The Radar · US desk · daily

United States: what's changing for data centres

Top story, 12 October 2026: FERC rejects PJM's plan to curtail new data centres that bring no capacity, accepts a 50 MW large-load registry. 11 items this week on the United States desk, each linked to its source (FERC order, ER26-3515-000 (197 FERC ¶ 61,019)).

Updated 12 October 2026 · data build 2026-10-10 · how we know · corrections

County rezonings and moratoriums, grid operators (PJM, ERCOT and others), federal and state rules, and the campuses that set the scale.

RegulatorPJM region

FERC rejects PJM's plan to curtail new data centres that bring no capacity, accepts a 50 MW large-load registry

On 9 Oct FERC accepted PJM's definition of a Large Load (50 MW or more of peak at one site, affiliated loads within one mile counted together) and a Large Load Registry, effective 12 Oct. It rejected the rest of PJM's 13 Aug filing: the Interim Resource Adequacy Service, under which new large loads without matching new capacity could be curtailed from June 2027, the bring-your-own-new-capacity rules, and removing such loads from the capacity auction's demand curve. FERC found parts of the plan appear to regulate retail customers, outside its authority, and that PJM had not justified the rest, and it gave guidance for a refiling. PJM had told FERC it will be short of capacity from the 2027/28 delivery year, largely because of data-centre growth.

Why it matters. The largest US grid market has lost, for now, its tool for rationing power to new data centres after they connect. European operators ration at the point of connection instead; PJM is left with price, and its last auction cleared at the cap.

Our data addsPJM's 2028/29 capacity auction cleared at the $325/MW-day cap and 6,831 MW short of its reliability requirement (PJM, 14 Jul 2026). Our Europe restrictions table counts 10 connection rules among 32 measures (Ireland, Denmark, Belgium, Germany), the stage PJM's order leaves to US states. /us/power-crunch → /europe/data-centre-restrictions →

50 MW
Large Load threshold (cumulative peak at one site)
Reported elibrary.ferc.gov, 9 October 2026

Sources: FERC order, ER26-3515-000 (197 FERC ¶ 61,019), 9 October 2026 · Utility Dive (backstop procurement timetable), 8 October 2026

Next, 22 October 2026: PJM special Members Committee on the backstop procurement; registry compliance filing due within 30 days of 9 Oct; 2029/30 auction in December

RegulatorNorth Carolina

Duke files a North Carolina large-load tariff agreed with Amazon, Google and Microsoft: upfront funding, 75% minimums

Why it matters. Three days after FERC accepted Duke's wholesale terms, the retail side is being fixed by settlement with the buyers themselves. For Europe, it is a worked template of who pays for no-show loads, set in the tariff before connection.

Sources: Duke Energy, Agreement and Stipulation of Settlement on Large Load Tariff, NCUC E-7 Sub 1329 and E-2 Sub 1380 (copy hosted by SELC)

Next: North Carolina Utilities Commission decision on the settlement; proposed effective date 1 Jan 2027

DealIllinoisPennsylvania

Google and Constellation sign an 890 MW nuclear uprate deal; DOE offers Vistra up to $4.2bn for 433 MW more

Why it matters. Uprates add firm power inside existing grid connections, the scarcest input in PJM. Contracts with Google, Meta and Amazon and a federal loan offer now back about 1.5 GW of new nuclear output in PJM, from 2028 on.

Sources: Constellation and Google release

Next: DOE's loan to Vistra closes only after technical, legal, environmental and financial conditions; NRC uprate applications

Coming up

Next dated events in this desk's open stories.

Developing stories

Every update, in order, on the story's own page.

Everything on the United States desk

Newest first; filter by type or by the question an item informs.

11 itemslatest 12 October 2026newest first

RegulatorPJM region

FERC rejects PJM's plan to curtail new data centres that bring no capacity, accepts a 50 MW large-load registry

On 9 Oct FERC accepted PJM's definition of a Large Load (50 MW or more of peak at one site, affiliated loads within one mile counted together) and a Large Load Registry, effective 12 Oct. It rejected the rest of PJM's 13 Aug filing: the Interim Resource Adequacy Service, under which new large loads without matching new capacity could be curtailed from June 2027, the bring-your-own-new-capacity rules, and removing such loads from the capacity auction's demand curve. FERC found parts of the plan appear to regulate retail customers, outside its authority, and that PJM had not justified the rest, and it gave guidance for a refiling. PJM had told FERC it will be short of capacity from the 2027/28 delivery year, largely because of data-centre growth.

Why it matters. The largest US grid market has lost, for now, its tool for rationing power to new data centres after they connect. European operators ration at the point of connection instead; PJM is left with price, and its last auction cleared at the cap.

Our data addsPJM's 2028/29 capacity auction cleared at the $325/MW-day cap and 6,831 MW short of its reliability requirement (PJM, 14 Jul 2026). Our Europe restrictions table counts 10 connection rules among 32 measures (Ireland, Denmark, Belgium, Germany), the stage PJM's order leaves to US states. /us/power-crunch → /europe/data-centre-restrictions →

50 MW
Large Load threshold (cumulative peak at one site)
Reported elibrary.ferc.gov, 9 October 2026

Sources: FERC order, ER26-3515-000 (197 FERC ¶ 61,019), 9 October 2026 · Utility Dive (backstop procurement timetable), 8 October 2026

Next, 22 October 2026: PJM special Members Committee on the backstop procurement; registry compliance filing due within 30 days of 9 Oct; 2029/30 auction in December

RegulatorNorth Carolina

Duke files a North Carolina large-load tariff agreed with Amazon, Google and Microsoft: upfront funding, 75% minimums

On 6 Oct Duke Energy Carolinas and Duke Energy Progress filed a settlement on a large-load tariff with the North Carolina Utilities Commission (dockets E-7 Sub 1329, E-2 Sub 1380). Signatories include the Public Staff, Amazon Data Services, Google, Microsoft and the Defense Department. It covers loads of 50 MW+ at 80% load factor, or 150 MW+ at any load factor: customers prepay dedicated facilities, post letters of credit for network upgrades, commit for 10 or 15 years and pay at least 75% of contract demand. Exit notice runs 24 to 48 months by size. The Commission has yet to approve it; the tariff would apply from 1 Jan 2027.

Why it matters. Three days after FERC accepted Duke's wholesale terms, the retail side is being fixed by settlement with the buyers themselves. For Europe, it is a worked template of who pays for no-show loads, set in the tariff before connection.

75%
minimum billing demand as a share of contract demand
Reported selc.org, 6 October 2026
150 MW
contract demand that brings any customer under the tariff
Reported selc.org, 6 October 2026

Sources: Duke Energy, Agreement and Stipulation of Settlement on Large Load Tariff, NCUC E-7 Sub 1329 and E-2 Sub 1380 (copy hosted by SELC), 6 October 2026 · Axios Raleigh, 7 October 2026

Next: North Carolina Utilities Commission decision on the settlement; proposed effective date 1 Jan 2027

DealIllinoisPennsylvania

Google and Constellation sign an 890 MW nuclear uprate deal; DOE offers Vistra up to $4.2bn for 433 MW more

Constellation and Google signed a 20-year power purchase agreement on 6 Oct to fund 890 MW of uprates at 11 reactors on six sites in Illinois, Pennsylvania and New Jersey (over $4.3bn of Constellation investment, first uprate by 2028), plus a 15-year supply deal for 2,700 MW of existing PJM output. On 5 Oct DOE offered Vistra a conditional loan of up to $4.2bn for uprates adding 433 MW at Beaver Valley, Davis-Besse and Perry; Power Engineering reports that capacity is part of Vistra's 20-year PPAs with Meta. On 30 Sep Constellation and Amazon announced a 20-year PPA tied to a 190 MW expansion of Calvert Cliffs, due 2030-2032 (Utility Dive).

Why it matters. Uprates add firm power inside existing grid connections, the scarcest input in PJM. Contracts with Google, Meta and Amazon and a federal loan offer now back about 1.5 GW of new nuclear output in PJM, from 2028 on.

Our data addsPJM's 2028/29 auction cleared 524.7 MW (UCAP) of new generation and uprates (PJM, 14 Jul 2026). These uprates total about 1,513 MW nameplate, due 2028-2034: not like for like, but roughly three times what the last auction drew. /us/power-crunch →

890 MW
uprates under the Constellation-Google PPA
Reported constellationenergy.com, 6 October 2026
$4.2bn
DOE conditional loan commitment to Vistra (up to)
Reported energy.gov, 5 October 2026
433 MW
new capacity from Vistra's uprates
Reported energy.gov, 5 October 2026
1,513 MW
sum of the three uprate programmes (890 + 433 + 190)
Calculated utilitydive.com, 6 October 2026

Sources: Constellation and Google release, 6 October 2026 · US Department of Energy release, 5 October 2026 · Power Engineering, 7 October 2026 · Utility Dive, 6 October 2026

Next: DOE's loan to Vistra closes only after technical, legal, environmental and financial conditions; NRC uprate applications

DealCheyenne, Wyoming

Black Hills to build 564 MW of gas and run a 2.1 GW private microgrid for a planned Google data centre in Cheyenne

Black Hills Corp. said on 6 Oct (8-K) it has signed agreements, effective 30 Sep and running to 2048, to serve a planned Google data centre in Cheyenne, Wyoming. A non-regulated affiliate will build 564 MW (nameplate) of new gas generation at its Cheyenne Prairie station for $1.8bn over 2027-2029, giving up to 590 MW of grid-connected service with market purchases. Black Hills will also manage about 2.1 GW of third-party Wyoming resources through a private microgrid under its Large Power Contract Service tariff: 2.7 GW in all with reserves. Service starts in late 2027 and reaches peak load in 2030. The company says Google bears all costs of serving the site, and that Google has advanced $399m, refundable, for long-lead equipment.

Why it matters. A utility building dedicated gas and a private microgrid for one customer, who pays all costs, is one way US data centres get around grid queues. Ireland's 2025 rules also make data centres bring their own dispatchable generation; Wyoming shows the scale that model reaches in the US.

New to our dataNot yet in our US campus table, which lists 9 gas-backed campuses (20.4 GW announced), including Project Jade (Tallgrass/Crusoe, 1,150 MW) in the same county. Ireland's CRU connection policy (Dec 2025) requires new data centres to bring dispatchable generation or storage. /us/power-crunch → /europe/data-centre-restrictions →

564 MW
new gas generation (nameplate) at Cheyenne Prairie
Reported sec.gov, 6 October 2026
2.1 GW
third-party resources managed through a private microgrid
Reported sec.gov, 6 October 2026
$1.8bn
Black Hills generation investment, 2027-2029
Reported sec.gov, 6 October 2026
$399m
Google's refundable advance for long-lead equipment
Reported sec.gov, 6 October 2026

Source: Black Hills Corp. 8-K, exhibit 99.1 (SEC EDGAR), 6 October 2026

Next: Gas plant construction from 2027; service from late 2027, peak load 2030 (Black Hills)

DecisionSpartanburg County, SCColleton County, SC

Spartanburg suit over a $2.8bn campus dismissed, Colleton settles a no-build zone, a developer sues Frederick

A Spartanburg County, SC judge dismissed residents' challenge to Valara Holdings' $2.8bn data centre on 6 Oct for lack of standing and a skipped administrative appeal, without ruling on the merits; the group says it will appeal (FOX Carolina). In Colleton County, SC, a settlement with SELC's clients creates a Data Center Exclusion Area over most of the county's ACE Basin (Live 5, 5 Oct). On 8 Oct Quantum Maryland sued Frederick County, MD and County Executive Jessica Fitzwater, alleging her freeze on data-centre applications was political; she calls the claims false (WBFF).

Why it matters. Courts are now deciding where US campuses go as often as zoning boards are: one challenge failed on procedure, one ended in a mapped no-build zone, and a developer is testing whether a local freeze can be undone in court.

$2.8bn
Valara Holdings' Spartanburg County data-centre investment
Reported foxcarolina.com, 7 October 2026

Sources: FOX Carolina, 7 October 2026 · Live 5 News (WCSC), 5 October 2026 · FOX45 (WBFF), 10 October 2026

Next: Spartanburg appeal; Valara's second permit (four buildings, power yard) pending with the county; Frederick County's response in circuit court

DecisionLoudoun County, Virginia

Loudoun shelves ending data-centre grandfathering after the county attorney warns of $60m in litigation

Loudoun County's Board of Supervisors took no action on 6 Oct on ending the 2025 grandfathering that lets some data-centre projects proceed through staff review without a Board vote, after the county attorney warned it could cost $60m in litigation; the chair tabled the item, and a motion to hire an outside auditor, for a later meeting (FOX 5 DC). The county counts at least 17 grandfathered cases totalling more than 11 million sq ft, which its 15 Sep pause does not touch. That pause, passed 7-1-1, defers Board action on legislative data-centre and substation applications during the Phase 2 rules review, within Virginia's 12-month limit; staff bring the formal resolution on 20 Oct (county statement, 16 Sep).

Why it matters. In Loudoun, the core of Northern Virginia's Data Center Alley, the pause slows new rezonings while grandfathered projects keep moving. The legal cost of reversing past approvals sets how fast a county can brake.

$60m
litigation risk cited by the county attorney
Reported fox5dc.com, 7 October 2026

Sources: FOX 5 DC, 7 October 2026 · Loudoun County statement, 16 September 2026

Next, 20 October 2026: Board business meeting: formal resolution on the pause

DecisionMemphis, TennesseeShelby County, Tennessee

Memphis council delays its data-centre moratorium vote to 20 Oct; the mayor orders a 90-day study, not a pause

Memphis City Council narrowly voted on 6 Oct to put off its final vote on a moratorium on new data centres until 20 Oct, after protests halted the meeting (WMC/Gray News; Commercial Appeal). On 9 Oct Mayor Paul Young issued an executive order for a 90-day study recommending rules for hyperscale data centres on land use, neighbourhood protections, air quality and energy and utility costs, with at least three public sessions; it does not impose a moratorium (Commercial Appeal). The Shelby County Commission is to take a first vote on a moratorium of its own (Daily Memphian, 11 Oct; date not given). xAI's Colossus sites are in the Memphis area.

Why it matters. Memphis is home to xAI's Colossus 1, in our US campus table. The 20 Oct vote shows whether local opposition can slow growth at an established AI cluster, not only stop new sites.

Our data addsOur US campus table lists xAI Colossus 1 (Memphis, 247 MW of permitted turbines, Shelby County Health Department, Jul 2025) and the Colossus 2 plant at Southaven, Mississippi (1,200 MW). /us/power-crunch →

Sources: WMC / Gray News (via WSMV), 7 October 2026 · The Commercial Appeal, 9 October 2026 · Daily Memphian, 11 October 2026

Next, 20 October 2026: Memphis City Council final vote on the moratorium

DecisionManatee County, FloridaLexington, Kentucky

Manatee County and San Francisco pause data centres, Lexington extends to 2027, a Missouri court blocks a pause

Manatee County, Florida, adopted a 12-month stop on new data-centre applications in unincorporated areas on 8 Oct (Ordinance 26-42) while it writes rules; Florida's new law defines a large-scale data centre as 50 MW or more of monthly peak load (Bradenton Times). Lexington-Fayette's council voted 11-0 on 8 Oct to extend its moratorium to 31 Oct 2027 (WUKY). San Francisco supervisors unanimously passed a 45-day moratorium on 6 Oct; Oakland and Los Angeles County are weighing similar steps (KTVU). Not every pause holds: on 6 Oct a Missouri circuit court enjoined Benton County's August moratorium, finding it rested on no findings that data centres harm health, in a suit by developer NSI 6 over a 12-acre site in Warsaw (KMMO).

Why it matters. Local land-use pauses keep spreading in the US, now including the Bay Area, and courts are starting to test them. Europe's brakes are mostly grid-connection rules: our restrictions table has no active local moratorium.

Our data addsOur Europe restrictions table (32 measures, 11 Oct) has 5 moratoriums, none active (3 proposed, 1 lifted, 1 replaced), against 10 connection rules. We do not yet count US local moratoriums. /europe/data-centre-restrictions →

12 months
Manatee County moratorium length
Reported thebradentontimes.com, 8 October 2026
50 MW
Florida's large-scale data-centre threshold (monthly peak load)
Reported thebradentontimes.com, 8 October 2026

Sources: The Bradenton Times, 8 October 2026 · WUKY, 9 October 2026 · KTVU FOX 2, 7 October 2026 · KMMO, 8 October 2026

Next, 20 October 2026: Fort Collins council votes on a moratorium; Lexington's zoning proposals return for second reading on 22 Oct

RegulatorNorth CarolinaSouth Carolina

FERC accepts Duke Energy Carolinas' 15-year, 75% minimum-payment terms for new loads of 100 MW or more

On 9 Oct FERC accepted Duke Energy Carolinas' revised network transmission service agreement, effective 1 Aug 2026. Wholesale customers adding or moving 100 MW or more of load must commit for 15 years and pay a shortfall charge if their use falls below 75% of the scheduled MW, so that grid upgrades built for a load that never arrives are not paid for by others. Duke told FERC it applies the same 100 MW threshold and 15-year term to retail customers, and that nine requests for new large loads of 102 MW to 945 MW have reached it since 2012. Two commissioners concurred separately; Commissioner Chang dissented, saying the 15-year commitment is backed by little security, about one to five months of transmission revenue.

Why it matters. Who carries the risk of a data centre that never shows up is being settled tariff by tariff. FERC accepted a 15-year minimum-payment model for wholesale customers, with a dissent on how little security backs it.

100 MW
load size that triggers the 15-year commitment
Reported elibrary.ferc.gov, 9 October 2026
75%
minimum share of scheduled MW paid for, or a shortfall charge
Reported elibrary.ferc.gov, 9 October 2026

Source: FERC order, ER26-2691 (197 FERC ¶ 61,020), 9 October 2026

Next: Further large-load tariff filings; FERC's own large-load interconnection rule (RM26-4)

DecisionBrighton, COBeaufort County, NC

Brighton, Colorado loses a 2.5m sq ft campus and backs a one-year pause; Beaufort County, NC pauses too

Developers withdrew the rezoning application for a 2.5m sq ft, eight-building data-centre campus in north-east Brighton, CO, and on 6 Oct the city council gave initial approval to a one-year moratorium on new data centres while it writes rules (Denver7, CPR). The city says it has no sign the plan will be resubmitted. In North Carolina, Beaufort County commissioners voted 6-1 on 5 Oct for a one-year moratorium on accepting or approving data-centre applications, although none is proposed there (WITN).

Why it matters. Pre-emptive pauses keep spreading to places with no live project, and in Brighton the backlash ended a campus before any vote. The US count of local pauses is now a running number to set against Europe's national restrictions.

2.5 m sq ft
Brighton campus withdrawn (eight buildings)
Reported denver7.com, 7 October 2026

Sources: Denver7, 7 October 2026 · Colorado Public Radio, 7 October 2026 · WITN, 5 October 2026

Next: Brighton moratorium final reading (date unchecked); Fort Collins vote 20 Oct; Memphis vote 20 Oct

RegulatorAlabama

Alabama PSC adopts a 90-day review of Alabama Power contracts with data centres of 150 MW or more

The Alabama Public Service Commission voted on 6 Oct to adopt procedures for reviewing Alabama Power's contracts with large data centres covered by Act 2026-610, those of 150 MW or more (SELC). Commissioners must vote on each contract within 90 days, but a contract is deemed approved if they do not; July's draft had a 60-day deemed approval. Alabama Power files a public summary naming the customer, location and maximum contracted capacity, and a confidential package with the full contract and a cost-revenue analysis, including a Rate Impact Measure test, for PSC staff and the Attorney General. There is no public hearing or intervention in individual reviews (WBMA).

Why it matters. Who pays for data-centre power is being settled state by state. Alabama chose a fast, mostly confidential review; Duke's FERC-accepted terms rely on 15-year minimum payments instead.

150 MW
data-centre size covered by Act 2026-610 reviews
Reported selc.org, 6 October 2026

Sources: WBMA (ABC 33/40), 6 October 2026 · Southern Environmental Law Center statement, 6 October 2026

Next: First Alabama Power data-centre contract filed under the new procedure

Follow:United States (RSS)All desks (RSS)JSON feed

The questions this desk feeds

Items in the last 30 days for each of the site's questions, from this desk.

Ireland's data-centre power gap0

Which Irish data-centre projects can get power, when, from where, and under which CRU rules?

Nothing this month.

Our data: /ireland/firm-power-gap · /ireland/capacity-market-delivery · /data-centres

What gets built, what stalls5

Where do data-centre projects move forward, and where do permits, appeals, moratoriums or cancellations stop them?

Latest: Spartanburg suit over a $2.8bn campus dismissed, Colleton settles a no-build zone, a developer sues Frederick

Our data: /data-centres · /councils · /europe/data-centre-restrictions

The rules that decide8

Which laws, regulations and public programmes change what gets built: LEU policy, EU energy rating, CADA, AI gigafactories, permitting reform?

Latest: FERC rejects PJM's plan to curtail new data centres that bring no capacity, accepts a 50 MW large-load registry

Our data: /policy · /europe/data-centre-energy-rules · /europe/ai-gigafactories

Sovereignty: substance or protectionism?0

Does sovereign-cloud and buy-European policy build real capability, or mostly raise costs?

Nothing this month.

Our data: /europe/sovereign-cloud · /europe/claims-checked · /europe/neoclouds

Where this desk looks now

Calculated

44 news sources and 34 watched pages (20 of them the primary sources behind this site's own datasets). 2 daily runs so far: 120 lines scored, 11 kept. Each source's score is the share of its recent checks that found something worth keeping; the scan spends most of its fixed daily budget at the top of this list and a few slots on the least-known sources. Each watched page learns how often it really changes.

SourceDeskScoreChecksKept
Google News: county rezonings, permits and moratoriumsUS75%16
Google News: Northern Virginia data-centre fightsUS75%13
Google News: withdrawals, cancellations, delaysUS67%15
Google News: data-centre lawsuitsUS67%14
Google News: nuclear deals for data centresUS67%12
Power EngineeringUS67%11
US Department of Energy newsroomUS67%11
Google News: federal data-centre policyUS67%11
Google News: Georgia data centres and Georgia PowerUS67%11
Federal RegisterUS67%00
Loudoun County data-centre pipeline (GIS)US67%00
Prince William County data-centre campuses (GIS)US67%00

Questions people ask

Why does a European site track US data-centre news?
Europe's AI build is measured against America's. The US desk tracks what sets the pace there (grid access, local permits, power deals and capital) so the site's Europe-versus-US comparisons rest on current events, not last year's.