Council · data centres and power

← All councils

Data centres in Donegal

0
Operating campuses
1 known at any stage
—
Average grid draw, 2025
EPA-reporting sites only
—
Estimated rates a year
—
Metered water, 2025
EPA-licensed sites
1
Planning applications
1 granted · 0 refused · 0 appealed

Campuses

Leaflet © OpenStreetMap contributors · Tailte Éireann (CC BY)

Grid headroom in Donegal

261 MVA
Demand headroom at HV stations, summed
31 transformer groups · upper bound
8 of 31
HV transformer groups with none
21 green · 2 capped by parent
182 MVA
At 38 kV
7 transformer groups
47%
Of LV substations with none
1,822 substations

Largest HV transformer groups, then MV, by demand headroom

StationConnect atDemand MVAGeneration MW
● Binbane T141/T14238 kV66.60
● Binbane T14338 kV56.359.9
● Trillick T14238 kV280
● Letterkenny38 kV13.20
● Ardnagappary38 kV11.80
● Trillick T14138 kV4.90
● Cathaleens Fall38 kV1.60
● Sorne HillMV (10/20 kV)27.75
● Killybegs T41MV (10/20 kV)13.50
● ConvoyMV (10/20 kV)7.20
● GortleeMV (10/20 kV)5.50

headroomcapped by parentnone · size = demand MVA

ESB Networks' indicative transformer headroom, not a connection offer; it ignores upstream circuits and the transmission system. Station capacity Oct 2025, contracts to Aug–Oct 2025, compiled 12/12/2025. How to read it.

Local TDs asking about data centres

Pearse Doherty · Sinn Féin · Donegal5
Thomas Pringle · Independent · Donegal3
Pearse Doherty · Sinn Féin · Donegal South-West1

Constituency-to-council matching is by name and approximate.