Europe · country profile

Data centres and AI in France, ranked against Europe and the US

France ranks 3rd of 26 European countries for cheapest big-user power (€0.072/kWh, H1 2026); its weakest is 18th of 29 for highest share of people using generative AI (37.5%, 2025). Data centres use about 1% of its electricity (SDES, 2024). It hosts 1 EU AI Factory. Sources: Eurostat, Ember, EuroHPC, TOP500, Epoch AI; data as of 2026-10-12.

Updated 12 October 2026 · data build 2026-10-10 · how we know · corrections

Where France ranks among 31 European countries

Rank 1 = best on the measure's own terms (cheapest, lowest carbon, highest share, most). Each rank is among the European countries with a figure, so the "of" number differs. France is an EU member. Measured

3rd
of 26 · Big-user electricity price; 1 = cheapest
€0.072/kWh · H1 2026 · Eurostat nrg_pc_205
5th
of 27 · Wholesale power, last 12 months; 1 = cheapest
€77/MWh · 2025-10 to 2026-09 · Ember European wholesale prices
5th
of 31 · Grid carbon intensity; 1 = lowest carbon
41 g/kWh · 2025 · Ember yearly electricity data
6th
of 31 · Clean power share; 1 = highest share
94.9% · 2025 · Ember yearly electricity data
14th
of 15 · Data centres' share of electricity; 1 = highest share (exposure, not success)
1% · 2024 · SDES
16th
of 28 · Businesses using AI; 1 = highest share
18.2% · 2025 · Eurostat isoc_eb_ai
18th
of 29 · People using generative AI; 1 = highest share
37.5% · 2025 · Eurostat isoc_ai_iaiu
6th
of 24 · TOP500 supercomputing power; 1 = most
317.1 PF · 2026/06 · TOP500
3rd
of 16 · GPU-cluster compute (Epoch AI); 1 = most
18,403 H100e · 2025-07 · Epoch AI GPU clusters est.
4th
of 16 · EU AI Factories hosted; 1 = most (hosts only)
1 · 2024-12 to 2025-10 · EuroHPC JU
4th
of 27 · Share of EU server imports; 1 = largest share
5.4% · 2025-08 to 2026-07 · Eurostat Comext DS-045409
Download CSV ↓

Source: Eurostat nrg_pc_205 · Ember European wholesale prices (via StackPath eu_power_prices) · Ember yearly electricity data (CC BY 4.0) · SDES, French ministry statistics service · Eurostat isoc_eb_ai · Eurostat isoc_ai_iaiu · TOP500, June 2026 list (via eu_compute) · Epoch AI GPU clusters (CC BY 4.0, via global_context) · EuroHPC JU (via eu_ai_factories) · Eurostat Comext DS-045409 · EU EED data-centre dashboard (via eu_dc_capacity) · RTE (TSO) · as of 2026-10-12 · Compiled by StackPath

France against the EU-27 average and the US

Same measure, same source family, nearest year. A dash means no comparable figure, not zero. Measured

How to read this. The first column is France; under it, the gap to the EU-27 (percentage points for shares, a multiple for amounts). Per-person rows divide by World Bank population and are our arithmetic. The US power price is EIA's average for all industrial users, not the 150 GWh+ band Eurostat uses for Europe, so read it as indicative.
MeasureFranceEU-27USIreland
Big-user electricity price€0.072/kWh H1 202634% below EU€0.110/kWh H2 2025€0.076/kWh 2025€0.165/kWh H1 2026
Grid carbon intensity41 g/kWh 202581% below EU211 g/kWh 2025384 g/kWh 2025263 g/kWh 2025
Clean power share94.9% 2025+23.9 pts vs EU71% 202543% 202547.7% 2025
Data centres' share of electricity1% 2024−2 pts vs EU3% 20244.4% 202323.2% 2025
Businesses using AI18.2% 2025−1.7 pts vs EU19.9% 2025–19.6% 2025
People using generative AI37.5% 2025+4.8 pts vs EU32.7% 2025–44.9% 2025
Electricity use per person7 MWh 20251.1× EU6.2 MWh 202513.3 MWh 20256.8 MWh 2025
Supercomputing per million people4.6 PF 2026/0655% below EU10.2 PF 2026/0620.6 PF 2026/061.2 PF 2026/06
GPU compute per million people268 H100e 2025-071.5× EU177 H100e 2025-073,660 H100e 2025-07–

Source: Eurostat nrg_pc_205, isoc_eb_ai, isoc_ai_iaiu · Ember · EIA via eu_power_prices · LBNL via US DOE (US data-centre share) · Ember Grids for data centres (Europe share) · TOP500 · Epoch AI GPU clusters · World Bank population · as of 2026-10-12 · Compiled by StackPath

Our reading. Per person, France has 7.3% of the US level of GPU-cluster compute in Epoch AI's database and 22% of the US level of TOP500 supercomputing power. Epoch's database covers only part of the world's AI compute, and private clusters are under-recorded everywhere. Estimate

Power: 95% clean generation, €0.072/kWh for the largest users

Generation mix in 2025 (Ember); big-user prices exclude VAT (Eurostat band IG, 150 GWh a year or more). Measured

Wind8.8%
Solar5.6%
Hydro10.3%
Nuclear68.3%
Bioenergy1.8%
Other renewables (e.g. geothermal)0.1%
Gas3%
Coal0.3%
Other fossil1.8%

Share of generation by source, 2025. Darker bars are fossil. Demand 480.6 TWh; generation 574.4 TWh; net exports 93.8 TWh. Carbon intensity 41 gCO2e/kWh (EU-27: 211; US: 384).

€0.00€0.05€0.10€0.16€0.21H2 '22H1 '23H2 '23H1 '24H2 '24H1 '25H2 '25H1 '26
FranceEU-27 average

Big-user electricity price, € per kWh excluding VAT, by half-year (band IG). The EU-27 average is published later than country figures.

Wholesale power averaged €77/MWh over 2025-10 to 2026-09 (5th cheapest of 27). Taxes and levies (excluding VAT) were 1% of the big-user price in Eurostat's latest year-end comparison.

Source: Ember yearly electricity data (CC BY 4.0) · Eurostat nrg_pc_205 · Ember wholesale prices via eu_power_prices · Compiled by StackPath

Data centres: about 1% of France's electricity

Electricity share, capacity reported under the EU Energy Efficiency Directive (EED, the EU's data-centre reporting law), grid requests, restrictions and energy rules. Reported

  • Share of electricity: 1% in 2024 (share of national electricity consumption; metered consumption of the 471 sites using over 1 GWh a year (4.3 TWh); SDES puts all sites at 4.3-6 TWh, 1-1.5%; SDES, French ministry statistics service). Europe as a whole: about 3% (2024, Ember estimate); the US: 4.4% (2023, LBNL estimate).
  • Reported to the EU (EED): 631 MW of IT capacity at 152 sites for 2024, of an estimated 264 sites that should report; average PUE (power usage effectiveness: total power ÷ IT power) 1.49. Coverage is partial, so this is a floor.
  • Forecast 2030: 15–20 TWh (about 3% of demand), RTE Forecast
  • Forecast 2035: 23–28 TWh (about 4% of demand), RTE Forecast
  • Grid requests: 18.0 GW reserved (data centres; RTE (TSO)) (as at 2026-05; source).
OperatorStageMWAs at
RTE (TSO)reserved–2026-05
RTE (via trade press)requested28,600–

Grid-queue figures as published; stages (requested, reserved, contracted) are not comparable across operators.

Restrictions and connection rules (2)

National energy rules for data centres: reporting and incentives only

On top of national rules, 7 EU-level rules apply to data centres in every member state (EED reporting, the rating scheme and heat-reuse rules).

Source: SDES, French ministry statistics service · EU EED data-centre dashboard · RTE (TSO) · Compiled by StackPath

Cloud and capital: €5.2bn pledged by hyperscalers, €0bn with visible building

Hyperscaler pledges (a pledge is not a building), sovereign-cloud offers by jurisdiction, and neocloud (GPU cloud) sites. Reported

CompanyPledgeAnnouncedEvidence
Amazon (AWS)more than €1.2bn (Amazon France total)2024-05-13unknown
Microsoft€4bn2024-05-13unknown

2 current pledges worth €5.2bn; €0bn of it is stalled (paused, delayed or cancelled). Horizons and currencies differ.

Sovereign-cloud offers under France's jurisdiction (10)

Neocloud sites in France

CompanySiteMWStatus
Nebiusnear Lille240 (under construction)building (site town not named by Nebius)
NebiusParis (colocation)–First colocation, agreement Jul 2024
NebiusFrance, two new colocation sites (unnamed)–Land and capacity secured Feb 2026
FluidstackBosquel, Somme (1 GW AI campus)1,000 (cancelled)dropped Mar 2026; site now a SoftBank–Sesterce JV
Mistral Compute (Mistral AI)Bruyères-le-Châtel (Eclairion site)44 (under construction)Q2 2026 target passed; go-live not confirmed
SesterceBosquel, Somme (SoftBank JV)1,000 (planned)JV with SoftBank Group announced 1 Jun 2026
SesterceRovaltain (Valence area)40 (planned)Confirmed 40 MW cap
EvrocMougins, near Cannes96 (planned)2025 target passed; no go-live found

Neoclouds headquartered here: Mistral Compute (Mistral AI), Sesterce, Scaleway (Iliad), OVHcloud (GPU/AI part).

Source: StackPath eu_pledges (company announcements) · StackPath sovereign_cloud · StackPath eu_neoclouds (filings, company releases) · Compiled by StackPath

Compute: 1 EU AI Factory, 317.1 PF on the TOP500

Public AI Factories (EuroHPC), gigafactory bids, the TOP500 supercomputer list and Epoch AI's database of GPU clusters (in H100-equivalents: compute expressed as a number of Nvidia H100 chips). Measured

  • EuroHPC role: AI Factory host.
  • TOP500 (2026/06): 21 systems, 317.1 PF combined (1.69% of the list); the largest is CEA-HE at Commissariat a l'Energie Atomique (CEA), ranked 29th in the world.
  • GPU clusters (Epoch AI): 18,403 H100e, 1.17% of the world total in Epoch's database (clusters operational by 2025-07). The US holds 1,251,044 H100e in the same data. Estimate
AI FactoryCityGPUsStatus
AI2F (AI Factory France)Bruyeres-le-Chatel (CEA TGCC)not statedcontracted

AI gigafactory bids based here

  • AION (Scaleway (iliad Group), Ardian, Artefact, Bull, Capgemini, EDF, Orange), 200 MW reported; bid announced
  • AETHER (2CRSi, Dassault Systemes (OUTSCALE), SiPearl, Axelera AI, Viridien, Electricite de Strasbourg, Equans), 42 MW reported; bid announced

The EU gigafactory tender closes 3 Dec 2026; bidders are not published, so this lists public announcements only.

Large AI clusters announced or built

ClusterMWGPUsStatus
Nebius AI factory near Lille240–under construction
Mistral Compute, Bruyères-le-Châtel4413,800under construction
Campus AI Fouju (MGX-Bpifrance-Mistral-Nvidia)1,400–under construction
Fluidstack France 1 GW AI supercomputer1,000–cancelled
Brookfield Cambrai AI campus1,000–announced
evroc Mougins9650,000announced
Cerebras Europe expansion200–announced
Alice Recoque24–under construction

Source: EuroHPC JU via eu_ai_factories · TOP500 June 2026 · Epoch AI (CC BY 4.0) · StackPath eu_compute (announced clusters) · Compiled by StackPath

Chips: €2,900m of Chips Act aid approved for 1 project

Fabs and pilot lines under the EU Chips Act (aid approved is not production), and AI-chip startups headquartered here. Reported

ProjectCompanyAid €mStatus
Crolles 300mm FD-SOI fabSTMicroelectronics and GlobalFoundries2,900paused
FAMES pilot lineCEA-Leti (Chips JU)–operating

AI-chip startups

CompanyCityFunding $mStatus
SiPearlMaisons-Laffitte140sampling
VSORAParis50taped out
AragoParis26pre-silicon

Source: StackPath eu_chips (Commission decisions, company releases) · StackPath eu_ai_chip_startups · Compiled by StackPath

AI use: 38% of people used generative AI in 2025 (EU: 33%)

Eurostat's surveys of businesses (10+ employees, any AI technology) and of people aged 16–74 (generative AI tools in the last three months), plus AI labs headquartered here. Measured

0%5%11%16%21%2021202320242025
FranceEU-27

Share of businesses with 10 or more employees using at least one AI technology (Eurostat isoc_eb_ai; survey years only). France: 18.2% in 2025, 16th of 28.

Any use: France37.5%
Any use: EU-2732.7%
For work: France18.4%
For work: EU-2715.4%
Private use: France27.7%
Private use: EU-2725.5%
Formal education: France11%
Formal education: EU-279.3%

Share of people aged 16–74 who used generative AI tools in the three months before the 2025 survey. There is no comparable official US series.

AI labs headquartered in France

LabTypeFunding $bnValuation $bn
Mistral AIEuropean lab6.4924
H CompanyEuropean lab0.22–
Meta FAIR ParisUS-owned lab in Europe––

Equity funding as tracked by Epoch AI and company releases; US-owned labs in Europe are listed but are not European capital.

Source: Eurostat isoc_eb_ai · Eurostat isoc_ai_iaiu · StackPath eu_ai_labs (Epoch AI, company releases) · Compiled by StackPath

Servers: 5.4% of the EU's server imports from outside the EU land in France

Customs flows (Eurostat Comext), not machines installed: ports of entry such as the Netherlands count goods that move on. Measured

  • Servers (HS 847150) from outside the EU, 2025-08 to 2026-07: €1.6bn, 4th of 27 member states.
  • All compute kit (servers, parts, network gear, chips) from outside the EU, last 12 months: €5.83bn (5.6% of the EU total, rank 6); servers up 367% on the previous 12 months.

Source: Eurostat Comext DS-045409 · StackPath eu_hardware_imports · Compiled by StackPath

Deeper pages and other countries

Each layer has its own page with the full European table.

All 31 country profiles

Our reading. Against Ireland, France pays 56% less for big-user power and runs a cleaner grid (41 vs 263 gCO2e/kWh). Where data centres and AI compute go also depends on grid access, land, fibre, tax and customers, which these measures do not capture. Our reading

Questions people ask

How much do large electricity users pay in France?
Eurostat's average for users of 150 GWh or more a year in France was €0.072/kWh in H1 2026, excluding VAT: 3rd cheapest of 26 European countries with a figure. The EU-27 average was €0.110 (H2 2025); US industrial users paid about €0.076 in 2025 (EIA, all industrial users).
How much electricity do data centres use in France?
About 1% in 2024 (SDES, French ministry statistics service). Europe as a whole: about 3% (Ember, 2024); the US: 4.4% (LBNL, 2023).
Does France host an EU AI Factory?
Yes: AI2F (AI Factory France) (EuroHPC JU selections, Dec 2024 to Oct 2025).
How many people and businesses in France use AI?
37.5% of people aged 16–74 used generative AI tools in the three months before the 2025 survey (EU-27: 32.7%). 18.2% of businesses with 10 or more employees used at least one AI technology in 2025 (EU-27: 19.9%). Source: Eurostat.
How does France compare with Ireland?
Big-user power: €0.072 vs Ireland's €0.165/kWh; grid carbon: 41 vs 263 gCO2e/kWh; data centres' share of electricity: 1% vs 23.2%; people using generative AI: 37.5% vs 44.9%.