Insight · offshore wind

Only the offshore wind farms that lost the State auction can power data centres

Only 1,175 MW of Ireland's planned offshore wind can count toward a data centre's 80% renewables match: Oriel and Arklow Bank 2, the two projects that lost the 2023 State auction. The 3,524 MW that won State support are excluded under CRU2025236, and no Phase 1 project has planning consent yet (Oct 2026).

By StackPath · published 3 October 2026 · updated 10 October 2026 · how we know · corrections

How many offshore wind farms does Ireland have?

One: the 25 MW first phase of Arklow Bank, built in 2004. 5 Phase 1 east-coast projects (3,799 MW) are waiting for An Coimisiún Pleanála, and every one is past its statutory decision date.

ProjectDeveloperMWState supportCan serve data centres?
Codling Wind ParkFred. Olsen Seawind and EDF Renewables (50/50; ownership unchecked)1,300ORESS1No
Dublin ArrayRWE and Saorgus Energy (Kish/Bray Offshore Wind Ltd)824ORESS1No
North Irish Sea Array (NISA)Statkraft and Copenhagen Infrastructure Partners (unchecked)500ORESS1No
Sceirde Rocks (Skerd Rocks)Fuinneamh Sceirde Teoranta (Corio Generation)450ORESS1No
Oriel Wind FarmOriel Windfarm Ltd (ESB and Parkwind/JERA Nex)375noneYes, in principle
Arklow Bank Wind Park 2Sure Partners Ltd (SSE Renewables)800noneYes, in principle
Tonn Nua (SC-DMAP site A)Helvick Head Offshore Wind DAC (ESB and Ørsted)900Tonn NuaNo
South Coast DMAP sites B-Dnot yet auctioned4,100future ORESS (expected)No
Arklow Bank Wind Park (phase 1)operating since 200425none (existing)No

Why can't data centres use State-supported wind?

The CRU's December 2025 rules require 80% of a new data centre's annual demand to be matched by new renewable generation in Ireland. The decision paper is explicit about what does not count:

"Renewable generation which has previously been or is currently contracted through existing support mechanisms (e.g. REFIT, RESS, ORESS) cannot be used" (CRU/2025/236, Large Energy Users connection policy decision, p.64)

Codling, Dublin Array and the North Irish Sea Array won contracts in the first offshore auction (ORESS 1). Tonn Nua won the south-coast auction in late 2025. Those 3,524 MW are excluded for the life of their contracts.

Oriel (375 MW) and Arklow Bank 2 (800 MW) lost that auction. They must find corporate buyers instead, which is exactly what a data centre needs.

Is it enough for data centres?

On paper, nearly. EirGrid deems the two projects' output at about 4.63 TWh a year. Data-centre growth to 2034 needs about 4.16 TWh a year of new renewables to meet the 80% test (EirGrid forecasts as cited by the CRU; our calculation).

In practice, not yet. Neither project has planning consent, and no power purchase agreement has been signed: SSE said in June 2026 it was still "finalising details of a commercial route to market" for Arklow Bank 2.

End of yearOffshore MW (our estimate)Of which data-centre eligibleEirGrid base caseEirGrid low case
20262503030
20272503030
20282503030
20292503030
20302501,35030
20314003751,95030
20321,2001,1752,520400
20333,8241,1753,120830

Our estimate assumes each project's commercial operation date from its planning stage and public statements; EirGrid's figures are from its adequacy assessment.

The goalposts moved

On 27 March 2026 the ORESS 1 contract longstop moved from 31 December 2031 to 31 December 2034, and the planning longstop from June 2028 to June 2029. The 2030 offshore target of 5 GW is now framed as "in construction by 2030". Sceirde Rocks (450 MW) withdrew in December 2025.

Why it matters

Our reading. The State's auction was meant to pick winners. For data centres it did the reverse: losing made Oriel and Arklow Bank 2 the only offshore projects they can buy from. Their bargaining power has risen, and their timing, around 2031–32 at the earliest, now sets the pace for any new data centre that hopes to meet the 80% rule with offshore wind.

Until then, permitted onshore wind without State support is the scarce product. Only about 1.4 GW of it exists in the planning system.

Questions people ask

Can data centres buy offshore wind power in Ireland?
Only from projects outside State support. Today that means Oriel and Arklow Bank 2 (1,175 MW), neither of which has planning consent or a signed buyer (Oct 2026).
When will Ireland's offshore wind farms be built?
Not before about 2031 on our estimate, given planning delays. EirGrid's base case assumes 1,350 MW by the end of 2030; its low case 30 MW.
What is ORESS?
The Offshore Renewable Electricity Support Scheme: the State auction that gives offshore wind farms a guaranteed price for about 20 years. Output under it can't count for data centres' 80% rule.

How we know

  • Project list, capacities, support status and planning cases from An Coimisiún Pleanála case pages, EirGrid auction results and developer statements, checked Oct 2026.
  • Eligibility read against CRU2025236 s.3.5.2 (quoted above). Deemed output uses EirGrid's capacity factors (implied 45%).