GB demand connections reform (Ofgem)

Latest, 7 October 2026: Ofgem proposes letting demand customers self-build sole-use transmission links; consultation to 13 Nov. Next: Self-build consultation closes (13 November 2026). 1 update since 12 October 2026 on the Europe desk, each linked to its source (Ofgem consultation page).

Updated 12 October 2026 · data build 2026-10-10 · how we know · corrections

Europe deskopen1 updatesince 12 October 2026

Next, 13 November 2026: Self-build consultation closes

Every update, newest first

Informs: Who gets grid power, and where · The rules that decide

RegulatorEuropeGreat Britain

Ofgem proposes letting demand customers self-build sole-use transmission links; consultation to 13 Nov

Ofgem on 7 Oct proposed that demand, generation and storage customers may build all sole-use assets from their connection point to the existing transmission system (lines, project substations) and transfer them to the transmission owner, dropping today's limit of sites within 2 km. The consultation, under the Connect strand of its demand connections reform, closes 13 Nov 2026. The same day Ofgem rejected the industry modifications CMP330 and CMP374 on the 2 km limit.

Why it matters. Would let large loads such as data centres speed up their own connection works instead of waiting for the network owner. It is a proposal, not yet a rule, and follows the data-centre connections consultation that closed on 17 Sep.

Source: Ofgem consultation page, 7 October 2026

Next, 13 November 2026: Consultation closes