The Radar · story

Mayo Data Hub's Killala data centre

Latest, 15 September 2026: Appeal board refuses Mayo Data Hub's Killala data centre, citing no grid agreement and the Climate Action Plan. Next: About eight weeks from the order: judicial-review window closes (10 November 2026). 1 update since 12 October 2026 on the Ireland desk, each linked to its source (An Coimisiún Pleanála case PL16.322575 (order signed 15 Sep 2026)).

Updated 12 October 2026 · data build 2026-10-10 · how we know · corrections

Ireland deskopen1 updatesince 12 October 2026

Next, 10 November 2026: About eight weeks from the order: judicial-review window closes

Every update, newest first

Informs: What gets built, what stalls · Ireland's data-centre power gap · The rules that decide

DecisionIrelandMayo

Appeal board refuses Mayo Data Hub's Killala data centre, citing no grid agreement and the Climate Action Plan

An Coimisiún Pleanála refused permission for Mayo Data Hub Limited's data centre at Mullafarry and Tawnaghmore Upper, Killala (case PL16.322575, council ref. 2460708), overturning Mayo County Council's grant of 25 April 2025. The order, signed on 15 September 2026, says the applicant failed to show a fixed grid connection agreement, existing grid capacity, significant on-site renewables or engagement with Corporate PPAs, and so failed to show consistency with the Climate Action Plan 2025 and the Government Statement on the Role of Data Centres. The scheme was a single building of about 29,076 m² with 25 backup generators. The decision followed the inspector's recommendation; the third-party appeal had been lodged on 21 May 2025.

Why it matters. A refusal resting on grid and climate grounds rather than local planning: on this reading, a data centre without a grid agreement and a renewables route can't clear ACP, whatever the council decided. The Grange Castle grant in the same month leaned on an existing EirGrid connection.

Our data confirmsOur lifecycle dataset already records the refusal (finalOutcome refused, 15 Sep 2026). At 482 days from appeal to decision it sits just above our median data-centre appeal of 462 days (n=16). /data-centres → /councils/mayo →

482 days
appeal lodged (21 May 2025) to order signed (15 Sep 2026)
Calculated pleanala.ie, 15 September 2026
29,076 m²
gross floor area sought
Reported pleanala.ie, 15 September 2026

Sources: An Coimisiún Pleanála case PL16.322575 (order signed 15 Sep 2026), 15 September 2026 · Irish Examiner, 18 September 2026

Next, 10 November 2026: About eight weeks from the order: judicial-review window closes

Ireland desk →The Radar →