The data-centre grid capacity nobody is using yet

Irish data centres hold about 2.0–2.4 GW of contracted grid capacity, nearly all agreed before the November 2021 rules, but drew an average of 875 MW in 2025. That leaves roughly 1.0–1.4 GW unused (EirGrid; CSO, Jul 2026). Newcomers, meanwhile, face a frozen Dublin grid.

By StackPath · published 3 October 2026 · updated 3 October 2026 · how we know · corrections

Is there a data centre moratorium in Ireland?

Not in law. In November 2021 the CRU directed that new data-centre connection requests be judged on location, on-site generation matching demand, and flexibility (CRU/21/124). In Dublin that stopped new contracts. EirGrid later counted one new data centre contracted under those rules by mid-2025 (AIRAA 2026–35, p.14). In May 2026 it described Dublin as "fully constrained".

Yet data-centre electricity use kept rising: 9.9% in 2025 alone, to 7.7 TWh (CSO). The freeze stopped new entrants. It did not stop growth.

2.4 GW
Contracted to data centres and other new loads
EirGrid AIRAA 2026–35
875 MW
Average draw, 2025
CSO GWh ÷ 8,760 h
38–46%
Share of contracted capacity in use
StackPath estimate
1.0–1.4 GW
Unused headroom
StackPath estimate

How much grid capacity do data centres hold?

Three public figures, from three dates, tell the same story:

SourceWhat it countsMVA
CRU/21/124 (Nov 2021)Connected931
CRU/21/124 (Nov 2021)Contracted, not yet connected1,017
CRU/21/124 (Nov 2021)Total exempt from the direction (Dublin: 1,884)1,948
EirGrid Constrained Area Overview (May 2026)Contracted data centres2,000
EirGrid AIRAA 2026–35Contracted, incl. some other new-technology loads2,400

EirGrid's own figures agree. It put data-centre demand at 959 MVA in 2024 against 2,400 MVA contracted, about 40%. Its median forecast for 2035 is 1,870 MVA, still below what is already contracted.

Capacity held before November 2021 is exempt from that direction. Almost all of it is in Dublin.

Figure 1

Grid capacity held by data centres, against what they actually draw

Data centres drew an average of 875 MW in 2025 but hold contracts for about 1.9 GW (2.3 GW counting other new loads): only 38–46% is in use. On paper that leaves room to grow under contracts signed before the 2021 rules, but the grid's 900 MW load-rejection limit and the MPID 345 caps now restrict how much more sites that can't ride through faults may draw.

Grid capacity held by data centres vs power drawnData centres used 7,662 GWh in 2025, an average draw of 875 MW. Contracted grid capacity is 2,000–2,400 MVA, about 1,900–2,280 MW usable, so 38–46% is in use.0 MW5001,0001,5002,0002,400 MVA × 0.95 = 2,280 MW usable2,400 MVA contracteddata centres + other new loads (EirGrid AIRAA)2,000 MVA × 0.95 = 1,900 MW usable2,000 MVA contracteddata centres only (EirGrid, May 2026)14.6 TWh ÷ 8,760 h = 1,667 MW averageEirGrid 2034 forecast14.6 TWh a year as an average7,662 GWh ÷ 8,760 h = 875 MW875 MW average draw, 20257,662 GWh ÷ 8,760 hours (CSO)Sum of 2025 average grid draw in EPA reports: 776.2 MW776 MW measured at 16 big sitesEPA annual environmental reports, 2025≈1.0–1.4 GW held but unused38–46% of contracted capacity in use
Grid capacity held by data centres vs power drawnData centres used 7,662 GWh in 2025, an average draw of 875 MW. Contracted grid capacity is 2,000–2,400 MVA, about 1,900–2,280 MW usable, so 38–46% is in use.0 MW5001,0001,5002,0002,400 MVA × 0.95 = 2,280 MW usable2,400 MVA contracteddata centres + other new loads (EirGrid AIRAA)2,000 MVA × 0.95 = 1,900 MW usable2,000 MVA contracteddata centres only (EirGrid, May 2026)14.6 TWh ÷ 8,760 h = 1,667 MW averageEirGrid 2034 forecast14.6 TWh a year as an average7,662 GWh ÷ 8,760 h = 875 MW875 MW average draw, 20257,662 GWh ÷ 8,760 hours (CSO)Sum of 2025 average grid draw in EPA reports: 776.2 MW776 MW measured at 16 big sitesEPA annual environmental reports, 2025≈1.0–1.4 GW held but unused38–46% of contracted capacity in use

Energy (GWh in a year) becomes average power (MW) by dividing by the hours in that year: 7,662 GWh ÷ 8,760 = 875 MW. The grey bars are grid capacity EirGrid reports as contracted to data centres, converted from MVA to MW at a power factor of 0.95. The gap between the red line and the end of the grey bar is capacity already promised to existing operators but not yet used; on paper even EirGrid's 14.6 TWh forecast for 2034 (about 1,667 MW on average) fits inside it, though for sites that can't ride through faults the grid's stability limit now binds before their contracts do. On top of this, the system operators' market sounding found about 5.8 GW of possible new data-centre demand. Big sites with EPA licences measured 776 MW of that draw themselves; peaks are higher than averages.

EstimateMVA-to-MW conversion, utilisation and unused headroom are StackPath estimates (3 Oct 2026); the 2034 average is EirGrid's TWh forecast divided by 8,760 hours.

Sources: CSO MEC02, 7 Jul 2026 · EirGrid All-Island Resource Adequacy Assessment 2026–2035, Dec 2025 · EirGrid Constrained Area Overview, May 2026 · EirGrid forecast as cited in CRU2025236, 12 Dec 2025 · EPA annual environmental reports, 3 Oct 2026

Who holds the unused capacity?

Public records name only part of it, about 384 MW:

CampusOperatorUnused MWMeasured against
Amazon (AWS) CruiserathAmazon (AWS)151contracted MIC
Microsoft HuntstownMicrosoft150stated demand (not a contract)
Meta CloneeMeta45stated demand (not a contract)
Amazon (AWS) Belgard, TallaghtAmazon (AWS)37stated demand (not a contract)

Amazon's Cruiserath campus holds a 240 MVA connection agreed in June 2017, before the rules changed, and ramped in annual steps to 2029. In 2025 it drew 76.6 MW on average (EPA annual environmental report).

The rest cannot be assigned site by site from public data. Contract sizes are not published.

Why it matters

Our reading. Incumbents hold a moat. Holders of pre-2021 capacity can keep growing into it with grid power. A newcomer needs its own dispatchable plant, 80% new Irish renewables and, in Dublin, a connection that EirGrid says cannot be progressed. Little new competition is likely before 2030.

It also explains forecasts. EirGrid's forecasts have data centres reaching about 32% of demand by 2030, largely on existing contracts (as reported; unchecked against the forecast document). The system operators' market sounding found about 5.8 GW of possible new demand on top (cited in CRU2025236).

For anyone reading a headline about a "moratorium", the useful question is not whether data centres can grow. It is who can.

Questions people ask

Is there a ban on new data centres in Ireland?
No legal ban. Since November 2021 new grid connections in Dublin have effectively stopped (one new contract by mid-2025, EirGrid), but data-centre electricity use still grew 9.9% in 2025 (CSO).
How much grid capacity do data centres have in Ireland?
About 2.0–2.4 GW is contracted (EirGrid, 2025–26), against an average draw of 875 MW in 2025.
Why is data-centre electricity use still rising?
Because existing operators are filling capacity they contracted before the 2021 rules. That capacity is exempt from the CRU direction.

How we know

  • Average draw = CSO annual data-centre GWh ÷ 8,760 hours. Usable capacity = contracted MVA × an assumed power factor of 0.95.
  • Named headroom compares a site's 2025 average grid draw (EPA annual environmental report) with its contracted capacity where public, or its stated demand in planning files where not. The last three rows are not contracts.

Sources

Numbers on this page are read from our data build of 10 October 2026 and update when it changes. Text marked Our reading is our analysis, not a sourced fact. Found a mistake? See corrections; method notes are on methodology.