Data centre · Donegal · 55.0382, -7.3684

← All data centres

Lifford (operator not identified)

lapsed Not identified Our classification · status

Not available for this site: measured grid draw (no EPA annual report: only sites with ≥50 MWth of plant file one); mapped footprint; rates (no valuation-list entry matched).

Why we say it's lapsed

  • Planning 1850236: lapsed without commencement notice

Who runs it

    Leaflet © OpenStreetMap contributors

    Planning history

    ReceivedRefWhatDecisionBuilt?
    2018-02-201850236
    ERECTION OF A TWO-STOREY DATA CENTRE BUILDING WITH ANCILLARY OFFICES AND ROOF LEVEL PLANT AREA AND SCREEN FENCE, NEW ACCESS ROAD, CARPARKING, LANDSCAPING, TWO NO. OPEN AIR PLANT COMPOUNDS, WASTEWATER TREATMENT SYSTEM AND ASSOCIATED WORKS AT KEVLIN SCIENCE AND TECHNOLOGY PARK
    UNCONDITIONALlapsed without commencement notice

    Sources for this page

    planning:DONEGAL/1850236

    Joined from OpenStreetMap, the planning register, An Coimisiún Pleanála, EPA licences and annual reports, the Tailte Éireann valuation list and Building Control. Data built 2026-10-10.