The data centres hiding in the planning register

A machine-learning search of 507,741 Irish planning applications found 69 data-centre applications that keyword searches miss: 61 confirmed by reading the files and 8 likely. They are described as "electrical rooms", "ICT facility", "data storage building" or "energy centre" (StackPath analysis, Oct 2026).

By StackPath · published 3 October 2026 · updated 10 October 2026 · how we know · corrections

Why don't data centres show up in planning searches?

Search Ireland's planning registers for "data centre" and you get a list. It is incomplete. 24 of the campuses our directory shows as operating have no planning record that uses the words "data centre" at all.

Applications use other words. Examples confirmed in the files:

  • "Electrical rooms for electronic operations": the phrase on applications at or next to Amazon's sites on Belgard Road and Greenhills Road in Tallaght (SD16A/0093, SD14A/0232), and at the Hexagon Building in Blanchardstown (FW13A/0067).
  • "ICT facility": three buildings, 66,630 m², with 20 generators each, at Kish Business Park, Arklow (Wicklow 20/1088), later amended to five buildings and an energy centre.
  • A warehouse converted to an "energy centre" with 12 generators "to power 2 data storage buildings" (Fingal FW22A/0257).
  • Warehouse space changed to "data storage use" in Clonshaugh (Dublin City 3640/21, withdrawn).

Our reading. Much of this is standard planning language rather than concealment. "ICT facility" is how many development plans describe the use. But the effect is the same: residents, councillors and journalists searching for data centres don't find them.

How we found them

We trained a classifier on the 131 applications we already knew were data centres. We removed the obvious words, such as "data centre", so it had to learn from everything else: the other vocabulary, floor areas, generators, and location (distance to a 220 kV substation or a known campus).

In cross-validation it ranked known data centres almost perfectly (ROC AUC 1). We then read the top-ranked applications we had not already labelled, one by one.

Top-ranked new applications readConfirmedLikelyPrecision (confirmed only)Precision (incl. likely)
109190%100%
2521284%92%
5037674%86%
6044673%83%
Figure 1

One campus, many records

Count buildings and Microsoft Grange Castle is 12 data centres; count EPA licences and it is 3; count planning files and it is 26. We count it as one campus.

Microsoft Grange Castle: one campus, many recordsMicrosoft Grange Castle: 12 mapped buildings, 9 rated properties, 26 planning files, 3 epa licences, 1 appeals, all joined into one campus. It drew 154.5 MW on average in 2025.ONE CAMPUS · SOUTH DUBLINMicrosoft Grange CastleMicrosoft DSFMicrosoft DUB03 / DUB04Microsoft DUB05Microsoft DUB06Microsoft DUB07Microsoft DUB08Microsoft DUB09Microsoft DUB10Microsoft DUB12Microsoft DUB13Microsoft DUB14Microsoft DUB1512 buildings · 19.5 ha of roof · 154.5 MW average draw, 202512Mapped buildingsOpenStreetMap9Rated propertiesvaluation list26Planning files9 found only by our model3EPA licencesgenerator fleets1AppealsAn Coimisiún Pleanála
Microsoft Grange Castle: one campus, many recordsMicrosoft Grange Castle: 12 mapped buildings, 9 rated properties, 26 planning files, 3 epa licences, 1 appeals, all joined into one campus. It drew 154.5 MW on average in 2025.Microsoft Grange CastleONE CAMPUS · SOUTH DUBLIN12 buildings · 154.5 MW avg, 202512Mapped buildings9Rated properties26Planning files3EPA licences1Appeals

Microsoft Grange Castle in South Dublin is the campus with the most public records joined to it. OpenStreetMap shows 12 separate buildings, the valuation list rates 9 properties, 3 EPA licences cover its generator fleets, and 26 planning files describe its halls, extensions and amendments (9 of them found only by our planning-register model because their descriptions never say "data centre"). Every one of those is a legitimate thing to count, which is why published totals for Ireland range so widely. A campus is the unit that matches how operators build and how the grid connects them.

Sources: StackPath directory, 10 Oct 2026 · OpenStreetMap contributors (ODbL), 10 Oct 2026 · EPA LEAP, 3 Oct 2026 · Tailte Éireann valuation list, 3 Oct 2026 · Council planning registers, 10 Oct 2026

What it changed

The search widened our planning set to 156 applications, gave 2 operating campuses their first planning record, and surfaced a new campus at Kish Business Park, Arklow. The campus count and planning statistics on this site include them.

It also matters for anyone quoting "the number of data-centre planning applications". Counts built from keyword searches undercount, and they undercount the largest operators most, because those use their own house wording.

For councils, it is a practical problem. Development plans now set conditions on data centres: waste heat in Dublin City (CEE25), at least 30% renewables in Kildare (RE O72), and policies in South Dublin (EDE7) and Fingal (DMSO92). Those conditions only apply if planners recognise the application as a data centre in the first place.

Limits

The model ranks; people decide. Every application counted was read. The model is weaker at finding data centres in places with none yet: in the top 20 of that list, precision was 10%. A planning application is not a building, and our build-time analysis shows many permissions are never used.

Questions people ask

How many data-centre planning applications are there in Ireland?
Our set has 156 applications that describe a data centre or its ancillary works, including 69 that keyword searches miss (Oct 2026).
What is an 'ICT facility' in Irish planning?
A common planning term for buildings that house computer and network equipment. Many data centres are applied for under that name.
Is there a data centre planned in Arklow?
Yes. Echelon's Avoca River Park site is under construction, and a separate permission at Kish Business Park covers several ICT buildings with generators (Wicklow County Council).

How we know

  • Text classifier (word and phrase features with the obvious data-centre terms removed) plus location features, trained on known applications and scored over every application in the planning mirror.
  • Precision is measured by reading each top-ranked application. "Confirmed" means the file names a data-centre use or operator; "likely" means strong but indirect evidence.

Sources

  • Council planning registers via planningregister (PlanSight mirror) · 2026-10-03
  • StackPath ml_hidden_dc pipeline · 2026-10-03

Numbers on this page are read from our data build of 10 October 2026 and update when it changes. Text marked Our reading is our analysis, not a sourced fact. Found a mistake? See corrections; method notes are on methodology.