Europe · country profile

Data centres and AI in Belgium, ranked against Europe and the US

Belgium ranks 4th of 28 European countries for highest share of businesses using AI (34.5%, 2025); its weakest is 17th of 24 for most TOP500 supercomputing power (11.0 PF, 2026/06). Data centres use about 4% of its electricity (BCG, 2024, estimate). It hosts no EU AI Factory (role: Antenna). Sources: Eurostat, Ember, EuroHPC, TOP500, Epoch AI; data as of 2026-10-12.

Updated 12 October 2026 · data build 2026-10-10 · how we know · corrections

Where Belgium ranks among 31 European countries

Rank 1 = best on the measure's own terms (cheapest, lowest carbon, highest share, most). Each rank is among the European countries with a figure, so the "of" number differs. Belgium is an EU member. Measured

8th
of 26 · Big-user electricity price; 1 = cheapest
€0.101/kWh · H1 2026 · Eurostat nrg_pc_205
10th
of 27 · Wholesale power, last 12 months; 1 = cheapest
€101/MWh · 2025-10 to 2026-09 · Ember European wholesale prices
14th
of 31 · Grid carbon intensity; 1 = lowest carbon
151 g/kWh · 2025 · Ember yearly electricity data
18th
of 31 · Clean power share; 1 = highest share
72.1% · 2025 · Ember yearly electricity data
3rd
of 15 · Data centres' share of electricity; 1 = highest share (exposure, not success)
4% · 2024 · BCG est.
4th
of 28 · Businesses using AI; 1 = highest share
34.5% · 2025 · Eurostat isoc_eb_ai
12th
of 29 · People using generative AI; 1 = highest share
42% · 2025 · Eurostat isoc_ai_iaiu
17th
of 24 · TOP500 supercomputing power; 1 = most
11 PF · 2026/06 · TOP500
9th
of 27 · Share of EU server imports; 1 = largest share
1.2% · 2025-08 to 2026-07 · Eurostat Comext DS-045409
0
EU AI Factories hosted
role: Antenna

No figure for Belgium on: GPU-cluster compute (Epoch AI).

Download CSV ↓

Source: Eurostat nrg_pc_205 · Ember European wholesale prices (via StackPath eu_power_prices) · Ember yearly electricity data (CC BY 4.0) · BCG, Belgium: the power of compute (via The Brussels Times) · Eurostat isoc_eb_ai · Eurostat isoc_ai_iaiu · TOP500, June 2026 list (via eu_compute) · EuroHPC JU (via eu_ai_factories) · Eurostat Comext DS-045409 · EU EED data-centre dashboard (via eu_dc_capacity) · as of 2026-10-12 · Compiled by StackPath

Belgium against the EU-27 average and the US

Same measure, same source family, nearest year. A dash means no comparable figure, not zero. Measured

How to read this. The first column is Belgium; under it, the gap to the EU-27 (percentage points for shares, a multiple for amounts). Per-person rows divide by World Bank population and are our arithmetic. The US power price is EIA's average for all industrial users, not the 150 GWh+ band Eurostat uses for Europe, so read it as indicative.
MeasureBelgiumEU-27USIreland
Big-user electricity price€0.101/kWh H1 20267% below EU€0.110/kWh H2 2025€0.076/kWh 2025€0.165/kWh H1 2026
Grid carbon intensity151 g/kWh 202528% below EU211 g/kWh 2025384 g/kWh 2025263 g/kWh 2025
Clean power share72.1% 2025+1.1 pts vs EU71% 202543% 202547.7% 2025
Data centres' share of electricity4% 2024+1 pt vs EU3% 20244.4% 202323.2% 2025
Businesses using AI34.5% 2025+14.6 pts vs EU19.9% 2025–19.6% 2025
People using generative AI42% 2025+9.3 pts vs EU32.7% 2025–44.9% 2025
Electricity use per person7.2 MWh 20251.2× EU6.2 MWh 202513.3 MWh 20256.8 MWh 2025
Supercomputing per million people0.9 PF 2026/0691% below EU10.2 PF 2026/0620.6 PF 2026/061.2 PF 2026/06
GPU compute per million peopleno figure177 H100e 2025-073,660 H100e 2025-07–

Source: Eurostat nrg_pc_205, isoc_eb_ai, isoc_ai_iaiu · Ember · EIA via eu_power_prices · LBNL via US DOE (US data-centre share) · Ember Grids for data centres (Europe share) · TOP500 · Epoch AI GPU clusters · World Bank population · as of 2026-10-12 · Compiled by StackPath

Our reading. Per person, Belgium has 4.5% of the US level of TOP500 supercomputing power. Epoch's database covers only part of the world's AI compute, and private clusters are under-recorded everywhere. Estimate

Power: 72% clean generation, €0.101/kWh for the largest users

Generation mix in 2025 (Ember); big-user prices exclude VAT (Eurostat band IG, 150 GWh a year or more). Measured

Wind18.6%
Solar14.5%
Hydro0.4%
Nuclear33.5%
Bioenergy5.1%
Gas20.8%
Other fossil7.1%

Share of generation by source, 2025. Darker bars are fossil. Demand 85.5 TWh; generation 72.1 TWh; net imports 13.4 TWh. Carbon intensity 151 gCO2e/kWh (EU-27: 211; US: 384).

€0.00€0.06€0.12€0.18€0.24H2 '22H1 '23H2 '23H1 '24H2 '24H1 '25H2 '25H1 '26
BelgiumEU-27 average

Big-user electricity price, € per kWh excluding VAT, by half-year (band IG). The EU-27 average is published later than country figures.

Wholesale power averaged €101/MWh over 2025-10 to 2026-09 (10th cheapest of 27). Taxes and levies (excluding VAT) were 6.8% of the big-user price in Eurostat's latest year-end comparison.

Source: Ember yearly electricity data (CC BY 4.0) · Eurostat nrg_pc_205 · Ember wholesale prices via eu_power_prices · Compiled by StackPath

Data centres: about 4% of Belgium's electricity

Electricity share, capacity reported under the EU Energy Efficiency Directive (EED, the EU's data-centre reporting law), grid requests, restrictions and energy rules. Reported

  • Share of electricity: 4% in 2024 (share of national electricity consumption (BCG estimate; year read from 'last year' in a May 2025 report); BCG, Belgium: the power of compute (via The Brussels Times), estimate). Europe as a whole: about 3% (2024, Ember estimate); the US: 4.4% (2023, LBNL estimate).
  • Reported to the EU (EED): 341 MW of IT capacity at 19 sites for 2025, of an estimated 48 sites that should report; average PUE (power usage effectiveness: total power ÷ IT power) 1.14. Coverage is partial, so this is a floor.

Restrictions and connection rules (2)

On top of national rules, 7 EU-level rules apply to data centres in every member state (EED reporting, the rating scheme and heat-reuse rules).

Source: BCG, Belgium: the power of compute (via The Brussels Times) · EU EED data-centre dashboard · Compiled by StackPath

Cloud and capital: €5bn pledged by hyperscalers, €0bn with visible building

Hyperscaler pledges (a pledge is not a building), sovereign-cloud offers by jurisdiction, and neocloud (GPU cloud) sites. Reported

CompanyPledgeAnnouncedEvidence
Google€5bn2025-10-08unknown

1 current pledge worth €5bn; €0bn of it is stalled (paused, delayed or cancelled). Horizons and currencies differ.

Sovereign-cloud offers under Belgium's jurisdiction (1)

Source: StackPath eu_pledges (company announcements) · StackPath sovereign_cloud · StackPath eu_neoclouds (filings, company releases) · Compiled by StackPath

Compute: 11 PF on the TOP500

Public AI Factories (EuroHPC), gigafactory bids, the TOP500 supercomputer list and Epoch AI's database of GPU clusters (in H100-equivalents: compute expressed as a number of Nvidia H100 chips). Measured

  • EuroHPC role: Antenna (BE-AIFA, selected, linked to LUMI AI Factory and JAIF).
  • TOP500 (2026/06): 2 systems, 11 PF combined (0.06% of the list).
  • GPU clusters (Epoch AI): none recorded for Belgium (Epoch's database is partial; absence means none recorded).

Source: EuroHPC JU via eu_ai_factories · TOP500 June 2026 · Epoch AI (CC BY 4.0) · StackPath eu_compute (announced clusters) · Compiled by StackPath

Chips: €1,400m of Chips Act aid approved for 1 project

Fabs and pilot lines under the EU Chips Act (aid approved is not production), and AI-chip startups headquartered here. Reported

ProjectCompanyAid €mStatus
NanoIC pilot lineimec (Chips JU)1,400operating

AI-chip startups

CompanyCityFunding $mStatus
Vertical ComputeLouvain-la-Neuve22pre-silicon

Source: StackPath eu_chips (Commission decisions, company releases) · StackPath eu_ai_chip_startups · Compiled by StackPath

AI use: 42% of people used generative AI in 2025 (EU: 33%)

Eurostat's surveys of businesses (10+ employees, any AI technology) and of people aged 16–74 (generative AI tools in the last three months), plus AI labs headquartered here. Measured

0%9%19%28%37%2021202320242025
BelgiumEU-27

Share of businesses with 10 or more employees using at least one AI technology (Eurostat isoc_eb_ai; survey years only). Belgium: 34.5% in 2025, 4th of 28.

Any use: Belgium42%
Any use: EU-2732.7%
For work: Belgium20.8%
For work: EU-2715.4%
Private use: Belgium33.5%
Private use: EU-2725.5%
Formal education: Belgium10.3%
Formal education: EU-279.3%

Share of people aged 16–74 who used generative AI tools in the three months before the 2025 survey. There is no comparable official US series.

Source: Eurostat isoc_eb_ai · Eurostat isoc_ai_iaiu · StackPath eu_ai_labs (Epoch AI, company releases) · Compiled by StackPath

Servers: 1.2% of the EU's server imports from outside the EU land in Belgium

Customs flows (Eurostat Comext), not machines installed: ports of entry such as the Netherlands count goods that move on. Measured

  • Servers (HS 847150) from outside the EU, 2025-08 to 2026-07: €357m, 9th of 27 member states.
  • All compute kit (servers, parts, network gear, chips) from outside the EU, last 12 months: €1.05bn (1% of the EU total, rank 12); servers up 7% on the previous 12 months.

Source: Eurostat Comext DS-045409 · StackPath eu_hardware_imports · Compiled by StackPath

What our data does not show for Belgium

Gaps, not zeros: a missing row means no public figure we could check, or that the series does not cover this country.

  • No EU AI Factory and no public AI gigafactory bid.

Deeper pages and other countries

Each layer has its own page with the full European table.

All 31 country profiles

Our reading. Against Ireland, Belgium pays 39% less for big-user power and runs a cleaner grid (151 vs 263 gCO2e/kWh). Where data centres and AI compute go also depends on grid access, land, fibre, tax and customers, which these measures do not capture. Our reading

Questions people ask

How much do large electricity users pay in Belgium?
Eurostat's average for users of 150 GWh or more a year in Belgium was €0.101/kWh in H1 2026, excluding VAT: 8th cheapest of 26 European countries with a figure. The EU-27 average was €0.110 (H2 2025); US industrial users paid about €0.076 in 2025 (EIA, all industrial users).
How much electricity do data centres use in Belgium?
About 4% in 2024 (BCG, Belgium: the power of compute (via The Brussels Times), estimate). Europe as a whole: about 3% (Ember, 2024); the US: 4.4% (LBNL, 2023).
Does Belgium host an EU AI Factory?
No. Its role in the EuroHPC programme: Antenna.
How many people and businesses in Belgium use AI?
42% of people aged 16–74 used generative AI tools in the three months before the 2025 survey (EU-27: 32.7%). 34.5% of businesses with 10 or more employees used at least one AI technology in 2025 (EU-27: 19.9%). Source: Eurostat.
How does Belgium compare with Ireland?
Big-user power: €0.101 vs Ireland's €0.165/kWh; grid carbon: 151 vs 263 gCO2e/kWh; data centres' share of electricity: 4% vs 23.2%; people using generative AI: 42% vs 44.9%.