Insight · measures

How good are Ireland's data centres for AI? The measures that matter

Judge a data centre on two levels: the building (PUE, water, heat reuse, power per rack) and the computers in it (chip efficiency, model FLOPs utilisation, goodput). Irish sites that reported to the EU averaged a PUE of 1.18 (2023 data), better than the EU's 1.36, but no public data show they can host today's 132 kW AI racks.

By StackPath · published 6 October 2026 · updated 10 October 2026 · how we know · corrections

Two levels: the building and the computers

A data centre turns grid power into steady, cooled power for computers. Building measures say how well it does that and at what cost in water and heat. Computer measures say how much useful work the chips do with the power they get. EU reporting covers the first kind only; nobody is required to publish the second.

MeasureWhat it measuresStandardLevel
PUE
Power usage effectiveness
Total facility energy ÷ IT energy. 1.0 would mean every unit reaches the computers.ISO/IEC 30134-2Building
WUE
Water usage effectiveness
Litres of water per kWh of IT energy.ISO/IEC 30134-9Building
CUE
Carbon usage effectiveness
kg of CO₂e per kWh of IT energy.ISO/IEC 30134-8Building
ERF
Energy reuse factor
Share of energy reused elsewhere, usually as heat.ISO/IEC 30134-6Building
REF
Renewable energy factor
Share of energy from renewables, including certificates and PPAs.ISO/IEC 30134-3Building
kW per rack
Rack power density
How much power one rack of servers can draw and have cooled.No single standardBuilding
Utilisation
Power utilisation
Power actually drawn ÷ power the site is built or contracted for.No standard benchmarkBuilding
Tier
Uptime Institute Tier I–IV
Resilience: I basic capacity, II redundant components, III concurrently maintainable, IV fault tolerant.Uptime InstituteBuilding
FLOP/s per watt
Chip energy efficiency
Peak arithmetic per unit of power for a given number format (BF16, FP8).Vendor datasheetsComputer
MFU
Model FLOPs utilisation
Share of the chips' peak arithmetic a training run actually uses for the model.PaLM paper definitionComputer
Goodput
ML goodput
Share of time and compute that turns into useful training progress, after failures and restarts.Google Cloud definitionComputer
Wh per query
Energy per prompt or token
Electricity per answer served; the inference counterpart of PUE.No standardComputer
Figure 1

What one megawatt buys, by generation

The same megawatt at the meter runs about 3.3 times more AI arithmetic with B200 servers (2024) than with A100 servers (2020). Where grid power is the limit, newer chips are how a site gets more out of it.

What one megawatt at the meter buys, by server generation1 MW at the meter, at PUE 1.18, leaves 847 kW for IT. DGX A100 (2020): 326 PFLOP/s peak BF16, about 132 PFLOP/s at 41% MFU; DGX H100 (2022): 657 PFLOP/s peak BF16, about 266 PFLOP/s at 41% MFU; DGX B200 (2024): 1,067 PFLOP/s peak BF16, about 432 PFLOP/s at 41% MFU.1 MWat the meter›÷ 1.18PUE (Irish average)›847 kWreaches the IT›× chipFLOP/s per watt›× ~41%MFU (Llama 3: 38–43%)PETAFLOP/S PER MW AT THE METER, BF16 · OUTLINE = PEAK, SOLID = USED BY A TYPICAL LARGE TRAINING RUNDGX A1002020 · 6.5 kW per serverDGX A100: 385 PFLOP/s per MW of servers (dense BF16); 326 per MW at the meter; about 132 used at 41% MFU132 used · 326 peakDGX H1002022 · 10.2 kW per serverDGX H100: 775 PFLOP/s per MW of servers (dense BF16); 657 per MW at the meter; about 266 used at 41% MFU266 used · 657 peakDGX B2002024 · 14.3 kW per serverDGX B200: 1,259 PFLOP/s per MW of servers (dense BF16); 1,067 per MW at the meter; about 432 used at 41% MFU432 used · 1,067 peak
What one megawatt at the meter buys, by server generation1 MW at the meter, at PUE 1.18, leaves 847 kW for IT. DGX A100 (2020): 326 PFLOP/s peak BF16, about 132 PFLOP/s at 41% MFU; DGX H100 (2022): 657 PFLOP/s peak BF16, about 266 PFLOP/s at 41% MFU; DGX B200 (2024): 1,067 PFLOP/s peak BF16, about 432 PFLOP/s at 41% MFU.1 MWmeter›÷ 1.18PUE›847 kWto IT›× chipper watt›× ~41%MFUPFLOP/S PER MW AT THE METER, BF16DGX A1002020 · 6.5 kW per serverDGX A100: 385 PFLOP/s per MW of servers (dense BF16); 326 per MW at the meter; about 132 used at 41% MFU132 used · 326 peakDGX H1002022 · 10.2 kW per serverDGX H100: 775 PFLOP/s per MW of servers (dense BF16); 657 per MW at the meter; about 266 used at 41% MFU266 used · 657 peakDGX B2002024 · 14.3 kW per serverDGX B200: 1,259 PFLOP/s per MW of servers (dense BF16); 1,067 per MW at the meter; about 432 used at 41% MFU432 used · 1,067 peak

Start with 1 MW drawn from the grid. At the Irish reporting sites' average PUE of 1.18, about 847 kW reaches the servers. Each NVIDIA server generation turns that into more peak arithmetic: 385 PFLOP/s per MW of A100 servers, 775 PFLOP/s per MW of H100 servers, 1,259 PFLOP/s per MW of B200 servers (dense BF16, from datasheets). Large training runs use only part of the peak: Meta reports 38–43% model FLOPs utilisation for Llama 3 on H100s, and the chart applies the midpoint to every generation.

EstimatePer-MW figures are dense peak ÷ maximum server power, our arithmetic; NVIDIA's headline figures are sparse, twice the dense ones. Applying one MFU to all three generations and ignoring networking and storage power make this an illustration, not a measurement of any site.

Sources: NVIDIA DGX A100 datasheet, 2020 · NVIDIA DGX H100 datasheet, 2023 · NVIDIA DGX B200 datasheet, 2024 · Llama Team, The Llama 3 Herd of Models, arXiv 2407.21783, Jul 2024 · DG ENER, first technical report on EU data-centre reporting, Jul 2025

The building: PUE, water and heat

Worldwide, the average PUE has been flat for six years at about 1.54 (Uptime Institute, 2025). Across the 770 EU sites that reported under the Energy Efficiency Directive, about 36% of those required to, it was 1.36. In Ireland only 18 of an estimated 123 sites reported in the first round, and the European Commission's technical report says Ireland "struggled to implement the necessary systems". Those 18 averaged 1.18: 1.14 for sites over 10 MW and 1.15 for enterprise sites, against 1.28 for colocation and 1.65 for small sites of 1–2 MW.

Figure 2

Irish data centres score well on PUE

The Irish sites that reported to the EU averaged a PUE of 1.18 (class B on the EU's new label), against 1.36 across the EU and 1.54 worldwide. PUE says how little power the building wastes, not whether it can host AI.

PUE on the EU rating scheme's classesEU PUE classes: A up to 1.15, B up to 1.25, C up to 1.35, D up to 1.5, E up to 1.7, F up to 1.9, G above 1.9. Global average (Uptime survey) (2025): 1.54, class E; EU, sites that reported: 1.36, class D; Ireland, sites that reported (2023): 1.18, class B; AWS, Ireland region (2025): 1.10, class A; Google, Dublin (2026): 1.08, class A; Microsoft, Ireland (2021): 1.197, class B.PUE: TOTAL ENERGY ÷ IT ENERGY · LOWER IS BETTERABCDEFG1.01.21.41.61.82.0Ireland, sites that reported, 2023: 1.18 (class B). 18 of an estimated 123 Irish sites reported (15%). Colocation 1.28, enterprise 1.15, sites over 10 MW 1.14, sites of 1–2 MW 1.65.1.18IrelandEU, sites that reported: 1.36 (class D). 770 data centres, about 36% of those required to report.1.36EU averageGlobal average (Uptime survey), 2025: 1.54 (class E). Flat for six years; 1.52 in the 2026 survey.1.54World averageGoogle, Dublin, 2026: 1.08 (class A). Trailing twelve months to Q2 2026.Google, Dublin 1.08 (2026)AWS, Ireland region, 2025: 1.10 (class A). 1.11 in 2024.AWS, Ireland region 1.10 (2025)Microsoft, Ireland, 2021: 1.197 (class B). Calendar 2021; nothing newer published for Ireland. Design PUE 1.12.Microsoft, Ireland 1.197 (2021)
PUE on the EU rating scheme's classesEU PUE classes: A up to 1.15, B up to 1.25, C up to 1.35, D up to 1.5, E up to 1.7, F up to 1.9, G above 1.9. Global average (Uptime survey) (2025): 1.54, class E; EU, sites that reported: 1.36, class D; Ireland, sites that reported (2023): 1.18, class B; AWS, Ireland region (2025): 1.10, class A; Google, Dublin (2026): 1.08, class A; Microsoft, Ireland (2021): 1.197, class B.PUE: TOTAL ENERGY ÷ IT ENERGY · LOWER IS BETTERABCDEFG1.01.21.41.61.82.0Ireland, sites that reported, 2023: 1.18 (class B). 18 of an estimated 123 Irish sites reported (15%). Colocation 1.28, enterprise 1.15, sites over 10 MW 1.14, sites of 1–2 MW 1.65.1.18IrelandEU, sites that reported: 1.36 (class D). 770 data centres, about 36% of those required to report.1.36EU averageGlobal average (Uptime survey), 2025: 1.54 (class E). Flat for six years; 1.52 in the 2026 survey.1.54World averageGoogle, Dublin, 2026: 1.08 (class A). Trailing twelve months to Q2 2026.Google, Dublin 1.08 (2026)AWS, Ireland region, 2025: 1.10 (class A). 1.11 in 2024.AWS, Ireland region 1.10 (2025)Microsoft, Ireland, 2021: 1.197 (class B). Calendar 2021; nothing newer published for Ireland. Design PUE 1.12.Microsoft, Ireland 1.197 (2021)

PUE divides a data centre's total energy by the energy reaching its computers. The EU's rating scheme, adopted in September 2026, puts it into classes from A (1.15 or less) to G (above 1.9). Only 18 of an estimated 123 Irish sites reported in the first round (2023 data), so the Irish average covers a minority of sites. Operators' own figures for their Irish sites are shown below the scale, each for the latest year published. At 1.18 against 1.54, the Irish sites waste about 23% less energy per unit of computing than the global average.

EstimateThe class of each figure is our reading of the EU bands; the "% less" comparison is our arithmetic.

Sources: European Commission, IP/26/1667 and C(2026) 3472 annexes, 21 Sep 2026 · Uptime Institute, Global Data Center Survey 2025, Jul 2025 · European Commission, COM(2026) 500, 21 Sep 2026 · DG ENER, first technical report on EU data-centre reporting, Jul 2025 · Amazon sustainability, AWS cloud, 6 Oct 2026 · Google data centres, efficiency, 6 Oct 2026 · Microsoft datacentre fact sheet, Ireland (uploaded Aug 2024), Aug 2024

On water, the Irish reporting sites used 0.64 litres per kWh of IT energy, against 0.58 across the EU (every licensed site's measured water). Their renewable energy factor was 0.99 (EU 0.86), but it counts certificates and power-purchase agreements over a year, so it says little about supply hour by hour. Ireland reported no heat-reuse figure; across the EU only 67 sites reported any. From 15 August 2027 each site's EU label, with its PUE and water classes, energy sources and heat-reuse readiness, becomes public; everything else stays confidential.

Utilisation is the measure Ireland can estimate itself: data centres drew about 38–46% of the grid capacity contracted to them in 2025, leaving 1.0–1.4 GW unused (our estimate).

The computers: chips, MFU and goodput

A chip's datasheet gives its peak arithmetic in FLOP/s, floating-point operations per second. Real training runs reach only part of it, because chips wait for data, for each other and for failures to be fixed. Model FLOPs utilisation (MFU) is the share of peak a run actually spends on the model. The published figures for large runs:

Training runOrganisationHardwareMFU
PaLM 540BGoogle6,144 TPU v446.2%
Llama 3 405BMetaup to 16,000 H10038–43%
175B model (MegaScale)ByteDance12,288 GPUs55.2%
GPT-3 175B (as reported in the PaLM paper)OpenAIV10021.3%

Goodput goes wider. Google Cloud defines ML goodput as the product of scheduling goodput (share of time all resources are available), runtime goodput (useful training steps while they are) and program goodput (in effect, MFU). Failures matter at this scale: Llama 3 405B training saw 466 interruptions in 54 days (419 unexpected, about 78% of those hardware, 58.7% GPUs) and still achieved more than 90% effective training time.

For serving, the comparable measure is energy per answer. Median Gemini Apps text prompt: 0.24 Wh (Google Cloud blog). Includes idle capacity and data-centre overhead (PUE 1.09); 0.10 Wh counting active accelerators only. Typical GPT-4o query (estimate): about 0.3 Wh (Epoch AI). Rising to about 2.5 Wh with 10,000 input tokens. Tokens per second per MW, H100 vs B200: about 0.9 million vs 2.8 million (SemiAnalysis). Counting all-in provisioned power; an analyst benchmark.

None of these is published for any workload run in Ireland.

Can Irish halls host the newest chips?

Each NVIDIA generation has packed more power into a rack:

GenerationRackPowerCooling
A100 (2020)8-GPU server6.5 kW per serverAir
Hopper (2023)4 × DGX H100 servers (8 GPUs each)41 kWAir
Blackwell (2025)GB200 NVL72 (72 GPUs)132 kWLiquid
Blackwell Ultra (2025)GB300 NVL72 (72 GPUs)135 kW (peak 155)Liquid
Vera Rubin (2026)VR NVL72 (formerly NVL144), from H2 2026~200 kW, estimateLiquid
Rubin Ultra (2027)NVL576 'Kyber' rack, announced for H2 2027~600 kW, announcedLiquid
Figure 3

Ireland's fleet was built before liquid-cooled AI racks

Every campus with measured 2025 grid draw and a completion record got its first certificate by 2022, before NVIDIA's first liquid-cooled rack-scale system shipped. Of 27 campuses whose files state a cooling method, 1 plans liquid-cooled racks.

Ireland's data-centre fleet against the AI hardware timeline23 of 55 operating campuses have a first completion certificate since 2014; those with measured 2025 grid draw were first completed between 2016 and 2022. Cooling stated for 27 campuses: 17 air: free air, evaporative or adiabatic, 9 chilled-water plant, 1 liquid-cooled racks.OPERATING CAMPUSES BY YEAR OF FIRST COMPLETION · SIZE = MEASURED 2025 DRAW201420152016201720182019202020212022202320242025202620272028A1002020 · air-cooledH1002022 · air-cooledGB200 NVL722025 · 132 kW, liquidRubin Ultra2027 · ~600 kW, announcedMicrosoft Grange Castle: first completion 2017, 154.5 MW average draw in 2025Amazon (AWS) Clonshaugh: first completion 2021, 144.4 MW average draw in 2025Meta Clonee: first completion 2019, 135.0 MW average draw in 2025Amazon (AWS) Cruiserath: first completion 2020, 76.6 MW average draw in 2025Amazon (AWS) Grange Castle South: first completion 2021, 61.0 MW average draw in 2025Amazon (AWS) Belgard, Tallaght: first completion 2019, 45.6 MW average draw in 2025Amazon (AWS) Greenhills Road, Tallaght: first completion 2017, 34.6 MW average draw in 2025Google Grange Castle South: first completion 2016, 26.0 MW average draw in 2025Equinix Blanchardstown: first completion 2022, 18.5 MW average draw in 2025K2 Strategic Ballycoolin: first completion 2022, 17.5 MW average draw in 2025Amazon (AWS) Drogheda: first completion 2021, 12.7 MW average draw in 2025EdgeConneX Newcastle Road, Lucan: first completion 2017, draw not reportedEchelon Crag Avenue, Clondalkin: first completion 2021, draw not reportedCyrusOne Grange Castle South: first completion 2021, draw not reportedPure DC Orion Business Campus: first completion 2023, draw not reportedDigital Realty Grange Castle: first completion 2017, draw not reportedK2 Strategic Citywest: first completion 2024, draw not reportedClonshaugh (operator not identified) (1): first completion 2020, draw not reportedAmazon (AWS) Leixlip: first completion 2026, draw not reportedClonshaugh (operator not identified) (2): first completion 2022, draw not reportedDCF Technology Blanchardstown: first completion 2017, draw not reportedGemini DC Fund Ballycoolin: first completion 2018, draw not reportedGovernment (OGCIO) Backweston, Celbridge: first completion 2025, draw not reportedHOW 27 CAMPUSES ARE COOLED, FROM THEIR PLANNING AND LICENCE FILESAir: free air, evaporative or adiabatic: Microsoft Grange Castle, Microsoft Huntstown (Energia/Huntstown Power data centres), Google Grange Castle South, Amazon (AWS) Clonshaugh, Amazon (AWS) Grange Castle South, Amazon (AWS) Belgard, Tallaght, Amazon (AWS) Greenhills Road, Tallaght, Amazon (AWS) Blanchardstown, Amazon (AWS) Cruiserath, Amazon (AWS) Drogheda, Meta Clonee, K2 Strategic Ballycoolin, Echelon Avoca River Park, Arklow, Data & Power Hub, Peamount Road, Newcastle, Herbata, Naas (Kildare), Art Data Centres, Ennis, Apple Athenry (abandoned)17 · Air: free air, evaporative or adiabaticChilled-water plant: CyrusOne Grange Castle South, SDC-EN Meath I, Bracetown (Clonee), Equinix DB5 Blanchardstown, Echelon Crag Avenue, Clondalkin, Equinix Profile Park, Digital Realty Profile Park, EdgeConneX Newcastle Road, Lucan, Avaio Digital / Mayo Data Hub, Killala, eir Drogheda exchange data centre9 · Chilled-water plantLiquid-cooled racks: Amazon (AWS) Kildare Innovation Campus, Leixlip1 · Liquid-cooled racks
Ireland's data-centre fleet against the AI hardware timeline23 of 55 operating campuses have a first completion certificate since 2014; those with measured 2025 grid draw were first completed between 2016 and 2022. Cooling stated for 27 campuses: 17 air: free air, evaporative or adiabatic, 9 chilled-water plant, 1 liquid-cooled racks.CAMPUSES BY YEAR OF FIRST COMPLETION'14'16'18'20'22'24'26'28A1002020H1002022GB200 NVL722025Rubin Ultra2027Microsoft Grange Castle: first completion 2017, 154.5 MW average draw in 2025Amazon (AWS) Clonshaugh: first completion 2021, 144.4 MW average draw in 2025Meta Clonee: first completion 2019, 135.0 MW average draw in 2025Amazon (AWS) Cruiserath: first completion 2020, 76.6 MW average draw in 2025Amazon (AWS) Grange Castle South: first completion 2021, 61.0 MW average draw in 2025Amazon (AWS) Belgard, Tallaght: first completion 2019, 45.6 MW average draw in 2025Amazon (AWS) Greenhills Road, Tallaght: first completion 2017, 34.6 MW average draw in 2025Google Grange Castle South: first completion 2016, 26.0 MW average draw in 2025Equinix Blanchardstown: first completion 2022, 18.5 MW average draw in 2025K2 Strategic Ballycoolin: first completion 2022, 17.5 MW average draw in 2025Amazon (AWS) Drogheda: first completion 2021, 12.7 MW average draw in 2025EdgeConneX Newcastle Road, Lucan: first completion 2017, draw not reportedEchelon Crag Avenue, Clondalkin: first completion 2021, draw not reportedCyrusOne Grange Castle South: first completion 2021, draw not reportedPure DC Orion Business Campus: first completion 2023, draw not reportedDigital Realty Grange Castle: first completion 2017, draw not reportedK2 Strategic Citywest: first completion 2024, draw not reportedClonshaugh (operator not identified) (1): first completion 2020, draw not reportedAmazon (AWS) Leixlip: first completion 2026, draw not reportedClonshaugh (operator not identified) (2): first completion 2022, draw not reportedDCF Technology Blanchardstown: first completion 2017, draw not reportedGemini DC Fund Ballycoolin: first completion 2018, draw not reportedGovernment (OGCIO) Backweston, Celbridge: first completion 2025, draw not reportedHOW 27 CAMPUSES ARE COOLEDAir: free air, evaporative or adiabatic: Microsoft Grange Castle, Microsoft Huntstown (Energia/Huntstown Power data centres), Google Grange Castle South, Amazon (AWS) Clonshaugh, Amazon (AWS) Grange Castle South, Amazon (AWS) Belgard, Tallaght, Amazon (AWS) Greenhills Road, Tallaght, Amazon (AWS) Blanchardstown, Amazon (AWS) Cruiserath, Amazon (AWS) Drogheda, Meta Clonee, K2 Strategic Ballycoolin, Echelon Avoca River Park, Arklow, Data & Power Hub, Peamount Road, Newcastle, Herbata, Naas (Kildare), Art Data Centres, Ennis, Apple Athenry (abandoned)17 · AirChilled-water plant: CyrusOne Grange Castle South, SDC-EN Meath I, Bracetown (Clonee), Equinix DB5 Blanchardstown, Echelon Crag Avenue, Clondalkin, Equinix Profile Park, Digital Realty Profile Park, EdgeConneX Newcastle Road, Lucan, Avaio Digital / Mayo Data Hub, Killala, eir Drogheda exchange data centre9 · Chilled waterLiquid-cooled racks: Amazon (AWS) Kildare Innovation Campus, Leixlip1 · Liquid racks

The top panel places 23 of the 55 operating campuses at the year of their first completion certificate in the national Building Control register, which starts in 2014; the rest were finished earlier or have no certificate on record. Filled circles are sized by average grid draw in 2025 from EPA reports (726 of the 776 MW measured is at campuses first completed by 2022; the rest is at campuses with no completion certificate on record). Campuses add buildings over time, so a first completion date doesn't say how old every hall is. The bottom panel classifies the cooling method stated in each campus's planning or EPA licence files: 17 air: free air, evaporative or adiabatic, 9 chilled-water plant, 1 liquid-cooled racks; the liquid-cooled one is Amazon (AWS) Kildare Innovation Campus, Leixlip, building B1, in a 2026 licence application.

EstimateCooling classes are our grouping of the stated methods. Meta Clonee's "StatePoint Liquid Cooling" is an evaporative system that cools room air (Meta, 2018), so it counts as air-based.

Sources: Building Control Management System completion certificates, via StackPath directory, 10 Oct 2026 · EPA annual environmental reports (2025 grid draw), 10 Oct 2026 · Planning and EPA licence documents (cooling), 3 Oct 2026 · NVIDIA DGX A100 datasheet, 2020 · NVIDIA DGX H100 datasheet, 2023 · Uptime Institute Journal (D. Bizo), 25 Jun 2025 · Tom's Hardware, GTC 2025 report, 19 Mar 2025 · Meta Engineering, StatePoint Liquid Cooling, 5 Jun 2018

Bitpower's Q4 2024 market update counted 1,062 MW of IT capacity in "well over 100,000" racks in Ireland: at most about 10.6 kW per rack on average (our arithmetic). Bitpower's Q4 2024 update also reported 'zero announcements of AI-style campuses' and average draw around half of capacity.

Converting an air-cooled hall is more than adding pipes. A 63 A rack power strip at 230/400 V tops out at 43.5 kW; racks for dense IT should be rated above 1,800 kg static load; shallow raised floors and weak floor loading complicate retrofits. Above 40–50 kW per rack on average, power distribution becomes a bigger problem than cooling (Uptime's Daniel Bizo). Fewer than 4% of US data centres can support racks above 100 kW (Uptime's Daniel Bizo, estimate). Workarounds exist: meta and Microsoft run liquid-cooled GB200 racks in air-cooled halls using sidecar heat exchangers that turn room air into cooled liquid. Installing one HGX B200 system at CloudCIX/AlloComp in Cork, a rack close to a tonne, needed structural changes and a new access route into the building. (TechCentral, Dec 2025).

Why density matters more in Ireland

Our reading. Where grid connections are the scarcest input, compute per contracted megawatt is the lever. The same megawatt runs about 3.3 times more arithmetic with B200 servers than with A100s (Figure 1), and 1.0–1.4 GW contracted to data centres is unused. Using it needs halls that take dense, liquid-cooled racks and, since the CRU's ride-through decision, compliance before a site's demand can grow past its cap (the 900 MW limit).

What is not known

  • Rack densities in Irish halls. No planning or licence file we read states a design kW per rack.
  • How many AI accelerators are installed in Ireland. Import statistics show hardware arriving, not where it is installed or used.
  • Irish sites' PUE, water and renewable figures one by one. EU reporting keeps them confidential; per-site rating labels are due from 15 Aug 2027.
  • Model FLOPs utilisation, goodput or energy per query for any workload run in Ireland. No operator publishes them by country.

Questions people ask

What is a good PUE for a data centre?
The EU's new label rates 1.15 or less as class A and up to 1.25 as class B. The global average was 1.54 in 2025 (Uptime Institute); large cloud operators report fleet averages of about 1.08 to 1.17.
What PUE do Irish data centres have?
The 18 Irish sites that reported to the EU averaged 1.18 (2023 data). Operators publish 1.1 for AWS's Ireland region (2025), 1.08 for Google's Dublin site (2026) and 1.197 for Microsoft in Ireland (2021).
What is model FLOPs utilisation (MFU)?
The share of the chips' peak arithmetic that a training run actually spends on the model. Published large runs reach roughly 38–55%: Meta reports 38–43% for Llama 3 405B on H100s.
Can Irish data centres host NVIDIA GB200 racks?
Few public signs so far. A GB200 NVL72 rack draws about 132 kW and needs liquid cooling; Ireland's fleet averages at most about 10.6 kW of IT capacity per rack, and only one campus's files describe liquid-cooled racks (Amazon, Leixlip, 2026).

How we know

  • Definitions, benchmarks and generation figures come from two web research passes on 6 October 2026: ISO/IEC 30134 standards, Uptime Institute surveys, the EU's data-centre reporting regulation and reports, NVIDIA datasheets, and published training papers.
  • Compute per megawatt is our arithmetic: dense BF16 peak ÷ maximum server power, from NVIDIA datasheets. Figure 1 applies one utilisation figure (the Llama 3 range's midpoint) to every generation, as an illustration.
  • Ireland's fleet figures come from this site's pipelines: first completion certificates (Building Control), measured grid draw (EPA annual reports) and cooling methods read from planning and EPA licence files. Bitpower's rack count is divided by its IT capacity by us.

Sources

Numbers on this page are read from our data build of 10 October 2026 and update when it changes. Text marked Our reading is our analysis, not a sourced fact. Found a mistake? See corrections; method notes are on methodology.