Appeal board grants Google's Grange Castle data-centre expansion, 735 days after the appeal

Latest, 23 September 2026: Appeal board grants Google's Grange Castle data-centre expansion, 735 days after the appeal. Next: Judicial-review window (eight weeks from the order) and a commencement notice on the national register. 1 update since 12 October 2026 on the Ireland desk, each linked to its source (An Coimisiún Pleanála case PL06S.320852).

Updated 12 October 2026 · data build 2026-10-10 · how we know · corrections

Ireland deskopen1 updatesince 12 October 2026

Next: Judicial-review window (eight weeks from the order) and a commencement notice on the national register

Every update, newest first

Informs: What gets built, what stalls · Ireland's data-centre power gap

DecisionIrelandSouth Dublin

Appeal board grants Google's Grange Castle data-centre expansion, 735 days after the appeal

An Coimisiún Pleanála granted Google Ireland Limited ten-year permission, with conditions, for a data storage facility at Grange Castle Business Park South, Dublin 22 (council ref. SD24A/0164W, case PL06S.320852). The order was signed on 23 September 2026; Google's appeal against South Dublin County Council's 2024 refusal was lodged on 18 September 2024. The Echo reports a 72,400 m² building with eight data halls, about 800 construction jobs and about 50 permanent jobs.

Why it matters. One of the few large Irish data-centre permissions since the CRU's new connection rules, and a test of how long appeals now take: Google says it already held a 2021 EirGrid connection.

Our data addsOur planning data puts the median data-centre appeal at 462 days from lodging to decision (16 decided appeals; three in four under 665 days). At 735 days this one sits beyond that range. /data-centres →

735 days
appeal lodged to decision signed
Calculated pleanala.ie, 23 September 2026
72,400 m²
floor area sought
Reported echo.ie, 6 October 2026

Sources: An Coimisiún Pleanála case PL06S.320852, 23 September 2026 · The Echo, 6 October 2026