Data centre · Fingal · 53.4932, -6.2009

← All data centres

Turvey, Donabate (operator not identified)

lapsed Not identified Our classification · status

Not available for this site: measured grid draw (no EPA annual report: only sites with ≥50 MWth of plant file one); mapped footprint; rates (no valuation-list entry matched).

Why we say it's lapsed

  • Planning F15A/0266: lapsed without commencement notice
  • Planning F16A/0189: expired (no commencement notice of its own; works may sit under the parent permission)

Who runs it

    Leaflet © OpenStreetMap contributors

    Planning history

    ReceivedRefWhatDecisionBuilt?
    2015-09-22F15A/0266
    Construction of a Data Centre development consisting of 5 no. single storey data halls (circa 925sq.m. each), with associated single storey electrical service rooms and loading bay (circa 2407 sq.m.)
    GRANT PERMISSIONlapsed without commencement notice
    Appeal 245778 (F15A/0266) · no decision recorded

    Sources for this page

    planning:FINGAL/F15A/0266 · planning:FINGAL/F16A/0189 · acp:245778

    Joined from OpenStreetMap, the planning register, An Coimisiún Pleanála, EPA licences and annual reports, the Tailte Éireann valuation list and Building Control. Data built 2026-10-10.