Data centre · Dublin City · 53.4056, -6.2233

← All data centres

Amazon (AWS) Clonshaugh

operating Amazon (AWS) Our classification · status

144 MW
Average grid draw, 2025
up to ≈16.5% of the CSO data-centre total (upper bound)
964 MWth
On-site generation licensed
backup-diesel
8.3 ha
Building footprint mapped
8 buildings · OSM
€6.6m
Estimated rates a year
NAV €22.8m
2021
First completion certificate

Why we say it's operating

  • EPA P1171: on-site generators licensed and in use (Licensable Activity Commenced)
  • EPA P1186: on-site generators licensed and in use (Licensable Activity Commenced)
  • Valuation list: property 733234 rated as DATA CENTRE
  • Valuation list: property 10028867 rated as DATA CENTRE
  • Valuation list: property 5027088 rated as DATA CENTRE
  • Valuation list: property 5027089 rated as DATA CENTRE
  • Valuation list: property 5027086 rated as DATA CENTRE
  • Valuation list: property 5027087 rated as DATA CENTRE

What's next on this site

  • permitted: Planning 3400/19: commenced (no completion certificate on a main building yet)

Who runs it

  • EPA licensee 'Amazon Data Services Ireland Limited' -> Amazon (AWS) (operator; high-confidence entity link from EPA)
  • OSM operator tag 'Amazon Web Services'
  • valuation list address names it
  • some records attributed by co-location only (no operator in their own source)
Leaflet © OpenStreetMap contributors

Generators and power

EPA licenceStatusRoleMWthPlantPermitted hours
P1171Licensed · Licensable Activity Commencedbackup-diesel672.85103 x 6.49 MWth diesel standby + 2 x 2.19 MWth (plus 4 x 0.45 MWth fire pumps)72 h/yr; <=601.46 MWth simultaneously
P1186Licensed · Licensable Activity Commencedbackup-diesel290.9540 x 5.44 + 10 x 6.49 + 1 x 3.6 + 1 x 2.19 MWth diesel standby (plus fire pumps); up from 219.12 MWth after 2026 review150 h/yr at 100% load; <=248.11 MWth simultaneously (P1186-02)

What the annual environmental reports say

YearLicenceGrid MW avgOn-site fuel GJFull-load hours
2023*P117159.91,5420.6
2024P11711037,8443.2
2025P1171116.59,6234
2023*P118616.34,5324.3
2024P118627.31,6351.6
2025P118627.91,1491.1

* part year. Full-load hours = fuel burned ÷ the whole fleet at full load, a derived figure.

What the planning and licence documents say

Two adjoining EPA-licensed installations: P1171 (Buildings A-F, 105 generators) and P1186 (Buildings W, X, Y + U, V after the 2026 review); figures are P1171 unless noted, with P1186 given in notes.

SpecValueQuote and source
Grid voltage110 kV"The site includes the Newbury 110 kV Substation, which is owned and under the control of the ESB." EPA P1186-02: LA-IR P1186-02 Amazon.pdf, p.6
P1186 part of campus; extension (Buildings U, V) fed from a separate ESB substation
Connection pointNewbury 110 kV GIS substation (ESB), plus separate ESB substation for Buildings U/V"connection to an 110kV Gas Insulated Switchgear (GIS) Substation (Newbury Station)" EPA P1186-02: Attachment-1-2-Non Technical Summary_22.pdf, p.7
P1186 installation; P1171 substation not named
On-site generationbackup diesel generators"there will be 103 no. 6.49 MWth diesel generators at the installation" EPA P1171-01: Inspector's Report, p.2
P1171; plus 2 x 2.19 MWth generators and 4 fire pumps; 11 are 'catcher' (redundant) units
Generating units105 units"The licence is for the operation of 105 no. generators as part of a data storage campus." EPA P1171-01: Inspector's Report, p.1
P1171 only; P1186 (post-2026 review) adds 52 back-up generators, campus ~157
On-site thermal input672.9 MWth (derived)"Given that the combined thermal input from the generators is 672.85 MWth" EPA P1171-01: Inspector's Report, p.2
P1171 only; P1186 adds 290.95 MWth (Attachment 4-4-1), campus total ~963.8 MWth (derived)
Fueldiesel / HVO"may operate using gas oil (diesel) or HVO (Hydrotreated Vegetable Oil) fuel, with a preference to use only HVO when supply is available" EPA P1186-02: LA-IR P1186-02 Amazon.pdf, p.10
P1186 review; P1171 AER also reports diesel + HVO
Running hours72 h/yr per generator"The operation of the generators is restricted to no more than 72 hours/year, at no more than 90% load" EPA P1171-01: Inspector's Report, p.9
P1171; P1186-02 allows 150 h/yr at 100% load, <=248.11 MWth simultaneously
Coolingevaporative (free cooling + evaporative AHUs)"The evaporative cooling system for the data halls operates in two modes; free cooling and evaporative cooling." EPA P1171-01: Inspector's Report, p.11
P1186 Building V uses refrigerant-based mechanical cooling instead
Water8 m3/day (derived)"Total Water Used 2,910.65 -86%" EPA P1171-01: P1171-01-Annual Environmental Report-2025.pdf, p.16
derived: 2,910.65 m3 in 2025 / 365 (P1171 only); P1186 used 2,563.18 m3 in 2025; licence application projected 17,879 m3/yr
Phasing6 buildings A-F (A-D existing, E-F extension); P1186 adds U and V to W, X, Y"When fully constructed the site will consist of 6 no. data storage installations (Building A to F)." EPA P1171-01: Inspector's Report, p.2
P1171
DatesBuilding E 2023; Building F early 2024"Building E is to be operational by 2023, and Building F is to be operational by the beginning of 2024." EPA P1171-01: Inspector's Report, p.2
P1171, as stated in 2023 inspector's report
Heat reuseheat-recovery ready; no district heating network yet"designed to facilitate the incorporation of heat recovery coils and an underground waste heat primary circuit, should a district heating system be developed" EPA P1171-01: Inspector's Report, p.14
RenewablesCPPAs in three wind projects; rooftop PV (26 kWe per building on E and F)"its investment through Corporate Power Purchase Agreements (CCPAS) in three major wind projects" EPA P1171-01: Inspector's Report, p.15
PV: 26 kWe per building, p14

Every value is quoted from the document and page cited; the quote was checked against that page's text. "Derived" means the reader worked it out from stated figures (shown in the quote). Planning and licence figures are design or permitted values, not measured use; values derived from an EPA annual environmental report (AER), mostly water, are reported use for that year. The note under each quote gives the scope and whether a demand figure is a maximum or an average.

Planning history

ReceivedRefWhatDecisionBuilt?
2019-07-023400/19
Planning permission for development on a site of c. 0.025 hectares at Clonshaugh Business and Technology Park, Dublin 17. The site is located to the south of an existing data storage facility at the former Cahill Printers building (Building B). The proposed development comprises of a container compound for the purposes of providing ancillary modular plant, electronic equipment and machinery space. The development comprises 4 no. prefabricated metal containers (stacked to form 2 no. storeys), associated access arrangements and staircases, a boundary fence enclosure around the proposed developme
GRANT PERMISSIONcommenced (no completion certificate on a main building yet)

Sources for this page

osm:way/47924356 · osm:way/68337136 · osm:way/47923380 · osm:way/697659634 · osm:way/1108073464 · osm:way/1047598884 · osm:way/1373868450 · osm:way/1108073465 · epa:P1171 · epa:P1186 · valuation:733234 · valuation:10028867 · valuation:5027088 · valuation:5027089 · valuation:5027086 · valuation:5027087 · valuation:10030755 · planning:DCC/3400/19

Joined from OpenStreetMap, the planning register, An Coimisiún Pleanála, EPA licences and annual reports, the Tailte Éireann valuation list and Building Control. Data built 2026-10-10.