Data centre · Fingal · 53.4932, -6.2009
Turvey, Donabate (operator not identified)
lapsed Not identified Our classification · status
Not available for this site: measured grid draw (no EPA annual report: only sites with ≥50 MWth of plant file one); mapped footprint; rates (no valuation-list entry matched).
Why we say it's lapsed
- Planning F15A/0266: lapsed without commencement notice
- Planning F16A/0189: expired (no commencement notice of its own; works may sit under the parent permission)
Who runs it









Leaflet © OpenStreetMap contributors
Planning history
| Received | Ref | What | Decision | Built? |
|---|---|---|---|---|
| 2015-09-22 | F15A/0266 | Construction of a Data Centre development consisting of 5 no. single storey data halls (circa 925sq.m. each), with associated single storey electrical service rooms and loading bay (circa 2407 sq.m.) | GRANT PERMISSION | lapsed without commencement notice |
Appeal 245778 (F15A/0266) · no decision recorded
Sources for this page
planning:FINGAL/F15A/0266 · planning:FINGAL/F16A/0189 · acp:245778
Joined from OpenStreetMap, the planning register, An Coimisiún Pleanála, EPA licences and annual reports, the Tailte Éireann valuation list and Building Control. Data built 2026-10-10.