What is the 900 MW load-rejection limit?
Every week EirGrid and SONI publish the operating limits they run the all-island system to. Since the update of 9 January 2026 one of them reads "Maximum total system load rejection": 900 MW. It is not in the update of 2 January 2026 (2026 week 2); the weeks in between were not found online. The latest update, week 42 of 2026 (published 9 October 2026), still lists it.
"Load rejection" means demand vanishing from the grid. Lose too much at once and generators speed up, frequency rises and protection can trip plant. The limit covers data centres and other large users together with power being exported on the interconnectors, because losing an export looks the same to the system as losing demand.
Why data centres fill it
When a fault dips the voltage, a data centre protects its servers by switching to its own batteries and generators. To the grid, its demand disappears in milliseconds and comes back later. EirGrid plans for a worst case in which 90% of all data-centre demand goes at once. At a data-centre peak of about 1,000 MW, 90% is 900 MW: the whole limit.
"the 900 MW load rejection limit was reached" (CRU202704)
Real faults have not yet reached that worst case, but each one has taken more demand off the grid:
| Date | Fault | Data-centre demand lost, MW | Share of data-centre demand |
|---|---|---|---|
| 7 January 2022 | Limerick: Killonan-Kilpaddoge 220 kV Fault | 74 | 16% |
| 13 December 2022 | Dublin: Kellystown-Woodland 220 kV Fault | 204 | 34% |
| 26 January 2025 | Dublin: Poolbeg 220 kV Reactor Fault | 321 | 44% |
| 8 May 2025 | Dublin: North Wall – Poolbeg 220 kV Fault | 387 | 52% |
| 6 June 2026 | Dublin: Poolbeg 220 kV Reactor Fault | 480 | 52% |
EirGrid figures as tabled in CRU202704 (Table 1), 8 July 2026.
Why the grid can only lose 900 MW at once
In a voltage dip data centres can drop off the grid in milliseconds. EirGrid plans for a worst case in which 90% of their demand goes at once (recorded faults dropped 16–52%), so about 1,000 MW of data centres fills the 900 MW limit, and that happened in Jun 2026.
When a fault dips the voltage, data centres protect their servers by switching to on-site batteries and generators, so their demand can vanish from the grid in milliseconds and frequency jumps. EirGrid's weekly operating rules cap the demand and exports the system can lose in one event at 900 MW; planning for 90% of data-centre demand at risk, roughly 1,000 MW of data centres uses it all, and EirGrid told the CRU that peak was reached in late June 2026. To stay inside the limit EirGrid keeps more spinning plant on (inertia floor 28,000 MWs), caps the instantaneous share of wind, solar, batteries and HVDC imports (SNSP) at 75%, limits battery charging and cuts interconnector exports. The step sketches are schematic, not measured traces.
Estimate"A 100 MW campus adds about 90 MW" is our arithmetic with EirGrid's 90% assumption.
Sources: EirGrid/SONI Weekly Operational Constraints Update, week 42 2026, 2026-10-09 · CRU202704 (EirGrid figures: ~1,000 MW peak, 90% drop, limit reached), 2026-07-08 · CRU202705, EirGrid FRT update, 2026-06-26 · CRU/2025/236 s.5.1.7, 2025-12-12
What EirGrid does to stay inside it
The limit is full, so EirGrid manages the system more tightly. In its own operating updates and its June 2026 report to the CRU (CRU202705):
- More spinning plant. The inertia floor rose from 23,000 to 28,000 MWs in the update of 8 May 2026, using two new synchronous condensers.
- Less wind at the margin. The planned trial of raising the instantaneous share of wind, solar, batteries and imports (SNSP) from 75% to 80% was paused; the cap stays at 75%.
- Batteries held back. System-wide battery charging is limited to 200 MW so storage can absorb power when data centres drop.
- Exports cut. Interconnector exports count toward the same limit, so EirGrid counter-trades to reduce them, including exports of surplus wind.
The CRU also notes that EirGrid issued a fault ride-through demand-curtailment procedure to affected users on 30 June 2026. No data on its use has been published.
What MPID 345 changes
On 22 September 2026 the CRU approved Grid Code modification MPID 345 (CRU2026145). The Grid Code is amended five weeks later, on 27 October 2026. It applies to every current and future demand facility connected to the transmission system, data centre or not.
"must remain connected and operate stably during and after any fault disturbance" (CRU2026145, p.17 (printed 7))
- Ride through faults, withstand frequency changes of ±1 Hz/s, and recover 90% of pre-fault demand within 500 milliseconds.
- Report and apply. Non-compliant sites must report and seek a derogation before 27 October 2026.
- Compliance plans from existing data centres within six months (by about Apr 2027, our arithmetic). Their group derogation runs 24 months, to about Oct 2028.
- A cap per site. Each transmission-connected data centre gets a Demand Utilisation Threshold (DUT): a monthly-average cap on its non-compliant demand, set at its highest 2025 monthly average plus a share of any headroom. Peaks up to 10% above it are allowed.
The decision does not raise the 900 MW limit. It shares it out. The total of all caps is the limit divided by a "demand loss factor", which EirGrid has not published, less allowances for distribution-connected sites, peaks and 2026 connections.
The fix: ride through faults, or accept a cap, until about October 2028
From 27 Oct 2026 every transmission-connected data centre must stay on through grid faults. Most can't yet, so each gets a capped allowance of non-compliant demand until about 27 Oct 2028, and the 900 MW limit itself stays.
The CRU approved Grid Code modification MPID 345 on 22 Sep 2026; it takes effect on 27 Oct 2026 and applies to all current and future transmission-connected demand, data centre or not. A compliant site must stay connected through a fault, withstand frequency changes of ±1 Hz/s and recover 90% of its demand within 500 milliseconds. Existing data centres get a 24-month group derogation, with a compliance plan due within six months, and meanwhile each has a Demand Utilisation Threshold (DUT) capping its non-compliant demand. The caps are sized from the load-rejection limit, but EirGrid has not published the demand loss factor, the allowances or any site's DUT; distribution-connected sites wait for an ESB Networks code change that is not yet public.
EstimateCompliance-plan and derogation-end dates are our arithmetic from the effective date (+6 and +24 months).
Sources: CRU2026145, Grid Code Modification MPID 345 and Compliance and Derogation Framework: Decision Paper, 2026-09-22 · CRU2026145b, EirGrid MPID 345 Compliance and Derogation Framework (Sept 2026, as decided), 2026-09-22 · CRU2026145c, CRU letter of direction to the GCRP chair (also on eirgrid.ie as 'MPID345 CRU Approval, effective 27/10/2026'), 2026-09-22 · CRU202704, 2026-07-08
What about sites on ESB Networks' system?
MPID 345 covers only transmission connections. Checked on 3 October 2026, no matching Distribution Code change is public. The CRU says ESB Networks:
"intends to propose a related modification to the Distribution Code, to address the FRT risk at a distribution level and has commenced customer engagement" (CRU2026145, p.44 (printed 34))
esbnetworks.ie still lists Distribution Code v8.0 (approved February 2023), whose ride-through rules cover generation, not demand. At the Grid Code panel the distribution operator said a MW threshold may be needed. EirGrid's November 2025 information paper put about 150 MW of a roughly 800 MW data-centre peak on the distribution system. No site list is public.
What is not known
- Which campuses define the limit: EirGrid has not published site-level data-centre demand, DUT values or which connections are curtailed. Only the aggregate (~1,000 MW peak, June 2026) is public.
- Site-level DUTs: EirGrid has set one per transmission-connected data centre (2025 highest monthly average plus a pro-rata share of headroom) but has not published the values, the demand loss factor or the aggregate DUT.
- How many sites have applied for derogations, and compliance rates: EirGrid reports these to the CRU quarterly (first report due end December 2026); publication of those reports is not stated.
Why it matters
Our reading. Grid capacity on paper is no longer the only limit. Until sites can ride through faults, every new megawatt of data-centre demand also uses up room under a fixed 900 MW ceiling. On EirGrid's 90% assumption a 200 MW campus would take about 180 MW, 20% of the whole limit. The pace at which existing sites become compliant will shape how quickly that room reopens, and the CRU has asked EirGrid for a roadmap for easing the operating measures.
The cost of the measures (extra spinning plant, curtailed wind, exports cut) falls on the system as a whole. EirGrid and the CRU have not published a figure for it.