Data centre · Fingal · 53.4116, -6.3195
Microsoft Huntstown
under construction Microsoft (operator medium confidence) Our classification · status
Not available for this site: measured grid draw (no EPA annual report: only sites with ≥50 MWth of plant file one); rates (no valuation-list entry matched).
Why we say it's under construction
- Planning FW21A/0151: commencement notice 2025-10-17, no completion certificate
- 1 building(s) mapped in OSM but no completion certificate, EPA commencement or valuation entry yet
Who runs it
- lifecycle: commencement notices name MSFT DUB40/41
- some records attributed by co-location only (no operator in their own source)






What the planning and licence documents say
Proposed 2-building data centre (A and B) by Huntstown Power Co (Energia) beside Huntstown power station, end user Microsoft; ABP-313583-22, granted by the Board 2025 against inspector's refusal recommendation.
Every value is quoted from the document and page cited; the quote was checked against that page's text. "Derived" means the reader worked it out from stated figures (shown in the quote). Planning and licence figures are design or permitted values, not measured use; values derived from an EPA annual environmental report (AER), mostly water, are reported use for that year. The note under each quote gives the scope and whether a demand figure is a maximum or an average.
Planning history
| Received | Ref | What | Decision | Built? |
|---|---|---|---|---|
| 2022-02-24 | FW21A/0151 | Demolition of 2 no. existing residential dwellings and construction of 2 no. data hall buildings. EIAR submitted with application | GRANT PERMISSION | commenced (no completion certificate on a main building yet) |
Sources for this page
osm:way/1460367741 · planning:FINGAL/FW21A/0151 · acp:313564 · acp:313583
Joined from OpenStreetMap, the planning register, An Coimisiún Pleanála, EPA licences and annual reports, the Tailte Éireann valuation list and Building Control. Data built 2026-10-10.