Data centre · Donegal · 55.0382, -7.3684
Lifford (operator not identified)
lapsed Not identified Our classification · status
Not available for this site: measured grid draw (no EPA annual report: only sites with ≥50 MWth of plant file one); mapped footprint; rates (no valuation-list entry matched).
Why we say it's lapsed
- Planning 1850236: lapsed without commencement notice
Who runs it






Leaflet © OpenStreetMap contributors
Planning history
| Received | Ref | What | Decision | Built? |
|---|---|---|---|---|
| 2018-02-20 | 1850236 | ERECTION OF A TWO-STOREY DATA CENTRE BUILDING WITH ANCILLARY OFFICES AND ROOF LEVEL PLANT AREA AND SCREEN FENCE, NEW ACCESS ROAD, CARPARKING, LANDSCAPING, TWO NO. OPEN AIR PLANT COMPOUNDS, WASTEWATER TREATMENT SYSTEM AND ASSOCIATED WORKS AT KEVLIN SCIENCE AND TECHNOLOGY PARK | UNCONDITIONAL | lapsed without commencement notice |
Sources for this page
planning:DONEGAL/1850236
Joined from OpenStreetMap, the planning register, An Coimisiún Pleanála, EPA licences and annual reports, the Tailte Éireann valuation list and Building Control. Data built 2026-10-10.