the demand loss factor gives about 1,000 MW of non-compliant data-centre demand, less allowances for distribution sites, a peak margin and 2026 connections, whose sizes are not published.NOT TO SCALE · EVENTS IN ORDER12 Dec 2025CRU flags the problemThe large-energy-user decision recordsEirGrid's concern that data centresdropping off and reconnecting worsensfaults.9 Jan 2026900 MW limit appearsFirst listed in EirGrid's weeklyoperating constraints (absent in theDecember 2025 edition).1 Apr 2026EirGrid proposes MPID 345A Grid Code rule for alltransmission-connected demand: ridethrough faults, withstand ±1 Hz/s,recover 90% of demand within 500 ms.8 May 2026Inertia floor raisedTo 28,000 MWs, using two new synchronouscondensers.Jun 2026Limit reachedData-centre demand peaks at about 1,000MW; exports already cut.8 Jul 2026CRU asks for more viewsThree options for setting each site'scap; closed 29 July 2026.22 Sep 2026CRU approves MPID 345With a derogation framework that capseach existing site's non-compliantdemand.27 Oct 2026Rule in forceSites must report non-compliance andapply for a derogation before this date.~27 Apr 2027Compliance plans due (our arithmetic)Data centres file a plan within 6months.~27 Oct 2028Group derogation ends (our arithmetic)The 24-month derogation for data centresconnected before end-2026 runs out.as of 9 Oct 2026How the cap on existing sites is sizedCRU2026145b, the derogation framework900 MWload-rejection limit (unchanged)÷ demand loss factor (not published)~1,000 MWmost non-compliant demand allowedminus three allowances, sizes not published?distribution−?peak margin−?2026 sites= shared out as one cap (DUT) per siteOne DUT per sitevalues not publishedEach transmission-connected data centre's DUT = itshighest 2025 monthly-average demand + a pro-rata shareof any headroom. Peaks up to DUT +10% are allowed; it ismeasured on 30-minute metering. Compliant demand is notcapped.

The CRU approved Grid Code modification MPID 345 on 22 Sep 2026; it takes effect on 27 Oct 2026 and applies to all current and future transmission-connected demand, data centre or not. A compliant site must stay connected through a fault, withstand frequency changes of ±1 Hz/s and recover 90% of its demand within 500 milliseconds. Existing data centres get a 24-month group derogation, with a compliance plan due within six months, and meanwhile each has a Demand Utilisation Threshold (DUT) capping its non-compliant demand. The caps are sized from the load-rejection limit, but EirGrid has not published the demand loss factor, the allowances or any site's DUT; distribution-connected sites wait for an ESB Networks code change that is not yet public.

EstimateCompliance-plan and derogation-end dates are our arithmetic from the effective date (+6 and +24 months).

Sources: CRU2026145, Grid Code Modification MPID 345 and Compliance and Derogation Framework: Decision Paper, 2026-09-22 · CRU2026145b, EirGrid MPID 345 Compliance and Derogation Framework (Sept 2026, as decided), 2026-09-22 · CRU2026145c, CRU letter of direction to the GCRP chair (also on eirgrid.ie as 'MPID345 CRU Approval, effective 27/10/2026'), 2026-09-22 · CRU202704, 2026-07-08

How the de facto moratorium happened, and ended

DateWhoWhat changed
2021-05-27EirGridEirGrid letter to CRU: 'Ireland's Data Centres – Next Steps'
Triggered the CRU process that produced CRU/21/060 (June 2021) and CRU/21/124 (Nov 2021).
2021-07DETEDETE submission to CRU consultation CRU/21/060
Government's enterprise arm publicly opposed a moratorium; the CRU's November 2021 decision followed that line.
2021-11-23CRUCRU/21/124: Direction to the System Operators related to Data Centre grid connection processing
In practice a near-moratorium in Dublin: almost all subsequent growth came from capacity contracted before the direction, and EirGrid reported only one new data centre contracted under these criteria by its June 2025 data freeze. Gas-fired on-site generation (to be hydrogen/biomethane-ready) became the expected route; units over 10 MW fall under secondary-fuel and capacity-market rules.
2022-01EirGridEirGrid: no new data-centre connections in Dublin until about 2028
Turned the CRU criteria into an explicit Dublin pause; pipeline projects not yet contracted were stranded or moved toward gas, private wires or regional sites.
2022-07-27Government (DETE)Revised Government Statement on the Role of Data Centres in Ireland's Enterprise Strategy
Became the reference for planning authorities, the CRU and GNI: GNI stopped contracting new data-centre gas connections beyond the 11 already contracted; councils began citing the principles; the CRU's later 80% renewable requirement draws on 'renewables additionality'.
2023-06-21CRUCall for Evidence: Review of Large Energy Users Connection Policy (CRU202357)
Started the 30-month process that ended in CRU2025236. Meanwhile CRU/21/124 stayed in force.
2023-10-04Gas Networks Ireland / CRUGNI s.39A application to CRU for Microsoft Grange Castle gas line
Shows the mechanism: DCCOPP flexible demand plus CRU/21/124 pushed hyperscalers to on-site gas; contracts signed before the July 2022 pause still proceed.
2023-11-15CRUCRU opening statement to the Oireachtas Climate Committee on data-centre connections
Showed the regulator wanted emissions conditions to sit in planning or legislation rather than in its own connection policy.
2024-01-15CRUConsultation on Review of Large Energy Users Connection Policy (CRU2024001)
Nothing binding; framed the problem as emissions (Climate Act) as well as security of supply.
2025-02-18CRUProposed Decision on Large Energy Users Connection Policy (CRU202504)
Shift from 'back-up for yourself' to 'bring new capacity for the system'; emissions requirements dropped to reporting only (later reversed in the final decision).
2025-12-12CRULarge Energy Users Connection Policy decision (CRU2025236)
Ended the open-ended near-moratorium with a defined, demanding route: a data centre now comes as a package of demand plus a gas plant (or storage) plus new wind/solar PPAs. No change for gas connections; an interruptible gas product is to be consulted on separately. SOs had to publish processes by 31 March 2026.
2026-01-13DETE / DCEELarge Energy User Action Plan (LEAP)
Shifts the long-term answer from 'connect where the grid is' to 'build the grid and generation where the user will be', but mostly post-2030. Widely reported as ending the Dublin 'ban', though the electricity constraint is unchanged.
2026-03-10Friends of the Irish Environment, Friends of the Earth Ireland, ClientEarthJudicial review lodged against CRU2025236
EirGrid's DCCOPP v3 warns applicants that they proceed at their own risk while the case is pending.
2026-05-20EirGridDCCOPP v3, Data Centre Technical Assessment and Constrained Area Overview
The door reopened on paper but the map is small: perhaps 150-300 MW nationally outside Dublin versus about 6 GW of expressed interest. In Dublin the required on-site gas generation itself worsens short-circuit levels, so the policy cannot work there until 400 kV reinforcement.
2026-06-25CRUCRU202657: proposed direction on interruptible gas connections
Proposal only (consultation closed August 2026; no decision as of early September 2026). If adopted, data-centre gas becomes non-firm unless it is a market generator, reinforcing the LEU design.

Read from the primary documents. Full timeline on the policy page.

Capacity contracted before the rules changed

38–46%
Of contracted grid capacity actually used, 2025
875 MW average vs 2,000–2,400 MVA
1–1.4 GW
Unused capacity already contracted
growth needing no new contract
1,948 MVA
Protected when the 2021 rules came in
1,884 MVA of it in Dublin
1
New data-centre contract under the 2021 rules
EirGrid
The moat the rules created. Freezing new connections protected whoever already held contracts. They are using well under half of what they hold, so existing operators can roughly double their draw while newcomers wait.

Unused capacity we can tie to named sites (MW)

Amazon (AWS) Cruiserath151
Microsoft Huntstown150
Meta Clonee45
Amazon (AWS) Belgard, Tallaght37

Only Amazon Cruiserath publishes both a contract (240 MVA, 2017) and its 2025 draw. Others compare draw with demand stated in planning or EPA papers, which is not a contract. Average draw understates peak use. MVA converted at power factor 0.95.

EirGrid AIRAA 2026–35 and Constrained Area Overview (May 2026) · CRU/21/124 · EPA annual reports · CSO · quotes checked · as of 2026-10-03

Questions people ask

Did data centres stop growing after 2021?
No. Data-centre electricity use kept rising, to 7.7 TWh in 2025 (+9.9% on 2024, CSO), as existing sites filled capacity contracted before the rules changed.