Data centre · Galway County · 53.2895, -8.8265
Apple Athenry
permitted Apple Our classification · status
Not available for this site: measured grid draw (no EPA annual report: only sites with ≥50 MWth of plant file one); mapped footprint; rates (no valuation-list entry matched).
Why we say it's permitted
- Planning 211047: unstarted, permission live
Who runs it
- planning applicant 'Apple Distribution International' -> Apple (operator; high-confidence entity link from planning); lifecycle: unchecked: Apple's Athenry site (general knowledge)






What the planning and licence documents say
Phase 1 single data hall (PL07.245518, granted 2016) of an 8-hall masterplan; never built.
| Spec | Value | Quote and source |
|---|---|---|
| Electrical demand | 30 MW | "Confirmation submitted from Eirgrid that the network can accommodate the 30MW demand." ACP 245518 inspector report, p.10 phase 1 (1 of 8 halls); objectors cite 240MW full build-out |
| Grid voltage | 220 kV | "There is a concurrent application for the construction of a 220kv substation located to the north west of the proposed data centre building" ACP 245518 inspector report, p.4 |
| Connection point | new on-site 220kV substation connecting to Cashla-Tynagh and Cashla-Prospect 220kV lines (07.VA0020) | "passes close to the north east corner of the site these being the Cashla to Tynagh and the Cashla to Prospect lines" ACP 245518 inspector report, p.4 |
| On-site generation | backup diesel generators | "The development proposes the provision of 18 no. standby diesel generators" ACP 245518 inspector report, p.5 |
| Generating units | 18 units | "The development proposes the provision of 18 no. standby diesel generators" ACP 245518 inspector report, p.5 phase 1; 18 per hall in 8-hall masterplan |
| On-site output | 36 MW (derived) | "each generator has a rated output of 2MW" ACP 245518 inspector report, p.5 derived: 18 generators x 2MW |
| Fuel | diesel | "The development proposes the provision of 18 no. standby diesel generators" ACP 245518 inspector report, p.5 |
| Cooling | air (ambient cooling) | "adequate air circulation for successful ambient cooling is achieved" ACP 245518 inspector report, p.54 |
| Floor area | 24,505 m2 | "comprising a 24,505 sq metre single storey data centre building" ACP 245518 inspector report, p.5 data hall only; plus 5,232m2 logistics/admin |
| Data halls | 1 halls | "Site Masterplan Drawing (14294.0000) which shows the overall future layout of the site with a total of 8 no. data halls" ACP 245518 inspector report, p.6 1 hall applied for; 8 in masterplan |
| Phasing | phase 1 of 8-hall masterplan | "Site Masterplan Drawing (14294.0000) which shows the overall future layout of the site with a total of 8 no. data halls" ACP 245518 inspector report, p.6 |
| Dates | granted 2016; extension of duration to 04/08/2026; project abandoned | "Expiry Date: 04/08/2026" GalwayCC ePlan register entry 211047 (development description), p.1 abandonment from campus record, not this doc |
| Renewables | 100% renewable objective via purchase of renewable energy (no specific PPA) | "objective of 100 percent renewable sources will be met by the use of efficient technologies, support for renewable energy generation projects and the purchase" ACP 245518 inspector report, p.10 |
Every value is quoted from the document and page cited; the quote was checked against that page's text. "Derived" means the reader worked it out from stated figures (shown in the quote). Planning and licence figures are design or permitted values, not measured use; values derived from an EPA annual environmental report (AER), mostly water, are reported use for that year. The note under each quote gives the scope and whether a demand figure is a maximum or an average.
Planning history
| Received | Ref | What | Decision | Built? |
|---|---|---|---|---|
| 2021-06-14 | 211047 | to construct the following: a 24,505sqm single storey data centre building, a 5232sqm single storey Logistics and Administration Building, a 289sqm single storey Maintenance Building, a 16sqm Security Hut and associated barriers, 2 number 48sqm Fibre Huts (max building eaves height = 10m), 18 external standby generators, all associated external plant, a 20kV Electricity Substation, contractor facilities, a main entrance including a new right turning lane, internal access roads and associated infrastructure, proprietary waste water treatment plants including percolation areas, mains water conne | UNCONDITIONAL | unstarted, permission live |
Sources for this page
planning:GALWAYCO/211047 · acp:245518
Joined from OpenStreetMap, the planning register, An Coimisiún Pleanála, EPA licences and annual reports, the Tailte Éireann valuation list and Building Control. Data built 2026-10-10.