Data centres in Galway County

0
Operating campuses
1 known at any stage
—
Average grid draw, 2025
EPA-reporting sites only
—
Estimated rates a year
—
Metered water, 2025
EPA-licensed sites
1
Planning applications
1 granted · 0 refused · 0 appealed

Campuses

Apple Athenrypermitted—
Leaflet © OpenStreetMap contributors · Tailte Éireann (CC BY)

Grid headroom in Galway County

52 MVA
Demand headroom at HV stations, summed
26 transformer groups · upper bound
13 of 26
HV transformer groups with none
12 green · 1 capped by parent
20 MVA
At 38 kV
3 transformer groups
66%
Of LV substations with none
1,896 substations

Largest HV transformer groups, then MV, by demand headroom

StationConnect atDemand MVAGeneration MW
● Cloon38 kV10.89.1
● Screeb38 kV6.921.4
● Somerset38 kV26.8
● CloonMV (10/20 kV)10.70.5
● OughterardMV (10/20 kV)6.54.1
● SpiddalMV (10/20 kV)4.51.7
● RecessMV (10/20 kV)2.84.4

headroomcapped by parentnone · size = demand MVA

ESB Networks' indicative transformer headroom, not a connection offer; it ignores upstream circuits and the transmission system. Station capacity Oct 2025, contracts to Aug–Oct 2025, compiled 12/12/2025. How to read it.

Local TDs asking about data centres

Denis Naughten · Independent · Roscommon-Galway15
Catherine Connolly · Independent · Galway West14
Mairéad Farrell · Sinn Féin · Galway West6
Louis O'Hara · Sinn Féin · Galway East2
Anne Rabbitte · Fianna Fáil · Galway East1
Claire Kerrane · Sinn Féin · Roscommon-Galway1
Noel Grealish · Independent · Galway West1

Constituency-to-council matching is by name and approximate.